Federal Aviation Administration Data Communications Integration Team (DCIT) DCL Trials test activities Presented to:DCIT # 15 By:Peter Muraca FAA Date:May.

Similar presentations


Presentation on theme: "Federal Aviation Administration Data Communications Integration Team (DCIT) DCL Trials test activities Presented to:DCIT # 15 By:Peter Muraca FAA Date:May."— Presentation transcript:

1 Federal Aviation Administration Data Communications Integration Team (DCIT) DCL Trials test activities Presented to:DCIT # 15 By:Peter Muraca FAA Date:May 30 – 31, 2012

2 Federal Aviation Administration DCIT # 15 May 30 – 31, 2012 Status Documents –Test Plan complete –E-E System Test Cases Document 85% complete –VRTM 90% complete –Working on SAT plan/procedures Coordination –ARINC and SITA service / connections –FAA FNTB – nesg gateway –T.C Project Aircraft –HADDS Lab for failover and revision change testing –Boeing Air Lab –DCIT Aircraft (FedEx, United, Delta) –A. Fry AIR LAB 2

3 Federal Aviation Administration DCIT # 15 May 30 – 31, 2012 Status - Test Activities 3 startstop pDTAP delivery to Tech Center5/10/20128/15/2012 pDTAP / HADDS in-box Interface Testing5/14/20125/28/2012 pDTAP / HADDS via FNTB Interface Testing5/28/20126/4/2012 pDTAP / HADDS / CSP Interface Testing via FNTB6/4/20126/13/2012 pDTAP / HADDS / CSP / LAB Avionics Connectivity Testing via FNTB6/13/20126/20/2012 pDTAP (applicable) Requirements Testing via Lab infrastructure6/20/20127/18/2012 pDTAP (applicable) Requirements Testing via Lab infrastructure to Boeing Air Lab7/18/20128/1/2012 pDTAP PTR fixes / Regression Testing in LAB env.8/6/20128/15/2012 Test Plan Update5/10/20127/20/2012 Test Cases Final5/10/20127/20/2012 pDTAP Quick Look Report7/11/20128/15/2012

4 Federal Aviation Administration DCIT # 15 May 30 – 31, 2012 Status - Test Activities (cont.) 4 DTAP End to End System Test8/15/201210/12/2012 DTAP Requirements Testing using Lab Infrastructure (follow VRTM & Test Cases)8/15/20129/14/2012 DTAP Requirements Testing using Lab Infrastructure with Test Aircraft (follow VRTM & Test Cases)9/14/20129/21/2012 DTAP Requirements Testing using Lab Infrastructure with Boeing Air Lab (follow VRTM & Test Cases)9/21/20129/28/2012 DTAP Requirements Testing using Lab Infrastructure with FedEx / Delta / United aircraft (follow VRTM & Test Cases)9/28/201210/5/2012 DTAP Error Conditions / Abnormal Cases8/5/201210/12/2012 DTAP PTR Fixes / Regression Testing8/5/201210/12/2012 End to End Test Report9/14/201210/12/2012

5 Federal Aviation Administration DCIT # 15 May 30 – 31, 2012 Status - Test Activities (cont.) 5 DTAP Site Acceptance Testing10/15/201210/26/2012 Final SAT Sub_set Test Cases document9/14/201210/12/2012 End to End Connectivity & Functional testing in field10/15/201210/18/2012 Failover Conditions Testing10/18/201210/20/2012 End to End Operational testing based on Sub_set Test Cases10/15/201210/26/2012 SAT Final Test Report10/15/201210/29/2012

6 HADDS HID HOST ERAM HADDS HID HOST ERAM NESG ED-8 ACY Airline HOST DEMARC TEST ED-8 ACY FAA Technical Center FNTB DEMARC FTI OPS IP HADDS HID HOST ERAM DTAP MOUSE KYBRD MONITOR OS FDP DCL AFN HMI FANS 1/A+ STACK 1 2 3 2,3 ARINC SITA IP TEST TOWER TDLS DCL Trials Architecture Airline HOST ARTCC 2 3 2,3 HADDS CSP & API DATA RECORD DEMARC TDLS PC-RCU Strip Printer


Download ppt "Federal Aviation Administration Data Communications Integration Team (DCIT) DCL Trials test activities Presented to:DCIT # 15 By:Peter Muraca FAA Date:May."