South Dakota Gas Pipeline Safety Program 2011 Summary
2
State Program General Number of operators – 2011 year end total13 – # of additions since 2010 1 – # of deletions since 2010 1 – Comments Number of inspectors – 2011 year end total 1.1 – Change from year end 2010 0
3
Program Operational Overview 2 inspectors: Josh 85 %, Nathan 28 % inspector, 72 % Program Manager 85 inspection days per year required, 126 in 2011 Complete regulation review once every two years Year 1 (2011): corrosion, patrolling, leak surveys, OQ, TIMP Year 2 (2012): welding, fusion, drug and alcohol, DIMP, PA
4
Covered Operators (13) Municipals Crooks Municipal Gas Garretson Municipal Gas Humboldt Municipal Gas Watertown Municipal Gas Private Distribution Mid-American Energy Montana-Dakota Utilities Northern Natural Gas NorthWestern Energy Transmission Basin Groton CT Pipeline Basin Deer Creek Black Hills Power Montana-Dakota Utilities NorthWestern Energy South Dakota Intrastate Pipeline Sioux Falls Sanitary Landfill Gas Pipeline Xcel Angus Anson Pipeline
5
2010 Year End Gas Statistics for South Dakota Gas transmission mileage 222 Gas distribution mileage 4,483 Number of gas services 202,990
6
SD Gas Distribution Federal Reportable Incident Summary 1998 – 2011 YearNumberFatalitiesInjuriesProperty Damage 2004100$110,266 2007200$696,630 2008100$150,000 20090000 20100000 20110000
7
Enforcement Statistics 2011 NPV & Warnings Cited215 NPV & Warnings Corrected67 NPV & Warnings Outstanding at Year End148 Number fines levied0* Amount of Fine0* *2 penalty dockets opened in 2011– fines assessed in 2012: $800 & $2,000
8
Declaratory Ruling - Pipeline Classification It is possible to have a transmission line under 20 % SMYS. A distribution center begins at the location of title transfer. A pipeline feeding a large volume customer is no longer distribution if it is < 20 % SMYS but must be downstream of a distribution center to be distribution. This could affect operators that may in the future have a large volume customer tapped into an interstate transmission line at a point other than a distribution center with a line operating at < 20 % SMYS. In such a case, this may now possibly be transmission rather than distribution.
9
Major Construction Activity None System expansion activity in distribution systems No new transmission lines
10
Special Permits Requested / Granted None in 2011
11
2011 Highlights Completed TIMP Protocol A inspections on all transmission operators Completed 5 public awareness inspections with new form Completed 5 DIMP inspections Josh Williams completed majority of training for new inspectors Made recommendation to implement mandatory damage reporting Conducted 3 construction inspections Participated on federal/state DIMP implementation team Coordinated and led a joint multi state DIMP inspection
12
2011 Highlights Continued Completed comprehensive OQ plan and field audits on all operators Inspected all operators in following areas: – Corrosion and cathodic protection – Line markers – Patrolling – Leakage surveys – Emergency valves – Excess flow valves – Pipe on structures
13
Pipeline Program Metrics 2010
14
2012 Outlook Cast iron/bare steel replacement begins in Sioux Falls One Call Board decision on supporting mandatory damage prevention Records Inspections: – reporting requirements and emergency plans – test requirements – welding and fusion – damage prevention – MAOP, regulator and relief valves Drug and alcohol inspections – Plan and operator records – Provider site inspections
15
2012 Outlook Continued New regulations – Finish DIMP inspections – Begin Control Room Management inspections – Finish Public Awareness inspections with new form – Training - Webinar on Pipeline Safety, Regulatory Certainty and Job Creation Act of 2011 Inspector Training: – Complete 3 remaining T & Q courses by pipeline staff – Inspector training outside of T&Q Courses (NACE certification, IMP, etc.) Operator Training: – Hold quarterly operator training webinars – Preparations to host 2013 Pipeline Safety Operator Training Seminar