Team AquaForce Team Members: Santos Ortiz (TL) Christopher Munoz Vicente Mora Instructor: Raresh Pascali Industry Advisor: Garrett Hohmann Faculty Advisor: 1
2
Outline Competition Product Selection Process Component Breakdown Design Intent Cost Analysis Gantt Chart Work Break-down Structure (WBS) 2
3
2014 MATE ROV COMPETITION Mission Scenario Location: Northwestern Lake Huron, Thunder Bay. More than 50 shipwrecks within the Thunder Bay National Marine Sanctuary (TBNMS). Scientist and conservation groups are needed. Map of the Great Lakes with Thunder Bay Map of Thunder Bay, highlighting the TBNMS and its shipwrecks 3
4
Mission Tasks Explore, document, and identify an unknown shipwreck. Collect microbial samples and measure conductivity of the groundwater emerging from a sinkhole. Remove trash and debris from the shipwreck and surrounding area. 2014 MATE ROV COMPETITION 4 Side and top view of ROV scanning shipwreck Zebra mussels engulf a shipwreck
5
2014 MATE ROV COMPETITION Mission Props 5 Outsourced Materials list provided Instructions provided
6
6 Competition Product Selection Process ROV Design Breakdown Design Intent Cost Analysis Gantt Chart Work Break-down Structure (WBS) Risk Matrix
7
7 Product Selection Process THRUSTER COMPARISON ThrusterElectrical Req. Thrust Performance Depth Cost (USD) SeaBotix19.1 VDC6 lbs500 ft$680-720 Crust Crawler 12 VDC to 50VDC15 lbs300 ft$480-520 Seamor 24VDC or 48VDC10 lbs1000 ft$3,500 Cost efficient Thrust capacity Compatibility
8
8 CAMERA COMPARISON CameraQualityHousing Cost (USD) Aquabotix720pIncluded$600 Webcam 1920p x 1080pNot included$80 Size Cost efficient Customizable Product Selection Process
9
9 FRAME MATERIAL COMPARISON MaterialDensity (English)Size (in) Cost (USD) Aluminum.098 3/8”x24x48”$250-275 Acrylic.0431/4”x24”x96” $180-220 Cost efficient Weight Machinability Weld ability Product Selection Process
10
10 Product Selection Process PROCESSOR COMPARISON ProcessorCapability (Volts)Digital I/OCommunication Arduino6-20V14USB Olimex 9-30V16Ethernet Seamate 7-52V8USB Compatibility Voltage capacity Cost efficient
11
11 CONNECTOR COMPARISON Connectors DependabilityConnection Cost (USD) SeaconIndustry StandardLimited to 3$30-70 Manufactured As needed$5-10 Product Selection Process Cost efficient Modifiable Competition advantage
12
12 Competition Product Selection Process ROV Design Breakdown Design Intent Cost Analysis Gantt Chart Work Break-down Structure (WBS) Risk Matrix
13
13 ROV Design Breakdown
14
14 MISCELLENAOUS MATERIALS ComponentMaterialReason Ballast Housing & PistonAcrylicWeight Arm Assembly AluminumStrength End Caps AluminumStrength ROV Design Breakdown
15
15 Ballast Housing P = 100psi Tensile strength of acrylic =10,587 psi Actual pressure at pool bottom =14psi ROV Design Breakdown
16
16 Arm Assembly Hydraulic controlled Mission specific design Cost effective ROV Design Breakdown
17
17 Tether and Connector ROV Design Breakdown
18
18 Competition Product Selection Process ROV Design Breakdown Design Intent Cost Analysis Gantt Chart Work Break-down Structure (WBS) Risk Matrix
19
19 Design Intent The surface area of plates’ provides us with the need to remove material to satisfy weight standards in needed. Side slots allow for cross elements to be easily adjusted.
20
20 Communication Flowchart Design Intent
21
21 Competition Product Selection Process ROV Design Breakdown Design Intent Cost Analysis Gantt Chart Work Break-down Structure (WBS) Risk Matrix
22
22 Cost Analysis ItemCost Low USDCost High USD Thruster (qty. 2 )$1200$7000 Tether$140 Connectors (qty. 6)$30$180 Misc. Acuators/Sensors$200$2000 Pressure Housing (qty. 4)$210$300 LabView-$700 Control Board$90$700 Camera$75$600 End Cap Material$55$750 Arm Material$40$60 Frame Material$180$275 Competition Materials/Props$50$100 Power SourceOn-hand- Total:$2,110$12,110
23
23 Competition Product Selection Process ROV Design Breakdown Design Intent Cost Analysis Gantt Chart Work Break-down Structure (WBS) Risk Matrix
24
24 Gantt Chart
25
25 Competition Product Selection Process ROV Design Breakdown Design Intent Cost Analysis Gantt Chart Work Break-down Structure (WBS) Risk Matrix
26
26 Work Breakdown Structure AquaForce’s ROV 43.3% Phase I 90.5% Research 90% Proposal 100% Competition 100% ROV components 100% Market Research 95% Competition Rules 100% Competition Mission 100% Cost Analysis 90% ROV Component 90% Software Required 50% Phase II 47% Mechanical Design 85% Frame 90% Select Materials 90% Circuit 20% LabView Programming 0% Calculations 60% Material Analysis 85% Electrical Analysis 0% Hydraulic Analysis 0% Phase III 0% Fabrication 0% Redesign 0% Material Purchasing 0% Frame 0% Tendering 0% Testing 0% Buoyance Testing 0% Leaking Test 0% Thruster Testing 0%
27