Download presentation
Presentation is loading. Please wait.
Published byArlene Bond Modified over 9 years ago
1
Project ManagementDay 3 in the am Project Management (PM) CHECK
2
Day 3 in the am # 2 / 24 Project ManagementCook
3
Day 3 in the am # 3 / 24 Project ManagementCook
4
Day 3 in the am # 4 / 24 Project ManagementCook
5
Day 3 in the am # 5 / 24 Project ManagementCook Earned Value Analysis EVA is a performance measurement technique that integrates scope, time, and cost data Given a baseline (original plan plus approved changes), you can determine how well the project is meeting its goals You must enter actual information periodically to use EVA
6
Day 3 in the am # 6 / 24 Project ManagementCook EVA Terminology Budgeted cost of work scheduled (BCWS) is the portion of the approved cost estimate planned to be spent on an activity during a given period Actual cost of work performed (ACWP) is the total of the direct and indirect costs incurred in doing the work on an activity during a given period Budgeted cost of work performed (BCWP), also called earned value, is the percentage of work actually completed multiplied by the cost (BCWS)
7
Day 3 in the am # 7 / 24 Project ManagementCook Earned Value Analysis (EVA)
8
Day 3 in the am # 8 / 24 Project ManagementCook Deriving EVA Metrics Weeks Elapsed = WE = ((actual task beginning) – (report date)) / 7 Weeks Performed = WP = WE * (SD)/(ED) ( note: “D” is for duration ) Where: SD = ((scheduled project beginning) - (scheduled completion)) / 7 ED = ((actual project beginning) - (expected completion)) / 7 Budgeted Cost of Work Scheduled = BCWS = BCF(1) + … BCF (WE) Where: BCF = Budgeted Cash Flow and ACF = Actual Cash Flow Budgeted Cost of Work Performed = BCWP = BCF(1) + … BCF (WP) Schedule Variance = BCWP - BCWS (measured in $, not time) Actual Cost of Work Performed = ACWP = ACF(1) + … ACF(WE) Spend Comparison = BCWS – ACWP ( commonly reported ) Cost Performance Index = BCWP / ACWP ( >1 is good ) Budgeted Performance Index = BCWP / BCWS ( >1 is good )
9
Day 3 in the am # 9 / 24 Project ManagementCook 1.Expected Completion 200__.____.____ ( 95% confidence ) 2.Δ Actual Cost ( in-house ) ____, _____ RMB ( + => expense ) 3.Δ Actual Cost ( contracted ) ____, _____ RMB ( + => overrun ) 4.Δ Actual Cost ( purchases ) ____, _____ RMB ( - => refund ) 5.Δ Quality Issues? ___ ( if “N”, then quality is presumed excellent ) 6.Δ Subcontracting Issues? ___ ( if “Y”, attach explanation ) 7.Δ Resource Issues? ( Staff, Material, Equipment ) ___, ___, ___ 8.Δ Integration/Dependency Issues? ___ 9.Δ Catastrophe Possibility? ___ 10.Δ Other Issues? ___ ( Scope, surprise, opportunity, infrastructure, … ) 11.Δ Notices ( vacations, emergencies, changes, conntact, … ): _______ _____________________________________________ Weekly Task Report (by WBS)
10
Day 3 in the am # 10 / 24 Project ManagementCook EVA Trend Analysis
11
Day 3 in the am # 11 / 24 Project ManagementCook 1.Expected Completion 20__.____.____ ( 95% confidence ) 2.Δ Actual Cost ( in-house ) ____, _____ RMB ( + => expense ) 3.Δ Actual Cost ( contracted ) ____, _____ RMB ( + => acceptance ) 4.Δ Actual Cost ( purchases ) ____, _____ RMB ( - => refund ) 5.Δ Quality Issues? ___ ( if “N”, then quality is presumed excellent ) 6.Δ Contracting Issues? ___ ( if “Y”, attach explanation ) 7.Δ Resource Issues? ( Staff, Material, Equipment ) ___, ___, ___ 8.Δ Integration/Dependency Issues? ___ 9.Δ Catastrophe Possibility? ___ 10.Δ Other Issues? ___ ( Scope, surprise, opportunity, infrastructure, … ) 11.Δ Notices ( vacations, emergencies, changes, contact, … ): ________ _____________________________________________ Weekly Task Report (by WBS)
12
Day 3 in the am # 12 / 24 Project ManagementCook Weekly Project Summary ( : ) In-House ( : %$) Contracted ( : %$) Purchases ( : %$) Schedule: % on-time (budget wtd.) % completed (budget weighted) Schedule variance (budget wtd.) Estimated completion date Estimation trend (10 week) Schedule Performance Index Serious issues open (# : trend) Cost: % within budget Estimated completion date Estimation trend (10 week) Schedule Performance Index Serious issues open (# : trend) Spent to date ($ : %) Situation: (need mgmt. help?)
13
Day 3 in the am # 13 / 24 Project ManagementCook Weekly Status Report
14
Day 3 in the am # 14 / 24 Project ManagementCook MS Reporting Capability
15
Day 3 in the am # 15 / 24 Project ManagementCook Basic Financial Terms Life cycle costing is estimating the cost of a project over its entire life Cash flow analysis is used for determining the estimated annual costs and benefits for a project Benefits and costs can be tangible or intangible, direct or indirect, but will have to be quantified Sunk cost is money spent in the past and should not be a criteria in project selection Learning curve theory – when many items are produced repetitively, unit cost decreases Reserves – money included in cost estimate Contingency reserves – allowances for future situations
16
Day 3 in the am # 16 / 24 Project ManagementCook Net Present Value Example
17
Day 3 in the am # 17 / 24 Project ManagementCook Return on Investment Return On Investment (ROI) : ROI = ((Discounted Benefits) – (Discounted Costs)) / (Discounted Costs) Breakeven Analysis: BE = ( Time when DB-DC =0) – (Time when DC began) Where: DB is Discounted Benefits and DC is Discounted Costs
18
Day 3 in the am # 18 / 24 Project ManagementCook NPV, ROI, and Payback I
19
Day 3 in the am # 19 / 24 Project ManagementCook NPV, ROI, and Payback II
20
Day 3 in the am # 20 / 24 Project ManagementCook Expected Monetary Value
21
Day 3 in the am # 21 / 24 Project ManagementCook Controlling Controlling is the process of measuring progress towards project objectives monitoring deviation from the plan taking corrective action to match progress with the plan Controlling cuts across all of the other phases of the project life cycle and involves seven knowledge areas
22
Day 3 in the am # 22 / 24 Project ManagementCook Control Processes
23
Day 3 in the am # 23 / 24 Project ManagementCook Cost Control Project cost control includes monitoring cost performance ensuring that only appropriate project changes are included in a revised cost baseline informing project stakeholders of authorized changes to the project that will affect costs Earned value analysis is an important tool for cost control
24
Day 3 in the am # 24 / 24 Project ManagementCook Concluding Remarks Questions and Answers Thank you, again. You can find a copy of this lecture (350 KB) on the Internet at: http://cha4mot.com/PM
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.