Download presentation
Presentation is loading. Please wait.
1
Excavation Below Subgrade (EBS)
Topic G Topic G
2
EBS QC/QV personnel do not determine/direct EBS operations.
Engineer ultimately determines the need for EBS. Topic G
3
EBS Remove objectionable materials.
Resulting excavation is then back filled with soil. Figure 3.1 Topic G
4
Figure 3.1: Intercepting Embankment
Topic G
5
Predicting EBS Areas Groundwater levels = 3 feet or less.
Silty “B” horizon. Topsoil depths exceed 12 inches. Moisture levels above plastic limit. Depositional characteristics (alluvial, lacustrine). Topic G
6
Predicting EBS Areas Roadway constructed prior to 1940.
Extensive filling. Roadway is distressed. Highly variable soil conditions exist. Subgrade is within 2 ft. of original surface. Topic G
7
Figure 3.2: Detail of EBS Topic G
8
EBS Remove uncertain soil. Note the diagonal rutting= unstable silt.
In addition to excavation. Topic G
9
Figure 3.3: EBS Topic G
10
Topic I
11
Rutting of Unstable Material
Transition from cut to fill are important. Inspect before the subbase or base. Rutting of unstable material shown. Topic G
12
Figure 3.4: Rutting of Unstable Material
Topic G
13
EBS Yielding water-bearing silt. Rock truck-hauling material away.
Backhoe-Loading EBS material out. Dozer-Pushing material to backhoe. Topic G
14
Figure 3.5: EBS Topic G
15
Backfilling EBS EBS has to be measured.
Original section is template in the cross. Final section How much was excavated. Topic G
16
Figure 3.6: Backfilling EBS
Topic G
17
EBS Do not do EBS when rain is imminent.
Do not leave EBS excavation open over night. Topic G
18
Topic I
19
Figure 3.7: EBS Topic G
20
Figure 3.8: Loading Unstable Material
Topic G
21
Backfilling EBS Careful placement and compact backfill.
Use similar materials in area. Topic G
22
Figure 3.9: Backfilling EBS
Topic G
23
Organic & Silty Soils Have foundation support for equipment. Topic G
24
Figure 3.10: Organic & Silty Soils
Topic G
25
Seepage in a Cut Must correct area like this. Ditches may work.
Riprapping Underdrains Vegetation will not grow. Topic G
26
Figure 3.11: Seepage in a Cut
Topic G
27
Dust Abatement Required to minimize dust.
Use water or dust control materials. Topic G
28
Figure 3.12: Dust Abatement
Topic G
29
Stone Piles & Fences Large rocks outside the shoulder point. Topic G
30
Figure 3.13: Stone Piles & Fences
Topic G
31
Marsh Excavation Picture 2:
Excavated marsh either cast out or loaded into marsh. Used for deeper marshes. Dragline works slower then backhoe. Topic G
32
Figure 3.14: Marsh Excavation 1
Topic G
33
Figure 3.15: Marsh Excavation 2
Topic G
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.