PAGE 1 DARLING HARBOUR LIVE Darling Harbour Live
2
PPAAGGEE 22 DARLING HARBOUR LIVE Entertainment Centre Pyrmont/Ultimo Powerhouse Museum Exhibition Centre Convention Centre Tumbalong Park Chinatown Darling Harbour
3
PAGE 3 DARLING HARBOUR LIVE
4
PAGE 4 DARLING HARBOUR LIVE
5
PAGE 5 DARLING HARBOUR LIVE
6
PAGE 6 DARLING HARBOUR LIVE ICC Theatre
7
PAGE 7 DARLING HARBOUR LIVE
8
PAGE 8 DARLING HARBOUR LIVE
9
PAGE 9 DARLING HARBOUR LIVE
10
PAGE 10 DARLING HARBOUR LIVE
11
PAGE 11 DARLING HARBOUR LIVE
12
PAGE 12 DARLING HARBOUR LIVE
13
PAGE 13 DARLING HARBOUR LIVE
14
PAGE 14 ICC Hotel DARLING HARBOUR LIVE Up to 900 room hotel Equity and operation currently being finalised
15
PAGE 15 Glebe Island Expo Contracts and other documents being finalised 25,000 m 2 of exhibition space with a banquet facility 1000 space car park Event Ferry and Bus shuttle service DARLING HARBOUR LIVE
16
PAGE 16 Existing Convention, Exhibition Halls demolished first half of 2014 Sydney Entertainment Centre (SEC) Car Park closes around end of January 2014 to allow demolition to commence Hoarding line around building / carparkperimeter After demolition hoarding line is modified to reflect new building form End of 2015 structure of event buildings and Boulevard substantially complete DARLING HARBOUR LIVE Preliminary Construction Staging
17
PAGE 17 End of 2015 SEC closes and is demolished to allow commencement of eastern side of Haymarket Beginning of 2016 Boulevard open and Tumbalong Park hoarded off. Tumbalong Park works completed in around 6 months End of 2016 New Core Facility, western side of Haymarket and Hotel opens Completion of eastern side of Haymarket delivered progressively with completion by early 2020’s. DARLING HARBOUR LIVE Preliminary Construction Staging (Cont)
18
PAGE 18 Monorail closed end of June 2013 Demolition follows with Darling Harbour section planned to be substantially complete by end of 2013 Convention Station and Paddy Market’s stations to be removed by early 2014 Advice indicates extension of existing Ferry Service will be difficult due to access issues Ongoing discussions with Transport and City of Sydney on improved directional signage Ongoing discussions on shuttle bus to serve western edge and Convention Centre Glebe Island Event Day Ferry Service will stop at Darling Harbour Mid 2014 – opening of Inner west Light Rail extension and Light rail frequency increased to 6 per hour [2020] – opening of CBD and South East Light Rail – connecting Darling Harbour with Circular Quay DARLING HARBOUR LIVE Transport
19
PAGE 19 Key Milestones DARLING HARBOUR LIVE ITEMDATE Preferred Bidder announced11 December 2012 Contract closed22 March 2013 Exhibition of development applications for Core Facilities and the Haymarket 27 March 2013 Close of Exhibition period10 May 2013 Exhibition of western area of Haymarket including commercial, residential and student housing Early May 2013 Exhibition of Hotel development applicationJune 2013 Construction of Glebe Island Expo commencesJune / July 2013 Closure of existing Convention & Exhibition facility8 December 2013 Glebe Island Expo OpensDecember 2013 Demolition and construction of new facilities2013 – 2016 Closure of Sydney Entertainment CentreEnd 2015 New facilities openEnd 2016
20