Download presentation
Presentation is loading. Please wait.
Published byWarren Park Modified over 9 years ago
1
July 13, 2012 Transmission Needs Analysis Scenario 1 Update: BAU All Technologies
2
2 Agenda Review Major Process Steps Review Base Case Upgrades Area Analysis 2
3
3 Major Process Steps Base Case Development –Develop a simplified network for study years 2022 (10yr) and 2032(20yr) based upon the most recent 5YP Case –Incorporate scenario-specific economic assumptions Load forecast Resource development / retirement –Create a workable case Identify and alleviate base case overloads Update monitored elements Identify and review congestion –Identify Conceptual Projects Work with TDSP’s to identify plausible solutions / economic alternatives to Base Case issues 3
4
4 Major Process Steps AC Analysis –Identify import limitations to major load regions that maintain voltage stability –Impose import constraints in a DC Model Economic and Reliability Assessment –Assess the adequacy of existing infrastructure and supplemental conceptual projects at meeting study criteria –Document scenario specific results by Area, including Significant Issues Reliability concerns Economic Opportunities 4
5
5 Base Case Reliability Upgrades 2022 To build a solvable 2022 model, certain upgrades were necessary to replicate what would typically be resolved in shorter term planning horizons. In certain instances (primarily near major load zones) major upgrades were necessary to build a useable case: kVMiles Approximate Cost 345376 $700M (2012) 138360 $278M (2012) Including: One upgrade of an existing 345kV Import into Houston Multiple 345kV upgrades with the Houston Urban area Several major upgrades of existing 345kV imports into Dallas / Fort Worth from east of the DFW region
6
6 Base Case Reliability Upgrades 2022
7
7 Base Case Reliability Upgrades 2032 Similar to(but more extreme than) the 2022 model, development of a 2032 model required certain upgrades necessary to replicate what would typically be resolved in shorter term planning horizons. In certain instances (primarily near major load zones) major upgrades were necessary to build a useable case: kVMiles Approximate Cost 3451376 $2.1B(2012) 138360 $1.2B (2012) Including: An incremental 345kV Import into Houston Extensive 345kV upgrades from South to Houston as well as 345kV upgrades into the Houston Urban area Extensive 345kV upgrades of existing imports into Dallas / Fort Worth from east / southeast of the DFW region
8
8 Base Case Reliability Upgrades 2032
9
9 Area Analysis BAU All Tech with DR 9
10
10 Methodology: 10 1.Develop a base-case with irresolvable constraints upgraded. 2.Identify scenario-specific import limitations into major load zones given most severe resource and element contingencies. 3.Create binding constraints to represent AC voltage stability limits in the DC / PROMOD Model. 4.Identify must-have reliability upgrades and economic supplements / alternatives.
11
11 Dallas / Fort Worth Area: Base Case Upgrades 11 From BusTo BuskV Original Rating New Rating Line Length new or upg $M/Mi (2012) Total Cost ($M, 2012) Year TricornerTrinidad3451072196940.5upg1.4659.1 < 2022 Big BrownNavarro3451072196930.4upg1.4644.4 < 2022 Big BrownNavarro3451072196930.4upg1.4644.4 < 2022 Trading HouseSam Switch3451072196922.8upg1.4633.3 < 2022 Trading HouseSam Switch3451072196922.8upg1.4633.3 < 2022 Cedar Hill SwitchWatermill3451072196917.3upg1.4625.3 < 2022 Jewett 500kV Watermill 500kV 500 6928135new2.98402.30 <2032 Monticello 345 Allen Switch 345 34510722987102.4upg1.46149.50 <2032 Royse Switch 345 Shamburger Switch 345 3451072298780.9upg1.46118.11 <2032 Farmersville 345Monticello 3453451072298780.9upg1.46118.11 <2032 NavarroWatermill 345345 163147new2.44114.68 <2032 TricornerTrinidad345 163140new2.4497.60 <2032 Venus SwitchSam Switch3451072298737.9upg1.4655.33 <2032 Venus SwitchSam Switch3451072298737.9upg1.4655.33 <2032 Wolf HollowRocky Creek3451072298735.7upg1.4652.12 <2032 Big BrownNavarro3451072298730.4upg1.4644.38 <2032 Big BrownNavarro3451072298730.4upg1.4644.38 <2032 Valley SESAnna Switch3451793298726.5upg1.4638.69 <2032 Royse Switch 345 Allen Switch 345 3451631298722.8upg1.4633.29 <2032 TrinidadRichland3451072298718.7upg1.4627.30 <2032 West LeveeWatermill 3453451631298717.7upg1.4625.84 <2032 Cedar Hill SwitchWatermill 3453451072298717.3upg1.4625.26 <2032
