Download presentation
1
NSTX-U Project Overview Ron Strykowsky
Supported by Project Overview Coll of Wm & Mary Columbia U CompX General Atomics FIU INL Johns Hopkins U LANL LLNL Lodestar MIT Lehigh U Nova Photonics Old Dominion ORNL PPPL Princeton U Purdue U SNL Think Tank, Inc. UC Davis UC Irvine UCLA UCSD U Colorado U Illinois U Maryland U Rochester U Tennessee U Tulsa U Washington U Wisconsin X Science LLC Culham Sci Ctr York U Chubu U Fukui U Hiroshima U Hyogo U Kyoto U Kyushu U Kyushu Tokai U NIFS Niigata U U Tokyo JAEA Inst for Nucl Res, Kiev Ioffe Inst TRINITI Chonbuk Natl U NFRI KAIST POSTECH Seoul Natl U ASIPP CIEMAT FOM Inst DIFFER ENEA, Frascati CEA, Cadarache IPP, Jülich IPP, Garching ASCR, Czech Rep Ron Strykowsky Project Manager for Construction Project Princeton Plasma Physics Laboratory Readiness for Operations Review LSB B318 December 9-11, 2014
2
Content Scope Execution Plan Deliverables Summary
3
NSTXU Device The NSTX device is exploring a novel structure for the magnetic field used to contain the hot ionized gas, called “plasma”, needed to tap this source of fusion energy. Mission of the NSTX is to establish the potential of the ST configuration as a means of achieving practical fusion energy. Not a steady state machine. Pulse length < 6 sec. Design rep rate <40 minute
4
Technical Performance Baseline Parameters (defined in section 2. 2
Technical Performance Baseline Parameters (defined in section of the Project Execution Plan (PEP)) Technical Performance Baseline Parameters To meet the mission need objective, the existing NSTX machine at PPPL will be upgraded to permit operation at the following increased levels; • Toroidal field from 0.5 tesla to 1.0 tesla; • Pulse length from ~1.0 second to 5.0 seconds; • Plasma current from 1MA to 2MA; • Neutral beam heating from 5-7MW to 10-14MW In PEP Design basis Day 1 hardware capable (design and tested) Not Day 1 planned achievement (phased in during 2-3 years)
5
NSTX Upgrade Deliverables
Double field and current Center Stack (CS) Upgrade. Design, build and install new CS assembly including; a new toroidal field (TF) hub assembly, new TF flag assemblies, new ceramic break, new inner TF bundle, new ohmic heating coil, new plasma facing component (PFC) tiles, new poloidal field (PF) 1a, b & c coils. Power, controls, water, services 2) Double neutral beam power & more tangential injection 2nd Neutral Beam-line (NBL). Decontaminate and prepare a TFTR neutral beam-line (NBL) for installation on NSTX. Evaluate and refurbish internal components as necessary (cryogenic panels, beam dumps, bending magnets, beam scrapers, calorimeter, etc.). Relocate the NBL and Provide a second set of beam-line services (e.g., power, water, vacuum, cryogenics, etc.). Larry Dudek will discuss in detail Tim Stevenson to discuss in detail In PEP This represents a major modification to an existing fusion device
6
CD-4 milestone completion criteria defined in section 2. 2
CD-4 milestone completion criteria defined in section of the Project Execution Plan (PEP) Demonstrated Performance The major milestone marking the transition from a fabrication project to an operating facility is the first plasma milestone (CD-4). First plasma is defined as an ohmically heated discharge > 50 kA at a toroidal magnetic field of > 1 kG. The operations phase will resume upon completion of the first plasma milestone. The installation of the second neutral beam on NSTX shall be considered complete at the stage where each item below has been demonstrated: Beamline water, vacuum, cryogenics, and feedstock gas services have been attached to the beamline; A Torus Isolation Valve and duct interconnects the NSTX vacuum vessel and the neutral beamline; Local Control Centers have been powered on to monitor power supply status, and; Project will be verified as complete when a 40,000 electron-volt beam has been produced and injected into the armor for .050 seconds In PEP
7
Project Organized to Execute Mission
