Presentation is loading. Please wait.

Presentation is loading. Please wait.

North Eastham Wind Feasibility Study Results Brian Eastman Eastham Energy Committee Kristen Burke Massachusetts Technology Collaborative Ric O’Connell.

Similar presentations


Presentation on theme: "North Eastham Wind Feasibility Study Results Brian Eastman Eastham Energy Committee Kristen Burke Massachusetts Technology Collaborative Ric O’Connell."— Presentation transcript:

1 North Eastham Wind Feasibility Study Results Brian Eastman Eastham Energy Committee Kristen Burke Massachusetts Technology Collaborative Ric O’Connell Black & Veatch June 19, 2006

2 2 Energy Committee Charge, Recommendation & Request Charge #6: Set up process to identify the best deals and reliable companies for the implementation of a wind turbine in the Town of Eastham. Recommendation: From the Feasibility Report, we recommend Option 4: Up to four Turbines at the North Eastham Site. Recommendation: Issue a Request for Proposals from private entities interested in developing and owning a project constituting up to four turbines in North Eastham Request: –Authorization to proceed in issuing an RFP with necessary local officials and departments –Authorization to explore and obtain necessary local and state permits

3 3 Topics Background and context North Eastham feasibility study results Project ownership and finance considerations Next steps

4 4 Massachusetts Technology Collaborative Renewable Energy Trust Created in 1998 as part of utility deregulation Funded by public benefits charge paid by investor- owned utility customers Massachusetts Technology Collaborative is manager, as part of “innovation economy” The Trust’s mission: –Increase the supply of and demand for energy from clean sources –Promote the development of a vibrant Massachusetts renewable energy industry

5 5 MTC Community Wind Collaborative Premise –Local project sponsorship creates a sense of ownership –We can increase comfort levels by beginning with small projects (i.e. few turbines) –Early projects will build public support for renewable energy MTC Role: provide technical, analytical and financial support to communities

6 6 Roles Community Sponsor a project on public land and build local support Manage local decision process Support project permitting and approvals process Private Sector Turbine supply & installation Finance, own, and manage the project Asset management services Operation and maintenance services

7 7 Community Wind Process 1.Project Conception / Identify Potential Sites 2.Wind Resource Monitoring & Analysis 3.Feasibility Analysis 4.Public Outreach, Education & Municipal decision __________________________________________________ 5.Business Planning 6.Construction and Interconnection 7.Operation and Maintenance MTC incurs cost for phases 1-4 for communities who qualify in an effort to support the decision making process. MTC is committed to helping support FEASIBLE projects through the later stages

8 8 Eastham Process Summary Wind Measurement Spring 2003-2004 Initiate CWC process with MTC Spring 2004 Black and Veatch assigned site screening analysis Summer 2005 Site Screening Analysis Fall 2005 –3 locations (municipal complex, DPW, North Eastham) Energy Committee requested North Eastham for Feasibility Analysis. Completed March 2006

9 9 Feasibility Study Results North Eastham location –Adjacent to the Cape Cod Rail Trail –Two municipal parcels with a gravel pit in between just West of Cape Cod National Seashore –Can accommodate up to 4 turbines (2 on each parcel) –Environmental studies necessary –Early Interconnection study necessary –Verification of wind data is suggested

10 10 North Eastham Location

11 11 Photo Simulation:

12 12 Opportunity for financial benefit: The final economic value of any project to the Town is subject to negotiation with the project’s developer/owner and is influenced by: 1.Wind resource 2.Total # of turbines installed 3.Total installed cost 4.Power and REC selling price

13 13 Revenue Options Lease + Taxes + Revenue Sharing +Lease for 20 Years: Flat rate +Taxes decline over time: Variable +Revenue Sharing: Variable PILOT + Revenue Sharing +Payment in Lieu of Taxes: Flat Rate +Revenue Sharing: Variable

14 14 Project Uncertainty; all impact financials Turbine price & availability Future price of energy; Power Purchase Agreement REC price risk (MTC mitigates to some degree) Wind resource Permitting risk

15 15 Bottom Line Increasing Electric Energy Costs Potential Revenue source Ability to offset much of Eastham’s Electric Energy Costs Positive Environmental Benefits

16 16 Key components to explore Interconnection LV Distribution or HV Transmission Interconnection study is necessary earlier Land Use Regulations Water Resources Protection District National Seashore Restrictions Wind Analysis SODAR can verify shear but needs to be placed far from homes. Would require clearing New Meteorological tower could be installed Environmental Assessments National Seashore Mass Audubon Eastham Conservation Foundation Education Bikeways Committee Citizens

17 17 Next Steps Town indicates probable project –Recommendation from the Board of Selectmen Authorization for Energy Committee to proceed in issuing an RFP with necessary local officials and departments Authorization for Energy Committee to explore and obtain necessary local and state permits Additional MTC services to support process –Additional Meteorological Tower –Utility Interconnect Discussions –Phase 1 Avian Risk Assessment –Participate in joint CCCC and CCNS discussions –Provide assistance in further permitting discussions/mapping

18 18 Additional Information... Kristen Burke, Wind Siting and Community Planning Manager Massachusetts Technology Collaborative Renewable Energy Trust 75 North Drive Westborough, MA 01581 508-870-0312 x1480 burke@masstech.org


Download ppt "North Eastham Wind Feasibility Study Results Brian Eastman Eastham Energy Committee Kristen Burke Massachusetts Technology Collaborative Ric O’Connell."

Similar presentations


Ads by Google