1 Smart Metering Portfolio DCC Day 1 Project Smart Metering Portfolio Focus Group Project Update Thursday 06 th June 2013.

Similar presentations


Presentation on theme: "1 Smart Metering Portfolio DCC Day 1 Project Smart Metering Portfolio Focus Group Project Update Thursday 06 th June 2013."— Presentation transcript:

1 1 Smart Metering Portfolio DCC Day 1 Project Smart Metering Portfolio Focus Group Project Update Thursday 06 th June 2013

2 2 Agenda Action Review Implications of the delay to Mass smart meter roll-out Xoserve Overview Shippers Overview Overview of Solution Options Shipper Design to meet UNC Modification 0430 Requirements Project Smart Metering Portfolio Focus Group to discuss & advise UKLC on the implementation date of UNC Mod 0430 Agree how UKL Comm members should be engaged through the Project Smart Metering Portfolio Focus Group Overview of next steps on Shipper Design & agree engagement at SPAA & UK Link iGT Update

3 3 Action Review Workshop actions:

4 4 Background & Purpose On the 10 th May 13 DECC announced the delay of mass smart meter roll-out by one year. Industry Trials are to commence April 2015 (assumption) and mass smart meter rollout to start Autumn 2015. Information gained from DECC indicated that the delay is to ensure that the successful DSP/CSP bidder and the Suppliers have sufficient time to prepare their systems and processes. To date we have been working towards dates of April 2014 for Industry Trials and October 2014 for the start of mass smart meter rollout. Agreed that Shipper Design will be progressed in advance of the DCA delivery to keep momentum gained in the project so far.

5 5 Background & Purpose What does this change mean for our current Smart Metering Portfolio? Foundation delivery is not impacted but becomes more important DCC Day 1 is impacted Develop and agree approach with stakeholders via the Project Smart Metering Portfolio Focus group for the preferred approach

6 6 Stakeholder Responses Xoserve have considered the options internally. Xoserve have discussed the way forward with a number of members of Project Smart Metering Portfolio Focus group. Consensus seems to be that development should proceed to the current plan. The actual date for deployment will be dictated by the outcome of the Detailed Cost Assessment.

7 7 Xoserve View 1.Phased delivery approach for MOD430 and iGT MOD047 as per current plans. Delivery of DSP gateway functionality in line with the availability of detailed requirements once the successful bidder has been selected by DECC.

8 8 Next Steps Seek Project Smart Metering Portfolio Focus Group Stakeholder support for our approach Review the plan with internal & external Stakeholders Delivery of DCA to GT’s Plan project delivery and engagement with respective parties (eg UKLC & SPAA)

9 9 Solution Options Overview See Attached File

10 10 Solution Options Overview - Impacted File Types – 1 Outgoing Existing File Change SummaryDCC Day 1 Data Items NMR Add new data items to the new record type under RT_S64_Offer_Details -> RT_S75_Meter_Point 13. SMS Operating Entity ID 14. SMS Operating Entity EFD 15.DCC Service Flag 16. DCC Service Flag EFD 17. IHD Install Status 18. First SMETS Installation Date (derived) 19. UPRN CFR (Confirmation Acceptance) Add new data items to the new record type under RT_S07_Accepted_Confirmation -> RT_S75_Meter_Point CFR (Withdrawal Notification) Add new items to the new record type under RT_S10_SP_Withdrawal_Notice -> RT_S77_Withdrawal_Meter_Point TRF (Transfer of Ownership) Add new data items to the new record type under RT_S15_Transfer_of_Ownership -> RT_S75_Meter_Point TRF (Ceased Responsibility Notification) Add data items to the new record type under RT_S88_Ceased_Responsability_Notice -> RT_K13_MPO_CEASE_OWN_DETS MRIAdd data items to the new record type under RT_U06_Meter_Read_Instructions PACAdd data items to the new record type under RT_U06_Meter_Read_Instructions

11 11 Solution Options Overview - Impacted File Types – 2 Incoming Existing File Change Summary DCC Day 1 Data Items ONJOB IHD Install Status to DATASET_GROUP_MTPNT Unique Property Reference Number within DATASET_GROUP_ADDRS to capture UPRN 17. IHD Install Status 19. UPRN ONUPDIHD Install Status to DATASET_GROUP_MTPNT GEA MAM change process SUN process including Supplier EFD SUN (Supplier Update Notification) Existing SUN file will be decommissioned

12 12 Shipper Design to meet UNC MOD 0430 Requirements Agree how UKL Comm members should be engaged through Project Smart Metering Portfolio Focus Group Project Smart Metering Portfolio Focus Group to discuss & advise on the implementation date of UNC MOD 0430 Overview of next steps on Shipper Design & agree engagement at SPAA & UK Link groups

13 13 iGT’s Update Business Requirements Document Update Update funding discussions Communications method updates Agree any next steps/decisions to make


Download ppt "1 Smart Metering Portfolio DCC Day 1 Project Smart Metering Portfolio Focus Group Project Update Thursday 06 th June 2013."