Download presentation
1
Project Scheduling: PERT/CPM
Metodos Cuantitativos M. En C. Eduardo Bustos Farias
2
Characteristics of a Project
A unique, one-time effort Requires the completion of a large number of interrelated activities Resources, such as time and/or money, are limited Typically has its own management structure Metodos Cuantitativos M. En C. Eduardo Bustos Farias
3
M. En C. Eduardo Bustos Farias
Project Management A project manager is appointed to head the project management team The team members are drawn from various departments and are temporarily assigned to the project The team is responsible for the planning, scheduling and controlling the project to its completion Metodos Cuantitativos M. En C. Eduardo Bustos Farias
4
M. En C. Eduardo Bustos Farias
PERT and CPM PERT: Program Evaluation and Review Technique CPM: Critical Path Method Graphically displays project activities Estimates how long the project will take Indicates most critical activities Show where delays will not affect project Metodos Cuantitativos M. En C. Eduardo Bustos Farias
5
M. En C. Eduardo Bustos Farias
Metodos Cuantitativos M. En C. Eduardo Bustos Farias
6
M. En C. Eduardo Bustos Farias
Project Schedule Converts action plan into operating timetable Basis for monitoring & controlling project activity More important for projects than for day-to-day operations projects lack continuity of on-going functions more complex coordination needed One schedule for each major task level in WBS Maintain consistency among schedules Final schedule reflects interdependencies, departments. Metodos Cuantitativos M. En C. Eduardo Bustos Farias
7
M. En C. Eduardo Bustos Farias
Network Model Serves as a framework for: planning, scheduling, monitoring, controlling interdependencies and task coordination when individuals need to be available communication among departments and functions needed on the project Identifies critical activities and slack time Reduces interpersonal conflict Metodos Cuantitativos M. En C. Eduardo Bustos Farias
8
M. En C. Eduardo Bustos Farias
PERT / CPM PERT: Program Evaluation and Review Technique estimates probability of on-time completion CPM: Critical Path Method deterministic time estimates control both time and cost Similar purposes, techniques, notation Both identify critical path and slack time Time vs. performance improvement Metodos Cuantitativos M. En C. Eduardo Bustos Farias
9
M. En C. Eduardo Bustos Farias
PERT / CPM Definitions Activity: task or set of tasks uses resources and takes time Event: result of completing an activity: has identifiable end state at a point in time Network: combined activities & events in a project Path: series of connected activities Critical: activities, events, or paths which, if delayed, will delay project completion Critical path: sequence of critical activities from start to finish Node / Arrow (Arc) - PERT / CPM notation Metodos Cuantitativos M. En C. Eduardo Bustos Farias
10
The Basics of Using PERT/CPM
Metodos Cuantitativos M. En C. Eduardo Bustos Farias
11
The Project Network Model
Metodos Cuantitativos M. En C. Eduardo Bustos Farias
12
M. En C. Eduardo Bustos Farias
PERT / CPM Notations EOT: earliest occurrence time for event time required for longest path leading to event LOT: latest occurrence time for event EST: earliest starting time for activity LST: latest starting time for activity Critical time: shortest time in which the project can be completed Notation: AOA, AON, dummy activities Metodos Cuantitativos M. En C. Eduardo Bustos Farias
13
M. En C. Eduardo Bustos Farias
Slack Time Metodos Cuantitativos M. En C. Eduardo Bustos Farias
14
M. En C. Eduardo Bustos Farias
Project Network Metodos Cuantitativos M. En C. Eduardo Bustos Farias
15
M. En C. Eduardo Bustos Farias
Example Metodos Cuantitativos M. En C. Eduardo Bustos Farias
16
M. En C. Eduardo Bustos Farias
Partial Network How should activity K be added? Metodos Cuantitativos M. En C. Eduardo Bustos Farias
17
M. En C. Eduardo Bustos Farias
This works, but there is a better way. Metodos Cuantitativos M. En C. Eduardo Bustos Farias
18
M. En C. Eduardo Bustos Farias
Metodos Cuantitativos M. En C. Eduardo Bustos Farias
19
Earliest Time for an Event
Metodos Cuantitativos M. En C. Eduardo Bustos Farias
20
Earliest Time for Each Event
Expected time to complete the project is 44 days. Metodos Cuantitativos M. En C. Eduardo Bustos Farias
21
Latest Time for an Event
