IRWIN MIDDLE SCHOOL
3
BUDGET ALLOWANCE: FY 2014- $988K Internal UFR FY2015- $208K Internal UFR FYDP16-20- $2.544M
4
IRWIN MIDDLE SCHOOL
5
PROCUREMENT PROJECTED TOTAL COST: $352,000 +/- SUPPORT TOTAL COST: $127,000 +/- SUPPLIES UNIT COST: $52,000 +/-
6
IRWIN MIDDLE SCHOOL 2013NOV04- SITEC CONDUCTS INITIAL SITE SURVEY 2013NOV13- PROJECTED DATE FOR DETAILED ASSESSMENT TO DETERMINE NUMBER AND PLACEMENT OF SIPR/NIPR DROPS AND OUTLETS
7
IRWIN MIDDLE SCHOOL NIPR CABLE CAN BE REUSED SIPR MUST BE PULLED IN CONDUIT ALL NETWORK ELECTRONICS ARE OUT OF SPECIFICATION AND MUST BE REPLACED
8
IRWIN MIDDLE SCHOOL PROJECTED MOVE IN TIMEFRAME NLT MAY/JUNE 2014