Sources & Controls M. Cropper NB Relocation/ Services N. Atnafu NBI Armor K. Tresemer NBI Power R. Ramakrishnan NTC Equipment Relocation E. Perry Control Sys Data Acquisition P.Sichta Auxiliary Systems W. Blanchard Construction E.Perry Integrated Systems Testing/Startup C.Gentile Centerstack Design & Procurement S.Raftopoulos NSTX Upgrade Project Manager R. Strykowsky Deputy and Construction Manager Project Controls S. Langish NSTX Centerstack Manager L. Dudek NSTX Neutral Beam Manager T. Stevenson Engineering Support Sys Analysis: P. Titus Sys Integr: C. Neumeyer Associate Director M. Williams Structures & Supports M. Smith Electrical Systems Diagnostics R.Kaita Centerstack PFC VPS/NB/TVPS Duct Most staff will transition over to machine operations
8
Project Scope WBS Breakdown
Larry Dudek will discuss scope in detail Tim Stevenson to discuss scope in detail
9
Project Scope WBS Breakdown (continued)
10
Design, Fabrication, Assembly, & Installation followed a disciplined approach
Physics Motivation and needs vetted in mission need statement General Requirement Documents (GRD's) prepared. Plasma parameters (equilibria) defined for 96 initial operational scenarios Detail design parameters in the Design Point Spreadsheet Design ENG-032 (work planning form), ENG-033 (design reviews),ENG-010 (change control) Global model analysis and calculations ENG-033 (calculation form) Procurement/ fabrication packages established ENG-006 (Specifications & statements of work) Receipt inspections, testing, pre-assembly fit-ups QA-004 (PPPL Site Inspection Program) (Control of Non-conformances) Installation Engineering Work Packages (EWP’s) ESH-004 (Job Hazard Analysis) ENG-30 (procedures), 055 (Conduct of Operations) Testing ENG-030 (Preoperational test procedures) Updated Failure Mode and Effects Analysis ENG-008 (FMEA ) Updated Safety Assessment Document (SAD) Lessons learned from previous experiences design reviews & external reviewers. Chits from design reviews independently tracked Risk registry maintained that identified mitigation plans that were incorporated into the design where applicable Stefan Gerhardt will elaborate Judy Malsbury will elaborate Erik Perry will elaborate Jerry Levine will elaborate
11
NSTXU Design, Fabrication and Assembly vetted by a rigorous review process
Multiple design & project level reviews (per eng-033). Chits documented and independently tracked by QA (402 total 94% closed). Remaining 6% to be closed prior to startup. Will be confirmed by the Activity Certification Committee (ACC). 69 individual external reviewers from 22 institutions QA integral part of the design, procurement, fabrication, and inspection process. Charlie Gentile will discuss the ACC process Judy Malsbury will describe QA/QC oversight.
12
Larry Dudek will discuss center stack and machine scope in detail
Major Machine Components Description Outer TF coils New NB port PF Coils Larry Dudek will discuss center stack and machine scope in detail
13
Center Stack - Core of machine
Simpler Inner TF design (single layer of TF conductors) Improved Joint Design Reinforced Coil Supports OH coil wound on TF Existing outer TF WITH water cooling Flex joint design critical required R&D. OH winding on TF required R&D. Inner TF epoxy required R&D Much R&D was required to vet critical design details
14
Centerstack Upgrade Scope
Bolted joints located at further radius hence lower joint current density and lower magnetic field at joint Original CS Two conductors types and two layers TF Bundle contains 36 identical conductors with one-layer joint design with non zinc-chloride flux Increased contact pressure even with higher loads.
15
Assembly of centerstack
Fabrication of center stack performed by PPPL with components supplied by industry Assembly four quadrants of conductors Assembling first of 4 quadrants of conductors Final VPI of OH/TF bundle Winding of OH conductor around TF bundle Assembly by PPPL conductor fab by Major Tool & EWI VPI and Testing of the OH/TF magnet successful…however
16
OH Aquapour Removal Issue
100 mill Aquapour gap TF Coil OH During VPI, epoxy saturated the Aquapour turning it into waster resistant substance. • No solution for removing the remaining Aquapour- epoxy mixed material. Decision to leave Aquapour in place. Independent peer review conducted to determine mitigation plan. Minimal impact on Operations Stefan Gerhardt will discuss operations considerations in detail
17
OH/TF center stack bundle assembly completed
Final sanding and clear coat applied. Outer ground plane applied.
