1 SFOBB East Span Seismic Safety Project Sarah Picker Duty Senior Toll Bridge Program, Caltrans

2 SFOBB East Span Seismic Safety Project Enhanced Constructibility Review for the SFOBB Self- Anchored Suspension Span/Yerba Buena Island (ECR SAS/YBI) 04-012064

3 SFOBB East Span Seismic Safety Project Enhanced Constructibility Review SAS/YBI Caltrans is asking for Contractor input We want to hear from you now We value your knowledge and experience

4 SFOBB East Span Seismic Safety Project Enhanced Constructibility Review SAS/YBI is the opportunity for Contractor to comment on constructibility of plans, specifications and items before advertisement

5 SFOBB East Span Seismic Safety Project We take Brainstorming

6 SFOBB East Span Seismic Safety Project ECR SAS/YBI build a safe bridge biddable job increase competition prevent costly change orders

7 SFOBB East Span Seismic Safety Project Contractors can comment on Safety NO BID item NO BID Specification Risk

8 SFOBB East Span Seismic Safety Project Enhanced Constructibility Review SAS/YBI Phase 1 Contractor Outreach Handout contents posted on Caltrans Office Engineer Website http://www.dot.ca.gov/hq/esc/oe/ecr/index.html

9 SFOBB East Span Seismic Safety Project Enhanced Constructibility Review SAS/YBI Phase 1 initiation March 18 three weeks to review and comment submit constructibility review comments by April 8

10 SFOBB East Span Seismic Safety Project Enhanced Constructibility Review SAS/YBI provide comments to SFOBB Duty Senior duty_senior_tollbridge_district04@dot.ca.gov include contract number 04-012064 include company name, phone number and name of commenter

11 SFOBB East Span Seismic Safety Project Enhanced Constructibility Review SAS/YBI Disclaimer ECR SAS/YBI are not contract plans or specifications and items the contract documents will be bid on

12 SFOBB East Span Seismic Safety Project IDEAS ability to place steel tower temporary detour access to the work on YBI steep slope milestone completion

13 SFOBB East Span Seismic Safety Project IDEAS steel market and fabrication bonding capacities working days foundation issues schedule other

14 SFOBB East Span Seismic Safety Project SAS/YBI 04-012064 Advertisement Fall 2002 Contract documents available from Plans and Document Section http://www.dot.ca.gov/hq/esc/oe/project_status/order_bid_location.html (916) 654-4490 or 4492

15 SFOBB East Span Seismic Safety Project Slide Show available http://www.dot.ca.gov/hq/esc/tollbridge/index.html

16 SFOBB East Span Seismic Safety Project Web Addresses for DBE information http://www.dot.ca.gov/hq/bep/index.htm

17 SFOBB East Span Seismic Safety Project WEB ADDRESS FOR ECR SAS/YBI http://www.dot.ca.gov/hq/esc/oe/ecr

18 SFOBB East Span Seismic Safety Project BUY AMERICA WAIVER APPROVED BY FHWA Tower Saddle (Upper Portion) S-Wire Cable Wrapping MacAlloy Bars

19 SFOBB East Span Seismic Safety Project Requested Buy America Waiver but not approved PPWS Strand

20 SFOBB East Span Seismic Safety Project REQUEST FOR SOLE SOURCE ITEM APPROVED Tower Saddle (Upper Portion) S-Wire Cable Wrapping Macalloy Bars Swivel Joint Seal Assembly Epoxy Asphalt Concrete

21 SFOBB East Span Seismic Safety Project SOLE SOURCE ITEM Requested but not approved PPWS Strand Cable Wire Rod