12
12 Dallas / Fort Worth Area Significant Issues: As studied, expanded import paths will be required by 2022 to maintain voltage stability –19GW assumed DFW Load –Critical Contingency: n: Trinidad-Tricorner-Watermill g: Mountain Creek To alleviate base case overloads on the Dallas Import interface in 2032, three projects were included: –Navarro – Watermill 345kV Double Circuit –Watermill to Jewett 500kV –Trinidad to Tricorner 345kV 12
13
13 DFW Import Capability Issue Options tested to improve DFW Import Capability Options Dallas Interface in AC Corresponding Year in AC Analysis Corresponding Year in DC Analysis MWDelta Base Case18890020222028 Watermill-Jewett double circuit 500kV1963574520242031 Navarro-Watermill double circuit 345kV1917528520242032 Tricorner-Trinidad double circuit 345kV1903014020232028
14
14 DFW Economic Project Options - 2022 Watermill-Navarro double circuit 345 kV option was evaluated for economy after demonstrating benefit in import analysis. While the option does not meet current economic criteria, it does increase import capability into Dallas and relieve nearby 345kV overloads. Project Options Tested for 2022 Length (mile) Estimated Capital cost (million in 2022) Production Cost Savings (million) Reliability benefit (cost realized by addressing or causing other overload issues) (million) Economic? New Watermill-Navarro 345 kV line47.4150.180.2(67.0)No
15
15 DFW Economic Project Options - 2032 Projectlength Estimated Capital cost (million in 2032) Yearly prod cost saving Reliability benefit (cost realized by addressing or causing other overload issues) (million) Economic? 345 kV Venus- Tricorner-Royse 79 miles335.22 135.6 No Dallas east import365 miles1,382.405.11,342.20No Dallas east import project solved significant overloads, and was very close meeting economic criteria (siting- specific solution.) The reliability / economic implications of these projects are dependent upon siting assumptions.
16
16 DFW: Special Issues Increasingly urban areas present limited ROW to access loads from remote resources East to Dallas transmission projects are only necessary under scenario specific siting assumptions 16
17
17 Houston Area: Base Case Upgrades 17 FromBusToBuskV Original Rating New Rating Line Length new or upg $M/Mi (2012) Total Cost ($M, 2012) Year South Texas ProjectWA Parish3451412196968.3upg1.4699.7< 2022 SmithersBelaire3451137196925.6upg1.4637.3< 2022 WA ParishBelaire3451137196925.2upg1.4636.8< 2022 WA ParishObrien3451450196917.0upg1.4624.8< 2022 WA ParishObrien3451450196917.0upg1.4624.8< 2022 CanalLufkin345NA5974138new2.44336.72 < 2032 South Texas ProjectWA Parish3451412298768.3upg1.4699.7< 2032 South Texas ProjectDow Chemical3451450298745.5upg1.4666.4< 2032 SmithersBellaire3451137298725.6upg1.4637.4< 2032 WA ParishBellaire3451137298725.2upg1.4636.8< 2032 South Texas ProjectHillje3451195298719.3upg1.4628.2< 2032 Lufkin SwitchBerea REA13884435.0233.5upg0.7525.1< 2032
18
18 Houston Metropolitan Area Significant Issues: Increased dependence on imported power and limited opportunities for resource development internal to Houston metro region highlights the need for additional import paths. The dependence on the north-to-Houston import path limits opportunities to improve economic efficiency absent geographic diversity. 18
19
19 Houston Metropolitan Area Significant Issues: As studied, expanded import paths will be required by 2022 to maintain voltage stability –20GW assumed Coast Weather Zone Load –Critical Contingency: n-1: Roan-Kuykendahl & Singleton – Tomball g-1: Cedar Bayou #2 Significant congestion on the North to Houston constraint Lufkin to Jordan 345kV* was added to alleviate base case import constraint overloads *(scenario specific least cost option) 19
