NuPECC Meeting – Athens / Greece March 17 & 18, 2006 GSI Darmstadt --- Helmholtz-Zentrum für Ionenforschung The FAIR Project -- Recent Developments and Milestones Walter F. Henning
2
FAIR -- Recent Developments Formal approval by the Cabinet of the German Government on the federal financial contribution to FAIR (65%; for the full construction period 2007-14) (contribution by the State of Hessen (10%) already formally approved in 2004) Formal approval by the Magistrate of the City of Darmstadt of the FAIR Construction Plan ('Bebauungsplan') Baseline Technical Report completed and reviewed; to be submitted to the International Steering Committee for FAIR (FAIR-ISC) on April 11, 2006. Legal documents for contracts developed; 2-company structure for FAIR
3
FAIR -- Recent Developments Formal approval by the Cabinet of the German Government on the federal financial contribution to FAIR (65%; for the full construction period 2007-14) (contribution by the State of Hessen (10%) already formally approved in 2004) Formal approval by the Magistrate of the City of Darmstadt of the FAIR Construction Plan ('Bebauungsplan') Baseline Technical Report completed and reviewed; to be submitted to the International Steering Committee for FAIR (FAIR-ISC) on April 11, 2006. Legal documents for contracts developed; 2-company structure for FAIR
4
FAIR -- Recent Developments Formal approval by the Cabinet of the German Government on the federal financial contribution to FAIR (65%; for the full construction period 2007-14) (contribution by the State of Hessen (10%) already formally approved in 2004) Formal approval by the Magistrate of the City of Darmstadt of the FAIR Construction Plan ('Bebauungsplan') Baseline Technical Report completed and reviewed; to be submitted to the International Steering Committee for FAIR (FAIR-ISC) on April 11, 2006. Legal documents for contracts developed; 2-company structure for FAIR
5
Civil-Construction Development Plan
6
Civil Construction Development Plan -- Procedures and Processes The plan had to go through: -2 public hearings -involvement and participation of all public, semi-public and private bodies representing public interests or officially recognised interests (together more than 100 so-called "TÖB") - preparation of 15 studies and expert statements (including reforestation, environmental impact studies, 'eco-points', radiation safety permit etc.) -several readings, discussions in local community councils and approval by the Darmstadt City Council -approval from The Regional Assembly (assembly of regional mayors, approval of the change of the Regional Development Plan) -compensatory reforestation measures (Hessen-Forst), wildlife support, purchase & exchange of farmland (private owners)
7
FAIR LAYOUT as of 9.02.2006
8
FAIR -- Recent Developments Formal approval by the Cabinet of the German Government on the federal financial contribution to FAIR (65%; for the full construction period 2007-14) (contribution by the State of Hessen (10%) already formally approved in 2004) Formal approval by the Magistrate of the City of Darmstadt of the FAIR Construction Plan ('Bebauungsplan') Baseline Technical Report completed and reviewed; to be submitted to the International Steering Committee for FAIR (FAIR-ISC) on April 11, 2006. Legal documents for contracts developed; 2-company structure for FAIR
9
FAIR - Facility for Antiproton and Ion Research 100 m UNILAC SIS 18 SIS 100/300 HESR Super FRS NESR CR RESR GSI today Future facility ESR FLAIR Rare-Isotope Production Target Antiproton Production Target
10
Fields of Research at FAIR 100 m UNILAC SIS 18 SIS 100/300 HESR Super FRS NESR CR RESR GSI today Future facility ESR FLAIR Hadron Physics & QCD with stored and cooled antiproton beams (0 to 15 GeV/c) Nuclear Structure & Astrophysics with beams of short-lived nuclei (0-1.5 GeV/u) Physics of Dense Plasmas with compressed ion beams & high- intensity petawatt-laser Nuclear Matter QCD-Physics with HI beams (2 to 45 GeV/u) Solid-state and biological applications with ion (& antiproton?) beams Fundamental Symmetries Ultra-high electro-magnetic fields & Quantenelectrodynamics with highly stripped ions and antimatter Accelerator Physics 667 users 909 users 578 users