18
Plasma Facing Components (PFC’s) installed on center stack casing
October 2014 First row diverter tiles pre-fit then removed to prevent damage PFC tiles installed! PFC tiles being installed on the CS Casing
19
Casing with tiles installed over the OH/TF bundle
20
Center stack assembly installed into the NSTX Machine
21
Second Neutral Beam Scope
A TFTR Neutral Beamline was Decontaminated and relocated to the NSTX Test Cell NSTX test cell TFTR test cell Tim Stevenson will discuss Neutral Beam scope in detail
22
Second Neutral Beam - Scope (continued)
NBL2 Duct w/ new TIV Torus Vessel Pump System Duct Port Extension Bay J-K Cap (Required NSTX Vessel Modification) NBI Armor addition
23
Second Neutral Beam Relocated
Beam box = 40 tons Lid = 14 tons Began work February 2009 30,000 hours (>17 person years) for decontamination, refurbishment, relocation design
24
Neutral beam component installation
Neutral Beam & TIV valve Vacuum Vessel Bay J/K rectangular port Neutral Beam connecting duct assembly being lowered into position Round bellows and duct Turbo molecular vacuum Pumps Rectangular Bellows
25
NB component armor installed
26
Neutral Beam High Voltage Enclosures & Transmission Lines Installed
27
Construction Coordination
Use of a Work Control Center for all work in the test cell. Project in-charge during assembly and testing (Erik Perry). Handoff to Operations (Al vonHalle) for start of ISTP System pre-operational tests conducted as part of the WBS scope. Work Control Center reviews all Engineering Work Packages for the field Daily Plan-of-the-Day meetings to coordinate activities between crews and fine tune technician assignments Erik Perry to discuss in detail
28
Current machine status
Neutral Beam (NB) #1 NB #1 duct in place. Existing RF pipes New Centerstack Machine Ready for pump down Neutral Beam (NB) #2 Neutral Beam Duct/TVPS High Voltage Enclosures (HVE) New Platforms
29
Summary Technical Performance Baseline Parameters as documented in the PEP and GRD’s were the basis for the project design. Execution of project scope followed a disciplined and auditable process following mature PPPL Procedures. Startup of NSTX (OP-NSTX-02) and start of ISTP (OP-NSTX – ISTP-01) marks the turnover from construction to operations. Conclusion of the construction project will be achieved as defined in the PEP Demonstrated Performance. Construction is almost complete. We will be ready to operate
30
Backup slides
31
Analysis & Value Engineering – An Iterative process
96 Plasma Equilibria (Physics) Design Point SS (Magnetic loads) Analysis (ANSYS, Workbench) Design (CAD Models) Field Assembly (Field Experience) TF Inner Leg and Flex Joint Qualification Concept, Initial Analysis TF Inner Joint Stress, Contact Pressures TF Current Diffusion TF Torsional Shear TF Stress, Insulation Tension Stress TF Tooth Interface w/Umbrella Structure Vessel and Umbrella Structure Original, Early Upgrade Full 360 degree Model from Pro E, Reinforcements TF Loading on Alum Blocks, hang, Vessel Lid and Bottom Cover Connection, Central Column to Umbrella Vacuum loading with neutral beam ports Pushing the structural limits of the existing machine required significant analytical modeling in concert with Physics, engineering and field input to optimize the design. Additional inspections and instrumentation requirements added (Larry Dudek, Steve Raftopoulos to discuss) Outer TF Leg Analysis Torsional OOP Loads Stress, Insulation Tension Stress Outer Leg Support Other Center Stack Plasma Facing Components Inner PF Supports Outer PF Supports Lower Support Pedestal HHFW Antenna Analyses Disruption OPERA Axisymmetric Vessel and Passive Plates, Early Upgraded Loads +DLF Detailed Vessel and Passive Plates EMAG Transient Dynamic Analysis Center Stack Casing with Halo Currents
32
Princeton Plasma Physics Laboratory-NSTXU
Field Coil Power Conversion Bldg Motor Generators RF Transmission lines Magnet Power Rectifiers Neutral Beam Power Conversion Bldg 138kV electric transmission line to PPPL NSTXU Test Cell Centerstack Fabrication area Mockup Bldg D-Site Tunnel from NSTXU control room to D-Site C-Site RF Bldg NSTXU Control Room (basement level) You are here