20
20 Houston Area Import Capability Issue Options (double circuit 345 kV) Houston Interface Limit (AC) Corresponding Year in AC Analysis Corresponding Year in DC Analysis MWDelta Base Case*88270 2022 2031 Fayette-O’Brien 345 kV9346519 2024 2032 Lufkin-Jordan 345 kV9538711 2026 Beyond 2032 (no overload in 2032) TNP One-Salem-Zenith 345 kV9306479 2024 Beyond 2032 (no overload in 2032) SO Texas-Hillje-O’Brien 345 kV9149322 2024 Beyond 2032 (no overload in 2032) Note: * The Fayette-Zenith 345 kV line has been removed from the study model
21
21 Houston Area Economic Project Options - 2022 Upgrading Green Bayou transformer is expected to provide economic benefit. Although Fayette-O’Brien, TNP One-Salem- Zenith, South Texas-Hillje-O’Brien 345 kV line are not economical, the options address potential overload issue on the W.A. Parish- O’Brien 345 kV line in the area. Project Options Tested for 2022 (all options are double circuit options) Length (mile) Estimated Capital cost (million in 2022) Production Cost Savings (million) Reliability benefit (cost realized by addressing or causing other overload issues) (million) Economic? New Fayette-O Brien 345 kV line81.3241.70.6(108.8)No New Lufkin-Jordan 345 kV line138.1430.24.136.79No New TNP One-Salem-Zenith 345 kV line149.5444.66.2(105.3)No Upgrade Gibbons Creek-Singleton 345 kV9.423.80.5n/aNo Upgrade Green Bayou 345/138 kVn/a11.92.8n/aYes Upgrade S. Texas-Hillje, and new Hillje- O’Brien 345 kV line 85.4254.04.1(54.1)No
22
22 Houston Area Economic Project Options - 2032 A new import path into the Houston Region was needed for stability in the 2032 case Study option Lufkin to Jordan was selected as a reliability fix for 2032 Lufkin to Jordan was tested and demonstrated economy in 2030 Projects tested for 2032Length(mile) Project cost ($M in 2032) Reliability benefit (upg cost avoided) ($M in 2032) adjusted cost/6 ($M in 2032) prod cost saving in 2032($M) economic? 500kV Zenith-TNP, 345kV TNP-Thouse 59(345kV)+133(500k V) 975.1333.8106.925.4No 500kV Limest-Zenith148831.2286.990.723No Congestion upgrade Houston268.8555219.455.920.45No Project tested for 2030Length(mile) Project cost ($M in 2030) Reliability benefit (cost avoided) (million in 2030) Adjusted cost/ ($M in 2030) prod cost saving in 2030($M) economic? Lufkin-Jordan 345kV138504385.519.829.9Yes
23
23 Houston Area Special Issues: Demand Response The BAU / All Technology Study introduces demand response to the planning model: 23 City Capacity (MW) IndustrialResidential/Commercial Austin60275 Dallas160733 Houston200734 San Antonio80458 Absent Demand Response in this model: The Houston Area Import constraint would be overloaded one year sooner (2030) The Lufkin to Jordan line would no longer maintain voltage stability in the Houston region up to the year 2032
24
24 Austin / San Antonio Area Base Case Upgrades (2032) 24 FromBusToBusLine or XfmrkV Original Rating New RatingLine Length new or upg $M / Mi Total cost ($M 2012) Hill CountrySkylineLine3451171298710.8upg1.4615.77 Marion 345Marion 138Transformer138478 0new 7.98 Cagnon 345Cagnon 138Transformer138600 0new 7.98 Cagnon 138VLSILine1383317898.7upg0.756.53 Cedar ValleyCopperAS CoveLine138171435.02227.3upg0.7520.48 McNeilMarshall FordLine13822143514.5upg0.7510.88 GarfieldHicrossLine13848078913.8upg0.7510.35 Howard LaneJollyvilleLine1384807897.7upg0.755.78 LeanderNamelessLine1382217896.8upg0.755.10
25
25 Austin/San Antonio Areas Significant Issues: As studied, expanded import paths will be required by 2027 to maintain voltage stability (San Antonio) –13GW peak load assumed for Austin / SA –Critical Contingency: n-1: Hill Country – Marion & Skyline – Marion g-1: Deely unit retired in 2018 25
26
26 Austin/San Antonio Areas 26 Significant Issues: Increased dependence on imported power and limited opportunities for resource development internal to San Antonio 345kV Loop highlights the need for additional import paths. Limited strong sources from the West places increasing dependence upon 138kV transmission in Austin.
