4th Phase : 4th Phase : CONTROL Why is control necessary? Because: People make mistakes External factors can have impact on the project Requirements, deadlines can change Budget can be reduced Project priority can be changed
2
Purpose of Control To track progress To detect variance from plan To take corrective actions
3
Aspects of Control Time plan (deadlines) Quality control (quality standards) Utilisation of resources, costs
4
Quality Control Built in the whole process, measurable Quality management: Operational metods and practices Quality standards for deliverables Norms for monitoring, evaluation, control Mmilestones Involvement of client / end-user
5
Status Report To monitor regularly work progress Status of WP / Tasks Variance (Plan - Current status): IF + OK IF - Behind schedule (Critical Path?) Costs Layout: Work Completed / Started / Plan for next 6 months
6
Review Which deliverables (reports, SW etc.) will be reviewed (External / Internal)? Who is responsible? Where will be last versions of deliverables stored? Who will review the project and when (how often)
7
Forms of review Site visits Working meetings: Control of work progress Inform all involved about the status quo Inform involved about problems encountered Costs monitoring Co-ordination of work Plan for the next period of time
8
Gantt chart - Plan
9
Gantt chart – status report
10
Assessment of change How the variance affects other project tasks? What has to be done to solve the problem and to bring the project back to to the track Why the variance has happened? What has to be done to prevent similar events happen in the future?
11
Solving problems A creative solution (e.g. use of a new technology) Use of reserves (slack time, non critical activities) Use of additional resources (increased costs) Postpone deadline (approval of sponsor) Change scope of project (will be delivered less)
12
TEAM ASSIGNMENT 3 Develop a Gantt chart of your Project.
13
4th Phase: 4th Phase: PROJECT CONTROL SUMMARY Purpose of control Aspects of Control Quality Control Status report Review Gantt diagram Change evaluation Solving problems