1
75 Express Lanes Project From NW 170 Street to I-595 Corridor Advisory Committee Meeting Wednesday, July 15
2
Project Team I-75 Express Fiorella Alvarez- Construction Public Information Officer Antonio Castro, P.E. – FDOT Construction Project Manager Paul Lampley, P.E. – FDOT Construction Program Manager Raj Rangaswamy, P.E. – CEI Senior Project Engineer, Target Engineering Yami Yaqub. – CEI Project Administrator, Target Engineering Ed Perez, P.E. – CEI Senior Project Engineer, Corradino Group Aurelio Matos, P.E. – CEI Senior Project Engineer, APCTE Scott Gombar, P.E. – CEI Senior Project Engineer, Eisman and Russo
3
State Road (SR) 826 from W. Flagler Street to I-75 and I-75 from SR 826 to I-595 (Total 28 miles) D4 Segment : I-75 from NW 170 Street to I-595 (15 miles) D6 Segment: SR 826 from W Flagler Street to NW 154 Street and I-75 from SR 826 to NW 170 Street (13 miles) Projects Limits
4
I-75 Express Overview From NW 170 Street (Miami-Dade County) to I-595 (Broward County) I-75 Express Project Limits
5
Scope of Work Constructing Express Lanes in the existing I-75 median Constructing ingress and egress points throughout the corridor Constructing direct connections to 595 Express, Palmetto Express and Homestead Extension of Florida’s Turnpike (HEFT) Reconstructing interchanges along the corridor Constructing sound barrier walls at various locations Installing additional traffic cameras, dynamic message signs and toll gantries Adding new signals, signage, lighting and landscaping I-75 Express Corridor wide
6
75 Express Lanes Typical Section Express Lanes – Centered in existing I-75 median Separated from the General Purpose Lanes – Two northbound and two southbound lanes Separated by concrete barrier wall – Full width paved shoulders I-75 Express
7
Express Lanes Entrance & Exit Ramps NOT TO SCALE I-75 Mainline I-75 Express
8
75 Express Lanes Entrance and Exit ramps I-75 Express Please visit our webpage to download the Entrance and Exit ramps guide
9
Segment E Overview Estimated construction completion date: Summer 2017 Construction cost: $75 million CEI: Target Engineering Group, Inc. Design-Build Team: Dragados USA/Parsons Brinckerhoff I-75 Express From North of Griffin Road to I-595
10
Segment E Construction update Current activities Building future Express Lanes in the existing median Excavating ponds for future drainage Building new bridge to connect 75 Express to 595 Express Installing drilled shafts for sign structures Future activities Complete and paint sound barrier walls Continue new bridge construction Build Express Lanes in the existing median
11
Connection Bridge to 595 Express Lanes
12
Upcoming Ramp Closures for Bridge Construction The ramp from southbound I-75 (from Naples) to eastbound 595 Express Lanes will be closed on Friday, July 24 is scheduled to reopen in summer 2016. Motorists will be able to access the 595 Express Lanes at the next entrance ramp on eastbound I-595, just west of 136 Avenue. The ramp from westbound 595 Express to I-75 northbound (to Naples) will be relocated to its final configuration, just north of the existing temporary ramp. Message boards will be placed to direct motorists to the new ramp location.
13
Segment D Overview Estimated construction completion date: Summer 2018 Construction cost: $80 million CEI: Target Engineering Group, Inc. Design-Build Team: Ranger Construction/Wantman Group I-75 Express From South of Sheridan Street to North of Griffin Road
14
Segment D Construction update Current activities Constructing sound barrier walls Sheridan Street Bridge Phase 1 construction Excavating ponds Future activities Full Closure of I-75 at Sheridan Street in July Sound barrier wall panel installation Drainage activities along segment Continue building Express lanes in existing median
15
New Improvement Features C-11 Canal Bridge I-75 Express
16
Sheridan Street Interchange I-75 Express
17
Upcoming Closures for Sheridan Bridge Construction All lanes of southbound I-75 at Sheridan Street will be closed on Thursday, July 30 to allow crews pour concrete bridge deck. Motorists will be detoured to take the exit ramp at Sheridan Street West (Exit 11B), continue westbound on Sheridan Street then turn left at Dykes Road and continue to eastbound Pines Boulevard to re-enter I-75 southbound using the Pines Boulevard on-ramp. Please follow the posted detour. All lanes of I-75 northbound at Sheridan Street will be closed on Monday, August 10 to allow crews pour concrete bridge deck. Motorists will be detoured to take the exit ramp at Sheridan Street East (Exit 11A), continue eastbound on Sheridan Street then turn left at Flamingo Road, then continue north to Griffin Road and continue westbound on Griffin Road to re-enter I-75 northbound using the Griffin Road on-ramp. Please follow the posted detour.