27
27 Austin/San Antonio Areas Import Capability Map of Options to Improve San Antonio/Austin Import Capability
28
28 Austin/San Antonio Areas Import Capability San Antonio Area Import Capability from Voltage Stability Perspective 13,209 MW at San Antonio/Austin Critical contingency: Hill Country-Marion & Skyline-Marion under G-1 Options San Antonio Interface Limit Corresponding Year in AC Analysis Corresponding Year in DC Analysis MWDelta Base Case303302027-2028 Beyond 2032 (no overload in 2032 Base Scenario) Elm Creek – Spruce 345 kV double circuit line 3118852028-2029 Kendall – Hill Country 345 kV double circuit line 3076432028-2029 Lon Hill – Pawnee – Spruce Line upgrade 3069362028 345 kV double circuit line from Cagnon – Miguel 32852522029 500 kV double circuit line from Comanche peak – Edinburg 44431410>2030 500 kV circuit from Newton – Miguel- Lon Hill 41871154>2030 500 kV circuit from Kendall – Miguel – Lon hill 4008975>2030
29
29 Austin/San Antonio Areas : Special Issues Hill Country to Skyline, absent incremental import capacity, will be overloaded by 2032. Congestion on to the SA loop is observed prior to 2032. A new western 345kV source may be difficult to terminate at existing switchyards on the 345kV loop. Western source needs for the Austin area merits further study. 29
30
30 Austin/San Antonio Area Economic Project Options - 2022 Project Options Tested for 2022 (all new 345 kV lines are double circuit options) Length (mile) Estimated Capital cost (million in 2022) Production Cost Savings (million) Reliability benefit (cost realized by addressing or causing other overload issues) (million) Economic? Cagnon-Miguel 345 kV65.0193.33.087.40No Cagnon-Miguel 345 kV & Cagnon 345/138 kV65.0217.14.5n/aNo Cagnon-Pawnee 345 kV81.3241.73.7137.33No Cagnon-Pawnee 345 kV & Cagnon 345/138 kV81.3265.44.9n/aNo Kendall-Hill Country 345 kV48.8145.0(8.2)n/aNo Upgrade Elgin-Taylor 138 kV11.415.31.0n/aNo Upgrade Hill Country-Skyline 345 kV10.830.31.2n/aNo Additional path(s) from the South into the San Antonio area will significantly relieve the loading on the Hill Country- Skyline and Spruce-Pawnee (assumes incremental generators sited South of S.A.)
