Exterior Restoration and Rehabilitation of Thompson Hall Presented By: University of New Hampshire Goody Clancy Shawmut Design and Construction
2
Today’s Agenda Team Introductions Project Description Pre-construction / Construction Schedule Preliminary Logistics Occupant Concerns / UNH Department Concerns and Issues / Fire, Police and Life Safety
3
University of New Hampshire Thompson Hall Project Team Brenda Whitmore, Project Manager Douglas Bencks, University Architect Paul Chamberlin, Executive Director, Facilities Design and Construction
4
Goody Clancy Thompson Hall Project Team Jean Carroon, Principal Lisa Howe, Project Manager Beth Sitterly, Architectural Conservator John Wathne, Principal (Structures North Consulting Engineers, Inc.)
5
Project Description
7
Shawmut Design and Construction Thompson Hall Project Team Lee Dellicker, Vice President/Partner Carl Jay, Director of Historic Preservation Ryan Lynch, Project Manager Dave Hayden, Site Superintendent Steve Kanavich, Senior Estimator Tim Leblanc, Director of Safety
8
Occupied Renovation Philosophy Shawmut Design and Construction brings a very different attitude to managing construction within occupied environments. We consider ourselves guests in your institution and instill this sense of respect with every subcontractor and individual worker on site. We firmly believe that what goes on “outside the construction fence” is just as important as the actual construction process. We have developed a job site culture with our superintendents and subcontractors that every person needs to demonstrate the highest level of sensitivity to the operational environments.
9
Project Schedule June 2004 – August 2004: Design Development August 2004 – October 2004: Final Design November 2004 – March 2005: Final Planning and Subcontractor Procurement March 2005 – December 2005: Construction
10
Preliminary Logistics Project Safety Subcontractor I.D. Program Site Signage Communication Methods
11
Guard Shack Covered Walkway Gate Tree Protection Emergency Meeting Location Dumpster Gate 2 nd Staging Area Dimond Library Murkland Emergency egress routes- Maintain clear access at all times TO BE APPROVED Staging with cover to maintain walk way at porte cochere
12
“By acceptance of the Contractor Badge, all personnel have acknowledged the worker decorum policy set forth for this project along with the requirements detailed in the General Requirements Rider of all subcontracts. If any worker fails to adhere to these policies or behaves inappropriately while on the University of New Hampshire’s campus, We Reserve The Right to remove any worker from the project.” Subcontractor I.D. Program
13
Site Signage Construction Vehicles ONLY Construction Deliveries NEXT GATE HARD HAT AREA Authorized Personnel ONLY
14
Communication
15
Questions? Thank You!