11
FAIR Baseline Technical Report 2006
13
PAC QCD E. Chiavassa PAC NUSTAR R. Casten PAC APPA D. Schwalm TAC Y. Cho Observers: FAIR Project CORE Cost Review Groups D. Plane, W. Bartel FCI Full Cost Issues B. Brandt AFI Working Group Administrative + Funding Issues Ö. Skeppstedt LFI Legal Framework Issues U.B. Jahn STI Working Group Scientific + Technical Issues H. Wenninger ISC International Steering Committee H. Schunck International Committee Structure for FAIR MiniTACs Cryogenics Warm and Cold magnets Power Supplies Beam Instrumentation p-Linac
14
STI: Working Group on Scientific and Technical Issues Chair: Horst Wenninger Sydney Gales until March 2005 Members Alex Müller, France Wolfram Korten, France Boris Sharkov, Russia John Simpson, UK Günther Rosner, UK ZHAN Wenlong, China Berta Rubio, Spain Jose Benlliure, Spain Dan-Olof Riska, Finland Juha Äystö, Finland Pasquale Fabbricatore, Italy Piero Dalpiaz, Italy Ulrich Wiedner, Sweden Håkan Danared, Sweden Walter Henning, Germany Hans Ströher, Germany Hans Gutbrod, FAIR Project Observers Peter Schroth, Germany Eberhard Widmann, Austria Nicolae Zamfir, Romania Ingo Augustin, Scientific Secretary
15
Programme Advisory Committees (PAC) QCD Emilio Chiavassa (Chair) Stanley Brodsky Piero Dalpiaz Donald Geesaman Hans Ake Gustafsson Serge Kox Rolf Landua Alain Magnon Rudolf Maier Bernd Müller John Nelson Eulogio Oset Dan-Olof Riska Hans-Georg Ritter Hans Ströher Itzhak Tserruya NUSTAR Rick Casten (Chair) Faical Azaiez Sherril Bradley Peter Butler Hubert Grawe Robert Janssens Shigeru Kubono Kurt Kilian Hans-Otto Meyer Alfredo Poves Berta Rubio Alan Shotter Antonio Villari Helmut Weick Michael Wiescher APPA Dirk Schwalm (Chair) Stefano Atzeni Michael Basko Gordon Drake Paul Indelicato Gilles Maynard Thomas Mehlhorn Peter Norreys Roland Sauerbrey Boris Sharkov Peter Spiller Markus Steck Dominique Vernhet Toshi Yamazaki
16
Technical Advisory Committee (TAC) Chair: Yanglai Cho Roland Garoby Sergey Ivanov Marcel Jacquemet Tomas Junquera Alex Müller Jerry Nolen Satoshi Ozaki Pasquale Fabbricatore Ferdinand Willeke Yoshishige Yamazaki Mini-TAC (topical sub-committees) p-linac –Raymond Fuja (Chair) –Helmut Haseroth –Roy Cutler Power supplies –Roy Cutler (Chair) –Raymond Fuja –Frederic Bordry –Gunnar Fernqvist –Hans-Jörg Eckoldt –Jens-Peter Jensen Beam diagnostics Cold magnets –Luca Bottura (Chair) –Pierluigi Bruzzone –Steve Gourlay –Jim Kerby –Marcel Jacquemet –Pasquale Fabbricattore –Tom Taylor –Walter Scandale –Erich Willen –Rob Wolf Cryogenics –Bernd Petersen (Chair) –Wolfgang Erdt –Ralf Trant –Siegfried Wolff –George Mulholland –Claus Rode –Hans Quack Warm magnets –Joseph Tuozolo (Chair) –Masayuki Muto
17
Cost Review Committees CORE-A for Accelerators –David Plane (Chair) –Klaus Blasche –Reinhard Bacher –Manfred Buhler-Broglin –Wolfgang Erdt –Gunnar Fernqvist –Helmut Haseroth –Ian Gardner –Dieter Kraemer –Lluís Miralles –Graham Stevenson –Pierre Strubin –Tom Taylor –Eberhard Weisse CORE-E for Experiments –Wulfrin Bartel (Chair) –Hans-Juergen Hilke –Ian Lazarus –Pierre Lazeyras –Hans Georg Ritter –John Simpson –Andrea Vacchi
18
PAC QCD E. Chiavassa PAC NUSTAR R. Casten PAC APPA D. Schwalm TAC Y. Cho Observers: FAIR Project CORE Cost Review Groups D. Plane, W. Bartel FCI Full Cost Issues B. Brandt AFI Working Group Administrative + Funding Issues Ö. Skeppstedt LFI Legal Framework Issues U.B. Jahn STI Working Group Scientific + Technical Issues H. Wenninger ISC International Steering Committee H. Schunck Scientific, Technical and Legal Framework for FAIR MiniTACs Cryogenics Warm and Cold magnets Power Supplies Beam Instrumentation p-Linac Baseline Technical Report - accelerator TR's - experiment proposals - civil construction plans (~ 3500 pages) PAC & TAC Review Reports Cost Book Cost Review Reports - accelerator & civil construction (CORE-A) - experiments (CORE-E) Convention Articles of Association By-Laws Final Act Document Legal Framework Report (LFI) Full Cost Structure Report (FCI)
19
