Download presentation
Published byBarnaby Nicholson Modified over 9 years ago
1
Optimization for Operation of Power Systems with Performance Guarantee
by Gokturk Poyrazoglu University at Buffalo, SUNY Department of Electrical Engineering
2
Electricity Supply Chain
Consumer Distribution Transmission Generation
3
Optimal Power Flow Problem
Dispatch Generating Units while minimizing Total Cost In a single time period ( i.e. 1 hour) Standard form of NLP min 𝑥 𝑓 𝑥 subject to 𝑔 𝑥 = ℎ 𝑥 ≤ 𝑥 𝑚𝑖𝑛 ≤𝑥≤ 𝑥 𝑚𝑎𝑥 Non-convex Feasible Region of OPF Courtesy of EDF Energy
4
Unit Commitment t=5 t=4 t=3 t=2 Time t=1
Select and Dispatch Generating Units while minimizing Total Cost In a multi time period ( i.e. 1 day or 1 week) t=5 t=4 t=3 t=2 Time t=1
5
Unit Commitment with DC Model
Select and Dispatch Generating Units while minimizing Total Cost In a multi time period ( i.e. 1 day or 1 week) t=5 t=4 t=3 t=2 Time t=1
6
Security Constrained Unit Commitment
Secure transaction between two consecutive periods 𝑥 3 𝑥 1 ∗ 𝑥 5 ∗ 𝑥 2 ∗ 𝑥 4 ∗ 𝑥 3 ∗ t=5 t=4 t=3 t=2 Time t=1
7
Power Systems Modeling
Quadratic Cost function Min and Max Capacity Limits Bus2 Bus1 Bus3 G1 G2 Load Max Power Flow Limits Power Balance Equalities Min and Max Voltage Limits Bus G Load
8
Transmission Switching Simulation VS Reality
Bus2 Bus1 Bus3 G1 G2 Load
9
University at Buffalo, SUNY Department of Electrical Engineering
PART I Optimal Topology Control with Physical Power Flow Constraints and N-1 Contingency Criterion This study was partially published in the following journal and conferences. University at Buffalo, SUNY Department of Electrical Engineering
10
Problem Definition AC OPF with optimal topology control:
AC Optimal Power Flow: Nonlinear and nonconvex programming (NLP or QCQP) AC OPF with optimal topology control: Mixed integer nonlinear and nonconvex programming (MINLP) Same N-1 reliability consideration as the original topology Line contingencies Large-scale problem
11
Challenges Comparison of OPF solutions among multiple topologies
NLP solvers seek for a local optimum Guarantee a better topology? NLP solutions may not reflect the quality of the global solution Therefore, comparison between two NLP solutions does not guarantee optimal topology
12
Range for the global optimizer
Approach Semi-Definite Programming (SDP) relaxes nonconvex feasible range of OPF SDP may find a feasible solution = the global solution SDP solution provides a lower bound of the global optimizer Global solution is sandwiched between an SDP and a local solution Upper Bound by an NLP Solver : possibly a local optimizer Range for the global optimizer Lower Bound by an SDP Solver: possibly infeasible solution
13
Optimal Power Flow (OPF) Problem
Quadratic Cost function Definition of Real and Reactive Power Flows (Bi-directional flow) Voltage Magnitude Reliability Limits Real and Reactive Power Balance Maximum Power Flow Limits (bi-directional flow) Real and Reactive Generation Capacity Limits The vector x is lifted up to a matrix W = Convex feasible region OPF problem is given in the form of Non-convex Quadratically Constrained Quadratic Programming (QCQP)
14
SDP Relaxation Real and Reactive Real and Reactive Generation Capacity
Power Balance Real and Reactive Generation Capacity Limits & Voltage Magnitude Reliability Limits Maximum Power Flow Limits(bi-directional flow) Schur Compliment of Quadratic Cost function Positive Semi-definite Matrix & Reference Angle
15
Topology Χ and Υ (original topology)
SDP Relaxation Topology Χ and Υ (original topology) Utilize the sandwich structure of the global solution NLP solution of Χ < SDP solution of Υ ≤ Global solution of Υ A local optimizer of Χ is better than the global optimizer of Υ Topology Χ Topology Υ Aim to find such a topology Χ in this study
16
Search for a Better Topology
NLP solution to Υ SDP solution to Υ NLP solution to Χ Candidate for Χ Step I: Candidate for Χ: Guaranteed a better topology than Υ Step II: Check the same N-1 reliability criterion as ones for Υ
17
Parallel Algorithm AC Transmission Topology Control with N-1 Reliability Criterion
SOLVE NLP SEPERATE CHECK CONDITIONS SOLVE SDP
18
Computation Time
19
Simulation Environment
Modified IEEE 30 bus system 6 generators 39 lines + 2 tie lines Generation capacity: 360 MW Peak load: 320 MW Area 2: load pocket High cost for generators Gen 5 and Gen6 Computation with a Linux server with GHz
20
Operating Cost Up to 10% cost reduction
21
Real Power Losses Reduced losses Increased losses
22
Conclusion Efficient algorithm to implement topology control in the restructured electricity market experiments Identified topology Guaranteed a better one Satisfy the same reliability criterion Topology control finds a solution with Decreased system cost but Losses may increase
23
University at Buffalo, SUNY Department of Electrical Engineering
PART II Scheduling Maintenance for Reliable Transmission System (The SMaRTS Model) This study will be partially published in the following journal and conferences. University at Buffalo, SUNY Department of Electrical Engineering
24
What is the SMaRTS Model?