Metodos Cuantitativos M. En C. Eduardo Bustos Farias
22
Latest Time for Each Event
Expected time to complete the project is 44 days. Metodos Cuantitativos M. En C. Eduardo Bustos Farias
23
M. En C. Eduardo Bustos Farias
Slack Time Metodos Cuantitativos M. En C. Eduardo Bustos Farias
24
M. En C. Eduardo Bustos Farias
Critical Activities Metodos Cuantitativos M. En C. Eduardo Bustos Farias
25
Probabilistic Time Estimation
Metodos Cuantitativos M. En C. Eduardo Bustos Farias
26
M. En C. Eduardo Bustos Farias
Expected completion time: Based on optimistic, pessimistic, most likely Take weighted average of the 3 times TE = (a + 4m + b)/6 Uncertainty = variance (range of values) Probability of completion of project in desired time D Metodos Cuantitativos M. En C. Eduardo Bustos Farias
27
Transforming Plan to Network
Metodos Cuantitativos M. En C. Eduardo Bustos Farias
28
M. En C. Eduardo Bustos Farias
Know activities which comprise project Determine predecessor and successor activities Time and resources for activities Interconnections depend on technical interdependencies Expected completion time as soon as possible versus as late as possible Metodos Cuantitativos M. En C. Eduardo Bustos Farias
29
M. En C. Eduardo Bustos Farias
GANTT Chart Metodos Cuantitativos M. En C. Eduardo Bustos Farias
30
Gantt Charts Henry Laurence Gantt (1861-1919) Metodos Cuantitativos
M. En C. Eduardo Bustos Farias
31
M. En C. Eduardo Bustos Farias
Planned and actual progress for multiple tasks on horizontal time scale easy to read, easy to construct effective monitoring and control of progress requires frequent updating Metodos Cuantitativos M. En C. Eduardo Bustos Farias
32
Components of GANTT Chart
Activities - scheduled and actual Precedence relationships Milestones (identifiable points in project) usually represents reporting requirements usually corresponds to critical events Can add budget information Does not show technical interdependencies Need PERT network to interpret, control, and compensate for delays Metodos Cuantitativos M. En C. Eduardo Bustos Farias
33
Planning and Scheduling
Metodos Cuantitativos M. En C. Eduardo Bustos Farias
34
M. En C. Eduardo Bustos Farias
Gantt Basics Basically, a timeline with tasks that can be connected to each other Note the spelling! It is not all-capitals! Can be created with simple tools like Excel, but specialised tools like Microsoft Project make life easier Metodos Cuantitativos M. En C. Eduardo Bustos Farias
35
M. En C. Eduardo Bustos Farias
Making a Gantt chart Step 1 – list the tasks in the project Metodos Cuantitativos M. En C. Eduardo Bustos Farias
36
M. En C. Eduardo Bustos Farias
Making a Gantt chart Step 2 – add task durations Metodos Cuantitativos M. En C. Eduardo Bustos Farias
37
M. En C. Eduardo Bustos Farias
Making a Gantt chart Step 3 – add dependencies (which tasks cannot start before another task finishes) Metodos Cuantitativos M. En C. Eduardo Bustos Farias
38
M. En C. Eduardo Bustos Farias
Notes The arrows indicate dependencies. Task 1 is a predecessor of task 2 – i.e. task 2 cannot start before task 1 ends. Task 3 is dependent on task 2. Task 7 is dependent on two other tasks Electrics, plumbing and landscaping are concurrent tasks and can happen at the same time, so they overlap on the chart. All 3 can start after task 4 ends. Painting must wait for both electrics and plumbing to be finished. Task 9 has zero duration, and is a milestone Metodos Cuantitativos M. En C. Eduardo Bustos Farias
39
M. En C. Eduardo Bustos Farias
Making a Gantt chart Step 4 – find the critical path The critical path is the sequence of tasks from beginning to end that takes the longest time to complete. It is also the shortest possible time that the project can be finished in. Any task on the critical path is called a critical task. No critical task can have its duration changed without affecting the end date of the project. Metodos Cuantitativos M. En C. Eduardo Bustos Farias
40
M. En C. Eduardo Bustos Farias
MS Project can work out the critical path for you! The length of the critical path is the sum of the lengths of all critical tasks (the red tasks 1,2,3,4,5,7) which is = 10.5 days. In other words, the minimum amount of time required to get all tasks completed is 10.5 days The other tasks (6,8) can each run over-time before affecting the end date of the project Metodos Cuantitativos M. En C. Eduardo Bustos Farias
41
M. En C. Eduardo Bustos Farias