2004 2005 Contract(s) Development Contract(s) Negotiations Closing ISC-FAIR International Working Group Activities Signing of MoU Phase I – Governed by MoU Phase II Governed by Contracts MoU PAC's Technical Committees: PAC's & TAC Proposals / TR's LoI's (2100 authors) Baseline Technical Report (BTR) and Project Definition (April 06) PAC and TAC Evaluations Cost Reviews TDR's 2006 Administrative and Financial Issues Working Group Scientific and Technical Issues Working Group
20
FAIR -- Recent Developments Formal approval by the Cabinet of the German Government on the federal financial contribution to FAIR (65%; for the full construction period 2007-14) (contribution by the State of Hessen (10%) already formally approved in 2004) Formal approval by the Magistrate of the City of Darmstadt of the FAIR Construction Plan ('Bebauungsplan') Baseline Technical Report completed and reviewed; to be submitted to the International Steering Committee for FAIR (FAIR-ISC) on April 11, 2006. Legal documents for contracts developed; 2-company structure for FAIR
21
Site Lab.-Services Landlord Activ. POF-Research Res.-Infrastr. Scientific- Technical Infrastructure Administrative Infrastructure FAIR (Facility) Construction / Operation GSI FAIR GmbH Management
22
Reasons for 2 Legal Structures (GmbH's): Same structure ( contractual arrangements) for both FAIR and XFEL Separation of GSI activities which are not part of the FAIR program Construction, regulatory & radiation safety permits and environmental impact statements under GSI authorship Relation with Helmholtz-Association (HGF) and program oriented funding (POF) clearly defined All partners in FAIR GmbH on equal basis (Germany 'same' as others)
23
Site Lab.-Services Landlord Activ. POF-Research Res.-Infrastr. Scientific- Technical Infrastructure Administrative Infrastructure FAIR (Facility) Construction / Operation GSI FAIR GmbH Management
24
Site Lab.-Services Landlord Activ. POF-Research Res.-Infrastr. Scientific- Technical Infrastructure FAIR (Facility) Construction / Operation FAIR-GmbH Management (Long-term) Contractual Arrangements "Geschäftsbesorgungsvertrag" Strategic Planning Budget & Financing Controlling Scientific Program & Schedule International Employment FAIR Line Management Administrative Infrastructure GSI Line Management Laboratory Facility & Site Operations Engineering Design Site Preparation and ES&H Technical & Civil Construction Production Supervision Assembly & Commissioning GSI-mbH Management
25
Schedule, Milestones and Critical Path Issues BUNG report on Planning of FAIR civil engineering, February 24 th, 2006, Consolidation of Planning of FAIR construction for April 10 th ISC meeting Mini-Tac or TAC on Civil Engineering ca. April/May 2006 STI presents the FAIR Baseline Technical Report to FAIR ISC April 10 th, 2006 ISC acts upon and makes decision as to the scope of the project..how quickly? Member states express (in writing?) their intention for specific in-kind contributions process is going on, see below AFI Final Results by late spring - early summer 2006 and presentation to FAIR ISC Finalization of FAIR geometry by August 2006 for starting planning for civil construction readiness for Fall of 2007 FAIR Contract closure should start in 2006 Decisions on NESR, RESR magnet technology (warm or cold) in summer of 2006 Spain If decision for NESR and RESR superconducting, prototype for end of 2008 Spain CR and Super FRS sc-dipole prototypes in 2008 China SIS 300 decision for or against curved magnets probably end of 2006 Italy, Russia SIS 300 sc magnets prototype a) straight magnets 2008, b) curved magnets 2008/9 Italy, Russia SIS 300 sc quadrupoles prototype 2008/9 France, CEA and IN2P3 SIS 100 sc magnet prototype 2008 Russia, Industry, GSI HESR curved sc magnets, feasibility study mid 2006, prototype in 2008 Industry, Jülich Design Super FRS Triplets 2007 Industry, GSI Prototype Super FRS Triplet 2008 Industry, GSI SUPER FRS Energy Buncher dipoles, delivery end of 2009 India
26
NuPECC Meeting – Athens / Greece March 17 & 18, 2006 GSI Darmstadt --- Helmholtz-Zentrum für Ionenforschung Thank you !!!