31
31 Austin/San Antonio Area Economic Project Options - 2032 ProjectLength Estimated Capital cost (million in 2032) yearly prod cost saving Reliability benefit (cost realized by addressing or causing other overload issues) (million) economic? 500kV Lnhill-Migel-Cagnon1911,106.702.5 379.9 No Congestion upgrade San Antonio 109252+8311222.3 No
32
32 Lower Rio Grande Valley Base Case Upgrades 32 FromBusToBus Line or Xfmr kV Original Rating New Rating Mi new or upg $M/Mi Total Cost ($M, 2012) Year WeslacoStewartLine13815743514.66upg1.116.1<2022 AbileneCallahanLine13813543519.2upg0.7514.4<2032 WormserRio BravoLine1384557899.9upg0.757.4<2032 AderholdDukeLine1382354357.6upg0.755.7<2032 ElsaAderholdLine1382354357.12upg0.755.3<2032 Barney DavisRodd FieldLine1383207897.1upg0.755.3<2032 Celanese BishopKlebergLine1382114356.1upg0.754.6<2032 South McAllenLas MilpasLine1381574355.9upg0.754.4<2032 HollyRodd FieldLine1383207895.21upg0.753.9<2032 AirlineCabanissLine1383207894upg0.753.0<2032
33
33 Reliability/Congestion Issues –LRGV for 2022 and 2032 The Lower Rio Grande Valley (LRGV) was studied with the following scenario specific assumptions: 1400 MW of thermal generation sited in the LRGV RPG approved projects in service Largest CCGT in service / outaged Given these assumptions, no congestion or reliability issues were observed for the selected study years. The following sensitivities were tested: Maximum MW Flow on LRGV Interface Observed in PROMOD During 2032 Peak Load Condition Under Different Generation Assumption Sensitivity ScenarioMaximum Flow (MW) Violated Interface Limit (2512 MW) ? With new expansion unit sited in LRGV918No With new expansion units sited outside LRGV2048No With new expansion units sited outside LRGV and With the major existing combined cycle units in LRGV offline 2691Yes
34
34 LRGV: Study Assumption Sensitivities Absent resource development in the LRGV, for the most severe generation contingency, incremental import capacity is needed in 2028 for voltage stability. 34 Without Expansion units modeled inside LRGV And With Major Existing Combined Cycle Unit offline MonthYearFlow (MW) Interface Limit Applied (MW) Violated Interface Limit? Maximum MW Flow in 2028, 2029, 2030 and 2032 on LRGV Interface 8 203226912512Yes 203026202512Yes 202925662512Yes 202824342512No
35
35 Preview of Scenario 2 – BAU with NG Retirements Scenario 2 assumes retirement of NG fired resources after 50 years 35 TH Wharton – All units (1022 MW) Greens Bayou – All units (354 MW) Cedar Bayou -1,2 (1494 MW) Sam Bertron -1,2 (348 MW) W A Parish -1,2,3,4,T1 (1191 MW) Sam Rayburn – GT1,GT2,3 (52 MW) B M Davis 1 (335 MW) Silas Ray 5 (17 MW) Pearsall -1,2,3 (74 MW) VH Braunig – 1,2,3 (862 MW) O W Sommers - 1,2 (810 MW) Dansby 1 (110 MW) Atkins 7 (20 MW) Sim Gideon - 1,2,3 (620 MW) Decker- 1,2 (748 MW) Trinidad 6 (226 MW) Stryker Creek -1,2 (673 MW) Graham - 1,2 (615 MW) Handley – 3,4,5 (1266 MW) R W Miller - 1,2,3 (403 MW) Mountain Creek -6,7,8 (808 MW) Ray Olinger -1,2,3 (331 MW) Powerlane Plant -1,2,3 (88 MW) Lake Hubbard -1,2 (916 MW) Ferguson (425 MW) 2006-2010 2011-2015 2016-2020 2021-2025 2025-2030
36
36 Summary: 2022/2032 36 Dallas / Fort Worth: Incremental import paths will be needed by 2022 Scenario-specific assumptions place most incremental resources South and Southeast of the DFW area. Future scenarios will be studied to determine the impact to import path needs. Dynamic and static reactive solutions may maintain voltage stability / delay the need for incremental import paths. Houston Metropolitan Area: Incremental import paths will be needed by 2022 Scenario-specific assumptions place most incremental resources South and North of the Houston Metro region. Certain import path upgrades demonstrate economy before a reliability required in-service year.
37
37 Summary: 2022/2032 37 Austin / San Antonio: Strong sources west of the Austin / San Antonio region aide economy and voltage stability Increased dependence on imported power in the Austin / San Antonio Area merits further study. Congestion and base-case overloads on the 345kV connections to the San Antonio ring support the need for incremental 345kV import paths. Increased imports to support voltage stability in the San Antonio are needed by 2028 (assuming limited or no development of incremental resources within the 345kV loop) Lower Rio Grande Valley: Limited congestion, overloads, or voltage stability issues are seen with incremental resources developed in the LRGV Scenario-specific assumptions site incremental resources in the South and LRGV. Absent resource development local to the area, incremental imports are needed by 2028 for voltage stability.
38
38 Questions? 38
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.