Commissioning: A University Perspective May 3, 2006 Rebuild Michigan Workshop Advanced Energy Technologies for Commercial Buildings
2
Terry Pahl, P.E., LEED, Facilities Engineer Grand Valley State University Energy Department Energy Estimates Utilities CxP Project Management Technical Assistance EMS Budgets Equipment LEED/Energy Star
3
Commissioning Commissioning - Defined What Commissioning Does Not Solve Reasons for Commissioning The Commissioning Process Commissioning Findings Recommendations
4
Commissioning - Defined Verify and ensure that fundamental building elements and systems are designed, installed and calibrated to operate as intended.
5
AHU System
6
Testing Controls
7
What Commissioning Does Not Solve Does not correct an improper design of the building or systems within the building.
8
Steel Beam Penetrations
9
What Commissioning Does Not Solve Does not correct an improper design of the building or systems within the building. Does not correct a poorly constructed building or poor installation of the building systems.
10
Poor Conduit Connection
11
Reasons for Commissioning Design and construction errors are identified early. Building system errors are identified early. Energy savings. Operational savings. Satisfied clients
12
The Commissioning Process - Past Historically In-house staff Cursory inspections Punch list
13
Gold Certified – LEED Building Michigan Alternative Renewable Energy Center
14
Silver Certified – LEED Building Lake Ontario Hall
15
The Commissioning Process - Present Current Engage a commissioning authority. Develop design intent and basis of design documentation. Include commissioning requirements in the construction documents. Develop and utilize a commissioning plan. Verify installation, functional, performance, training and documentation. Complete a commissioning report. Current - additional Review the design prior to the CDs. Review the CDs prior to completion. Review selected commissioned equipment submittals. Develop a system and energy management manual. Contract for near-warranty or post-occupancy review.
16
Commissioning Findings...
17
Duct Connection
20
Flexible Connection
21
Proper Duct Seal During Construction
22
Missing Insulation
23
Leaks
24
Improper Return Duct Seal During Construction
25
Proper Return Duct Seal During Construction
26
Proper Duct Seal During Construction
27
Design Issue
28
Construction Issue
29
Design Issue
30
Construction Issue
31
Recommendations Choose your design firms and contractors based on their commitment to detail and solving problems. Always commission. In-house Outsource Strengthen specifications to include commissioning tasks. Add the commission costs as part of the budget process.