Pohang Accelerator Laboratory POSTECH EPICS Collaboration Meeting 2004 @ RICOTTI, Tokai, JAPAN The status of PLS EPICS application EPICS collaboration meeting 2004 Dec 8 - 10, 2004 RICOTTI, Tokai, JAPAN Pohang Accelerator Laboratory Kiman Ha, M.Y Oh, J.H Kim, J.M Kim, J.W. Lee, J.C. Yun, J.H Choi hkm@postech.ac.kr
2
Pohang Accelerator Laboratory POSTECH Outline EPICS Collaboration Meeting 2004 @ RICOTTI, Tokai, JAPAN -Present status of PLS -New project PAL-XFEL -Summary
3
Pohang Accelerator Laboratory POSTECH Feedback status EPICS Collaboration Meeting 2004 @ RICOTTI, Tokai, JAPAN -November, Orbit feedback operation started for user service. -Orbit stability with feedback short term (1 hour) : < 1 m long term (12 hours) : < 3 m -22 sets of V and H corrector PS are involved for orbit feedback This has been a big issue at PLS, with epics based control system. BPM, PS, ID’s are necessary elements of the feedback operation
4
Pohang Accelerator Laboratory POSTECH EPICS status EPICS Collaboration Meeting 2004 @ RICOTTI, Tokai, JAPAN - Most control system upgraded to EPICS Power Supply BPM RF Modulator ID control
5
Pohang Accelerator Laboratory POSTECH Hardware platforms EPICS Collaboration Meeting 2004 @ RICOTTI, Tokai, JAPAN - VME MVME5110 – 15, BPM, Corrector, RF Operation MVME5500 for RTEMS test - PC Windows Quad MPS, Beam current, ID - PC Linux Kicker, Septum - Power MAC G4 Epics PV monitoring Web Server
6
Pohang Accelerator Laboratory POSTECH Used epics software toolkit EPICS Collaboration Meeting 2004 @ RICOTTI, Tokai, JAPAN -Matlab CA: Global orbit feedback -Ca : Operator panel, correction utility -MEDM : Operator panel -EDM : Operator panel -Gateway -Web based PV monitoring >mySQL >PHP >GNU plot -Oracle based Web server
7
Pohang Accelerator Laboratory POSTECH More upgrade plan and testing EPICS Collaboration Meeting 2004 @ RICOTTI, Tokai, JAPAN -LINUX IOC kernel upgrade 2.6 -RTEMS MVME5500 IOC tested >Environment ready >BSP(from kate Feng) and example IOC tested at MVME5500 >AsynDriver 4.0 tested E2050B with HP3458 GPIB
8
Pohang Accelerator Laboratory POSTECH PAL-XFEL layout EPICS Collaboration Meeting 2004 @ RICOTTI, Tokai, JAPAN Storage Ring Linac FEL-3 fs-FIR FEL-1 FEL-2 FEL injector PAL XFEL Project Period: 2005-2009 Budget: 80 M$ SASE FEL Energy: 0.7 - 3 GeV FEL-1: 10~50 nm FEL-2: 2 ~ 5 nm FEL-3: 0.1 ~ 0.3 nm
9
Pohang Accelerator Laboratory POSTECH Status for PAL-XFEL EPICS Collaboration Meeting 2004 @ RICOTTI, Tokai, JAPAN -October, established task force team for XFEL design -Review of construction budget -Review of Beam line -Review of Linac Microwave -Review of Diagnostics -Review of Safety
10
Pohang Accelerator Laboratory POSTECH XFEL control system status EPICS Collaboration Meeting 2004 @ RICOTTI, Tokai, JAPAN We are collecting FEL control system applications from LCLS, DESY,.. -Timing -Modulator -Power Supply -BPM -Diagnostic
11
Pohang Accelerator Laboratory POSTECH Summary EPICS Collaboration Meeting 2004 @ RICOTTI, Tokai, JAPAN - PLS, successfully upgraded to epics based control system Easily accessible by high level users Very stable control and feedback -PAL-XFEL project will require highly enhanced hardware and software