Presentation is loading. Please wait.

Presentation is loading. Please wait.

Water Treatment Plant No. 2 Concentrate Zero Liquid Discharge August 30, 2011.

Similar presentations


Presentation on theme: "Water Treatment Plant No. 2 Concentrate Zero Liquid Discharge August 30, 2011."— Presentation transcript:

1 Water Treatment Plant No. 2 Concentrate Zero Liquid Discharge August 30, 2011

2 McKim & Creed, Inc. Tommy Brown, P.E. – Vice President, Project QA/QC Craig Wells, P.E. – Principal-in-Charge Phil Locke, P.E. – Senior Project Manager Ryan Popko, P.E. – Assistant Project Manager, Lead Project Engineer

3 Water Treatment Plant No. 2 Overview Membrane Softening Water Treatment Plant – Fresh groundwater wells provide the source water – Produces drinking water – Produces concentrate or “reject” stream – Concentrate discharged into Royal Palms Waterway

4 Current Plant Design Capacity Permitted production is ~6.3 Million Gallons per Day (MGD) Source water required is ~7.5 MGD Drinking water ~6.3 MGD Reject water ~1.2 MGD Concentrate Permeate Groundwater

5 Administrative Order Administrative Order for Concentrate Disposal – EPA determined current concentrate discharge permit is not allowed by the Clean Water Act – FDEP notified City that concentrate disposal permit would not be renewed – Administrative Order requires City to devise an alternate method of disposing of the concentrate

6 Background City performed an evaluation of concentrate disposal alternatives based on: – Costs – Regulatory compliance Evaluation selected Zero Liquid Discharge for Pilot Study Zero Liquid Discharge Pilot Study confirmed treatability, feasibility, and economics as favorable ― Technical feasibility ― Environmental benefits

7 Zero Liquid Discharge (ZLD) Overview Treats concentrate stream to remove excess mineral content Treated stream blended with finished water from water plant Process is integrated into existing water plant; will operate as one facility Eliminates concentrate discharge from water plant

8 No Liquid Discharge ZLD Recovered Water Concentrate Permeate Groundwater Drinking water – ~7.5 MGD Future Situation

9 Project Delivery Method City selected an Original Equipment Manufacturer (OEM) – Advertised Request for Qualifications (RFQ) Six OEMs responded Evaluation included technical process and experience information City selected three OEMs for further consideration – Advertised Request for Proposal (RFP) Evaluation included pricing information – Selected Doosan Hydro Technology

10 Project Delivery Method City selected a Design Engineer – Requested technical qualifications (RFQ) from the three firms under contract to provide utility engineering services Evaluation utilized qualifications based selection per state law – Selected McKim & Creed

11 Project Delivery Method Future Actions – Design to be performed by McKim & Creed Design will incorporate the OEM equipment that has been selected by the City Technical plans and specifications will be prepared to include equipment provided by the OEM – Advertisement for a General Contractor (GC) Price competition, based on using OEM equipment and pricing provided to City

12 Project Costs Total Estimated Project Costs $7.3M vs. $7.5M budget Construction Costs $2.15M OEM (quote) $4.00M General Contractor (still subject to bid environment) $0.24M Bidding and Engineering Services during Construction (quote) Design Costs $0.58M Engineering (quote) $0.11M OEM Services (quote) Integration Costs $0.22M Supervisory Control and Data Acquisition System (quote)

13 Benefits of Project Achieves regulatory compliance Increases water plant design capacity at build-out by ~1.2 MGD Eliminates discharge permit and associated sampling costs Meets the Consumptive Use Permit requirement for Alternative Water Supply Design incorporates City’s green initiatives – Water Conservation – Waste Recovery Delays costs associated with future expansions

14 Project Schedule Work Order issued for design: September 2011 Award construction contract: May 2012 Substantial completion and Administrative Order compliance: April 2013

15 Questions


Download ppt "Water Treatment Plant No. 2 Concentrate Zero Liquid Discharge August 30, 2011."

Similar presentations


Ads by Google