The amount of time a task can be extended before it affects other tasks is called slack (or float). Both tasks 6 and 8 can take one extra day before they affects a following task, so each has one day’s slack. Metodos Cuantitativos M. En C. Eduardo Bustos Farias
42
M. En C. Eduardo Bustos Farias
Critical tasks, by definition, can have NO slack. Tip: If ever asked Can task X’s duration be changed without affecting the end date of the project?, if it is a critical task the answer is always NO! Metodos Cuantitativos M. En C. Eduardo Bustos Farias
43
M. En C. Eduardo Bustos Farias
Benefits of CPM/PERT Useful at many stages of project management Mathematically simple Give critical path and slack time Provide project documentation Useful in monitoring costs Metodos Cuantitativos M. En C. Eduardo Bustos Farias
44
Advantages of PERT/CPM
useful at several stages of project management straightforward in concept, and not mathematically complex uses graphical displays employing networks to help user perceive relationships among project activities critical path and slack time analyses help pinpoint activities that need to be closely watched networks generated provide valuable project documentation and graphically point out who is responsible for various project activities applicable to a wide variety of projects and industries useful in monitoring not only schedules, but costs as well Metodos Cuantitativos M. En C. Eduardo Bustos Farias
45
Limitations to CPM/PERT
Clearly defined, independent and stable activities Specified precedence relationships Subjective time estimates Over emphasis on critical paths Metodos Cuantitativos M. En C. Eduardo Bustos Farias
46
Limitations of PERT/CPM
project activities must be clearly defined, independent, and stable in their relationships precedence relationships must be specified and networked together time activities in PERT are assumed to follow the beta probability distribution -- this may be difficult to verify time estimates tend to be subjective, and are subject to fudging by managers there is inherent danger in too much emphasis being placed on the critical path Metodos Cuantitativos M. En C. Eduardo Bustos Farias
47
Probabilistic PERT/CPM
Metodos Cuantitativos M. En C. Eduardo Bustos Farias
48
Mean and Standard Deviation of Project Duration
Once the expected time te for all activities has been computed, proceed to use te in place of the single activity duration in CPM to work out the critical path and the project duration The resulting project duration is the mean project duration TE We also need to work out the standard deviation of the project duration as follows: Project Duration = (Summation of i2 f all the activities on the critical path) Metodos Cuantitativos M. En C. Eduardo Bustos Farias
49
Probability of Different Project Durations
From statistics, once we know the mean project duration, TE, and the standard deviation of the project duration, we can work out the probability that the project duration will be shorter than any specific time, T (i.e. the project will take T days or less) through the following formula: Z=(T- TE )/ , where Z is the quantity called the Normal variate Knowing Z, we can read off the probability from Normal Distribution Tables which are provided in nest slides Metodos Cuantitativos M. En C. Eduardo Bustos Farias
50
Normal Distribution Table for Negative Values of Z
Probability <3.0 -1.5 3.0 -1.4 -2.9 -1.3 -2.8 -1.2 -2.7 -1.1 -2.6 -1.0 -2.5 -0.9 -2.4 -0.8 -2.3 -0.7 -2.2 -0.6 -2.1 -0.5 -2.0 -0.4 -1.9 -0.3 -1.8 -0.2 -1.7 -0.1 -1.6 0.0 Metodos Cuantitativos M. En C. Eduardo Bustos Farias
51
Normal Distribution Table for Positive Values of Z
Z | Probability 0.0 | 0.1 | 0.2 | 0.3 | 0.4 | 0.5 | 0.6 | 0.7 | 0.8 | 0.9 | 1.0 | 1.1 | 1.2 | 1.3 | 1.4 | 1.5 | Z | Probability 1.6 | 1.7 | 1.8 | 1.9 | 2.0 | 2.1 | 2.2 | 2.3 | 2.4 | 2.5 | 2.6 | 2.7 | 2.8 | 2.9 | 3.0 | >3.0| 1 Metodos Cuantitativos M. En C. Eduardo Bustos Farias
52
M. En C. Eduardo Bustos Farias
Example Consider a project with TE = 5days and =2 days.If we wish to find out the probability that the project will take 7 days or less. Thus T=7days. First, work out a value (calles the normal variate) Z, as follows: Z=(T- TE )/ =(7-5)/2=1 Read off the Normal Distribution Tables, the probability for Z=1. We get the value Thus the probability that the project will take 7 days or less is If we need to find the probability that the project takes more than 7 days, we make use of the fact that: Probability that project takes more than x days= 1-Probability that project takes x days or less Probability that project takes more than 7 days= 1-Probability that project takes 7 days or less = =0.1587 Metodos Cuantitativos M. En C. Eduardo Bustos Farias
