Southern Delivery System NSPE-Colorado State Meeting February 19, 2010
2
2 Regional project –Colorado Springs –Fountain –Security –Pueblo West Our future depends on it –Growing community –Drought protection –System Reliability –Long-term Water Supply SDS: Our Future Depends on It 2
3
Colorado Springs Water System 3
4
4 SDS Components 4 62 miles underground pipeline 3 pump stations Water treatment plant Capacity = 78 mgd Firm yield = 42,400 acft/yr Primary source = Reuse by exchange of Fry-Ark Project water FOUNTAIN SECURITY
5
5 5 SDS Today SDS Milestones Record of Decision Pueblo County 1041 Permit Colorado Springs Utilities Board Approval Fountain Creek District Board approval 5
6
El Paso County permit Army Corps 404 permit State 401 certification Fish & Wildlife Mitigation Plan Reclamation contracts Next Steps Approvals Underway 6
7
2009201020112012201320142015201620172018 1041 Permit Condition ENGINEERING LAND ACQUISITION CONSTRUCTION START-UP SDS IN SERVICE 2016 2016 Implementation Schedule Record of Decision Pueblo County 1041 Permit MAJOR PERMITS 7
8
8 SDS Economic Benefits: Phase 1 Construction Total Construction Costs$550 million – Portion spent on construction labor$160 million Average employment380 workers Peak employment700 workers Regional Economic Benefits Estimated workforce by year: 2010 – 1702013 – 6302015 – 510 2011 – 2902014 – 7002016 – 80 2012 – 290 We expect about 50 to 75 percent of the labor force to come from the region.
9
9 Procurement outreach Contractor workshops beginning this year Register at csu.org Construction/Contracting
10
10 –Project eNewsletter –Email us: sdsinfo@csu.org –www.sdswater.org 10 Follow our progress