33
Requirements documented in 2 GRD’s
NSTX CENTER STACK UPGRADE GENERAL REQUIREMENTS DOCUMENT NSTX_CSU-RQMTS-GRD Revision 5 June 14, 2012 This General Requirements Document (GRD) defines: The Machine Parameters (Table 1-1) The overall engineering requirements for the Center Stack Upgrade as well those specific to each major element of the Work Breakdown Structure (WBS) (Table 1-2) The Machine Planned Pulse duty (Table 2-4) Performance and plasma shape including disruption modes
34
Design Point Spreadsheets
Physics Radial Build Center Stack Dimensions TF Coil OH Coil Inner PF Coils PF/OH Coil Summary Power Systems Coil Circuit Summary Coil Insulation Summary PF/OH Coil Forces Coil Combination Forces and Moments PFC Heat Loads TF Current Waveform Force Influence Matricies Circuit Impedances Pulse Spectrum Design Point Spreadsheets Example for OH Coil Provides detail design parameters that need to be met to satisfy the GRD and 96 plasma equilibria. Larry Dudek to discuss in detail
35
Calculations & analysis form the basis of our design
67 calculations independently checked Example for OH Coil Larry Dudek to discuss in detail
36
Reinforcement of the TF outer leg support structure
Extensive analysis and reinforcements required for magnet supports and vacuum Vessel Reinforcement of the TF outer leg support structure
37
Design/Build Process we followed
Concept through reality roadmap
38
Initial experimental modes defined
Defined experimental modes yields base case 96 plasma equilibria that quantified the operating parameters for each coil Stefan Gerhardt to discuss in detail
39
National Spherical Torus Experiment – NSTX
Umbrella Structure Neutral Beam #1 operating since Sept 2000 TF Coil Plasma PF Coil Time consuming low technical risk. Center-stack Assy Vacuum Vessel NSTX Device operating since February 1999 CS Pedestal
40
Remaining Construction Work in NSTX Test Cell
Pumpdown - November Leak check - December Install bus inside umbrella and back to racks - November Install new TF lead extensions - January Install TF flex bus - January Install new umbrella lids - February Install umbrella lid support rings - February Bakeout - February ISTP - March
41
Engineering Design Implementation
Work Planning Work Planning Form ENG-032) Calculation Form (ENG-033) Engineering / Software Change Notice (ENG-010) Design Review Doc (ENG-033) Chit form (ENG-033) Procedure Cover Sheet (ENG-030) Procedure review and Approval Matrix Procedure Revision Sheet Record of Training Job Hazard Analysis (ESH-004) Design Verification Drawing/Software Control Installation/Operations
42
NSTX History OP-NSTX-02 “Startup of NSTX” executed for each start-up
NSTX First Plasma February 1999 NSTXU First Plasma March 2015 NSTX History 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 NSTX Design & Construction Operations Neutral Build New NSTXU Fabrication and Beam #1 Inner TF Design Assembly Bundle RWM Coils, PF1A Upgr Litium Evaporator Diagnostic Upgrades = Operations HHFW Antenna Upgrade = Outage HHFW & Diag Upgrades Enhanced LLD OP-NSTX-02 “Startup of NSTX” executed for each start-up (13 times)
43
Reconciliation between Demonstrated Performance
Deliverables and GRD Baseline Parameters NSTX (Max.) FY 2015 NSTX-U Operations FY 2016 NSTX-U FY 2017 NSTX-U Ultimate Goal IP [MA] 1.2 ~1.6 2.0 BT [T] 0.55 ~0.8 1.0 Allowed TF I2t [MA2s] 7.3 80 120 160 IP Flat-Top at max. allowed I2t, IP, and BT [s] ~0.4 ~3.5 ~3 5 1st year goal: operating points with forces up to ½ the way between NSTX and NSTX-U, ½ the design-point heating of any coil Will permit up to ~5 second operation at BT~0.65 2nd year goal: Full field and current, but still limiting the coil heating Will revisit year 2 parameters once year 1 data has been accumulated 3rd year goal: Full capability Stefan Gerhardt will discuss in detail
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.