53
Interpolating from the Normal Distribution Table
In the previous example, the ‘Z’ value was 1.0 and could be read off directly. If you had a value like 1.01, you could still round it off to 1.0 However there will be instances when you will get a value like 1.275, in which case you will need to interpolate from the table From the table Z1=1.2, P1=0.8849 Z2=1.3, P2=0.9039 Use the interpolation formula: P=P1+Z-Z1 *(P2-P1) Z2-Z1 Therefore at Z=1.275, P= * ( ) = Metodos Cuantitativos M. En C. Eduardo Bustos Farias
54
Crash and Normal Times and Costs
Activity Cost Crash $34,000 $33,000 $32,000 $31,000 $30,000 Crash Cost - Normal Cost Crash Cost/Week = Normal Time - Crash Time Crash Cost $34,000 - $30,000 = 3 - 1 $4,000 = = $2,000/Week 2 Weeks Normal Normal Cost 1 2 3 Time (Weeks) Crash Time Normal Time Metodos Cuantitativos M. En C. Eduardo Bustos Farias
55
M. En C. Eduardo Bustos Farias
CRASH COSTING 1. Find critical path. 2. Find cheapest act. in critical path 3. Reduce time until: a. Can’t be reduced b. Another path becomes critical c. Increase in direct costs exceeds savings from shortening project 4. Return to Step 1, as long as savings. Metodos Cuantitativos M. En C. Eduardo Bustos Farias
56
M. En C. Eduardo Bustos Farias
Time-Cost Trade-Off Cost Time Costs of Crashing Indirect/Penalty Costs Total Costs 10-9 Metodos Cuantitativos M. En C. Eduardo Bustos Farias
57
Beta Probability Distribution with Three Time Estimates
Probability of 1 in 100 (a) Occuring Probability of 1 in 100 (b) Occuring Optimistic Time (a) Most Likely Time (m) Pessimistic Time (b) Activity Time Metodos Cuantitativos M. En C. Eduardo Bustos Farias
58
Time Estimates (in weeks) for project
Variance = b - a 6 ( ) 2 t = a + 4m + b 6 Optimistic a Most Probable- m Pessimistic b Expected Time t = [(a + 4m + b)/6] Variance [(b - a)/6]2 Activity A B C D E F G H 1 2 3 2 3 4 3 4 6 7 9 11 2 3 4 5 3 - 1 6 ( ) 4 36 = 2 4 - 2 6 ( ) 4 36 = 2 3 - 1 6 ( ) 4 36 = 2 6 - 2 6 ( ) 16 36 = 2 7 - 1 6 ( ) 36 = 2 9 - 1 6 ( ) 64 36 = 2 11 - 3 6 ( ) 64 36 = 2 3 - 1 6 ( ) 4 36 = 2 Metodos Cuantitativos M. En C. Eduardo Bustos Farias Total 25 weeks
59
Probability of Project Meeting the Deadline
Project Standard Deviation, T = Project Variance Due Date - Expected Completion Date Z = T = = 0.57 1.76 .57 Standard Deviations Probability (T 16 Weeks) is 71.6% 15 Weeks 16 Weeks Metodos Cuantitativos M. En C. Eduardo Bustos Farias Time
60
M. En C. Eduardo Bustos Farias
PERT/Cost PERT/Cost is a technique for monitoring costs during a project. Work packages (groups of related activities) with estimated budgets and completion times are evaluated. A cost status report may be calculated by determining the cost overrun or underrun for each work package. Cost overrun or underrun is calculated by subtracting the budgeted cost from the actual cost of the work package. For work in progress, overrun or underrun may be determined by subtracting the prorated budget cost from the actual cost to date. Metodos Cuantitativos M. En C. Eduardo Bustos Farias
61
M. En C. Eduardo Bustos Farias
PERT/Cost The overall project cost overrun or underrun at a particular time during a project is determined by summing the individual cost overruns and underruns to date of the work packages. Metodos Cuantitativos M. En C. Eduardo Bustos Farias
62
Example: How Are We Doing?
Consider the following PERT network: Metodos Cuantitativos M. En C. Eduardo Bustos Farias
63
Example: How Are We Doing?
Earliest/Latest Times Activity ES EF LS LF Slack A B C D E F G H I J Metodos Cuantitativos M. En C. Eduardo Bustos Farias
64
Example: How Are We Doing?
Activity Status (end of eleventh week) Activity Actual Cost % Complete A $6, B , C , D E , F , G , H I J Metodos Cuantitativos M. En C. Eduardo Bustos Farias
65
Example: How Are We Doing?
Cost Status Report (Assuming a budgeted cost of $6000 for each activity) Activity Actual Cost Value Difference A $6, (1.00)x6000 = $200 B , (1.00)x6000 = C , (.90)x6000 = D E , (.25)x6000 = F , (.75)x6000 = G , (.50)x6000 = H I J Totals $25, $26, $- 900 Metodos Cuantitativos M. En C. Eduardo Bustos Farias
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.