18
Segment C Overview Estimated construction completion date: Summer 2018 Construction cost: $85 million CEI: A&P Consulting Transportation Engineers Design-Build Team: Ranger Construction/Wantman Group I-75 Express From South of Miramar Parkway to South of Sheridan Street
19
Segment C Construction update Current activities Continuing new Pembroke Road bridge construction Continuing Miramar Parkway Bridge phase 2 construction Excavating ponds at Miramar Parkway and Pines Blvd Building future Express Lanes within existing median Constructing swale areas on the outside Completed all sound barrier wall construction Future activities Miramar Parkway Bridge phase 3 construction Continue new Pembroke Road bridge construction Anticipated bridges completion by late 2016 C-4 Canal crossing construction within existing median
20
Miramar Parkway Bridge Construction update Current Status Phase 1 completed Eastbound traffic detoured to newly constructed section Phase 2 started - demolition of existing eastbound bridge completed and pile operations commenced Future activities New end bents and piers construction
21
Phase One: Constructing a portion of the new bridge, south of the existing bridge. Miramar Parkway Interchange Construction Phasing I-75 Express EASTBOUND WESTBOUND NOT TO SCALE WORK ZONE
22
Phase Two: Shifting eastbound traffic onto the new bridge section constructed in Phase One, demolition of the eastbound section of the existing bridge, and construction of the middle section of the new bridge. Miramar Parkway Interchange Construction Phasing I-75 Express EASTBOUND WESTBOUND NOT TO SCALE WORK ZONE
23
Miramar Parkway Bridge – Phase 2 Demolition
24
Phase Three: Shifting westbound traffic onto the new bridge middle section constructed in Phase Two, demolition of the westbound section of the existing bridge, and construction of the final section of the bridge. Miramar Parkway Interchange Construction Phasing I-75 Express EASTBOUND WESTBOUND NOT TO SCALE WORK ZONE
25
Phase Four: Stripe lanes to final configuration. Miramar Parkway Interchange Construction Phasing I-75 Express EASTBOUND WESTBOUND NOT TO SCALE
26
Pembroke Road Bridge Construction update Current Status All concrete piles have been driven Constructed intermediate bridge piers MSE wall on east and west side under construction Broward County constructing bridge approaches Future activities Broward County complete bridge approaches Completion of bridge end bents Erect beams and pour bridge decks Anticipated bridge completion by late 2016
27
Pembroke Road Bridge
28
Segments A & B Overview Estimated construction completion date: Spring 2019 Construction cost: $234 million CEI: The Corradino Group Design-Build Team: Community Asphalt/Wantman Group I-75 Express From NW 170 Street (Miami-Dade County) to South of Miramar Parkway
29
Segments A&B Construction update Current activities Constructing Snake Creek canal bridge Excavating ponds along segment Building Express Lanes within existing median Clearing vegetation along several communities Future activities Complete sound barrier wall installation Continue Express Lanes bridges and ramps Continue building Express lanes in existing median
30
Snake Creek canal bridge
31
Proposed I-75/HEFT Interchange I-75 Express Northbound Turnpike to Northbound I-75Southbound I-75 to Southbound TurnpikeSouthbound I-75 Express to Southbound TurnpikeSouthbound I-75 to Northbound TurnpikeSouthbound Turnpike to Southbound I-75 & Miami Gardens DriveSouthbound Turnpike to Northbound I-75Southbound Turnpike to Northbound I-75 ExpressNorthbound I-75 to Northbound TurnpikeMiami Gardens Drive to Northbound TurnpikeNorthbound Turnpike to Northbound I-75 Express Existing Movement to RemainNew MovementExisting Movement to RemainNew Movement N
32
Ground Mounted Sound Barrier Walls To be completed by 2017 Direct coordination with affected communities Hours of construction – Daytime work only – No weekend work I-75 Express
33
Shoulder Mounted Sound Barrier Walls Shoulder mounted Sound Barrier Walls Completed with roadway construction Direct coordination with affected communities I-75 Express
34
Sound Barrier Wall Location Segment E Benefited communities Highland Ranch Estates New River Estates Woodgate Condos Vista Filare Royal Palm Forest Oak I-75 Express
35
Sound Barrier Wall Location Segment D Benefited communities Sheridan Glen The Crossbow Waverly Hundred Falcon’s Lea Waterford Hawkes Bluff Ivanhoe Estates Chelsea I-75 Express
36
Sound Barrier Wall Location Benefited communities Windsor at Miramar Villas at Nautica Cobblestone Townhomes Towngate Segment C I-75 Express
37
Sound Barrier Wall Locations Benefited communities Royal Landings West Lakes Estates Century Gardens Lakes on the Green Marbella Park West Riviera Isles Huntington Courtyards at Nautica Segments A & B I-75 Express
38
What to Expect Lane closures during non-peak hours Signage will be placed to guide motorists Public Information updates via electronic mail, postcards and project website Heavy equipment and construction crews in and around area Trucks and construction vehicles entering and exiting the work zones I-75 Express
39
Projected Express Lane Openings Partial Express Lanes Opening (North of Griffin Rd to I-595) in Spring 2017 Full Express Lanes Opening (NW 170 th Street to I-595) in Summer 2018 Construction Completion in Spring 2019 Construction Schedule I-75 Express
40
Stay Informed Sign up for Construction Updates and Lane Closure Information: I-75 Express Project Public Information Officer Fiorella Alvarez (954) 548-2754 fiorella@iscprgroup.com Next Corridor Advisory Meeting will be on Wednesday, August 26 at 10 a.m. I-75 Express
41
For more information please visit our website at www.75-express.com Stay Informed
42
We welcome your questions. I-75 Express