Scheduling Maintenance for Reliable Transmission System Combination of studies on power economics Security Constrained Unit Commitment Transmission Topology Control Outage Coordination N-1 Reliability Criterion TTC N-1 SCUC SMaRTS
25
Security Constrained Unit Commitment (SCUC)
Selection of generator units Minimize total operating cost Security on ramp up and ramp down of units Mixed Integer Linear Programming (MILP) Being used widely in business
26
Transmission Topology Control (TTC)
Selection of branches to keep in service Minimize total operating cost Security on ramp up and ramp down of units Mixed Integer Linear Programming (MILP) No reported use in business
27
Challenges of Topology Control
Transient Stability Concerns Switching effect Cost of Switching Who will pay? Financial Transmission Rights (FTR) Market Unwillingness of market participants
28
The Proposed Model : SMaRTS
Transmission lines require Preventive Maintenance Schedule maintenance Optimal time Follow same procedure No stability concern No extra cost for switching No impact on FTR market
29
Feasible Region of SMaRTS
No outage request SMaRTS = Unit Commitment Outage requests on all lines SMaRTS = Topology Control SMaRTS SCUC TTC
30
Business-As-Usual VS The SMaRTS
31
Problem Formulation Objective Function: No Load Cost of Generators ($)
Generation ($) No Load Cost of Generators ($) min 𝜃, 𝑃 𝐺 , 𝑃 𝑘 ,𝑢 𝑠,ℎ,𝑧,𝑚,𝑎 𝑡 𝑔∈Γ 𝐶 𝑔 𝑃 𝑔,𝑡 𝐺 𝛽 + 𝑔∈Γ 𝑁𝐿 𝑔 𝑢 𝑔,𝑡 + 𝑔∈Γ 𝑆𝑈 𝑔 𝑠 𝑔,𝑡 + 𝑘∈Ψ 𝑃𝑀 𝑘 𝑡 𝑚 𝑘,𝑡 − 𝑎 𝑘 In per unit Start-Up Cost of Generators ($) Partial Maintenance Cost ($)
32
Power Balance Constraints & Power Flow Definitions
𝑃 𝑘𝑖𝑗,𝑡 ≤ 𝐵 𝑘 𝜃 𝑖,𝑡 − 𝜃 𝑗,𝑡 + 1− 𝑧 𝑘,𝑡 𝑀 , ∀𝑡, 𝑘∈Ψ 𝑃 𝑘𝑖𝑗,𝑡 ≥ 𝐵 𝑘 𝜃 𝑖,𝑡 − 𝜃 𝑗,𝑡 − 1− 𝑧 𝑘,𝑡 𝑀 , ∀𝑡, 𝑘∈Ψ 𝑃 𝑘𝑖𝑗,𝑡 = 𝐵 𝑘 𝜃 𝑖,𝑡 − 𝜃 𝑗,𝑡 , ∀𝑡, 𝑘∈Ψ θ 𝑟𝑒𝑓,𝑡 = , ∀𝑡 𝑔∈Γ 𝑃 𝑔 𝑖 ,𝑡 𝐺 − 𝑃 𝑖,𝑡 𝐷 = 𝑘∈ 𝑖,∗ 𝑘∈Ω 𝑃 𝑘𝑖𝑗,𝑡 − 𝑘∈ ∗,𝑖 𝑘∈Ω 𝑃 𝑘𝑖𝑗,𝑡 , ∀𝑡, 𝑖∈ Φ 𝐺 − 𝑃 𝑖,𝑡 𝐷 = 𝑘∈ 𝑖,∗ 𝑘∈Ω 𝑃 𝑘𝑖𝑗,𝑡 − 𝑘∈ ∗,𝑖 𝑘∈Ω 𝑃 𝑘𝑖𝑗,𝑡 , ∀𝑡, 𝑖∈ Φ/Φ 𝐺 Power flow definitions - Maintenance requested Lines - Other lines Reference Voltage Angle Real Power Balance Equalities
33
Box Constraints Generation be in between capacity limits
𝑃 𝑔 𝐺,𝑚𝑖𝑛 𝑢 𝑔,𝑡 ≤ 𝑃 𝑔,𝑡 𝐺 ≤ 𝑢 𝑔,𝑡 𝑃 𝑔 𝐺,𝑚𝑎𝑥 , ∀𝑡, 𝑔∈Γ −𝑃 𝑘 𝑚𝑎𝑥 𝑧 𝑘,𝑡 ≤ 𝑃 𝑘𝑖𝑗,𝑡 ≤ 𝑧 𝑘,𝑡 𝑃 𝑘 𝑚𝑎𝑥 , ∀𝑡, 𝑘∈Ψ −𝑃 𝑘 𝑚𝑎𝑥 ≤ 𝑃 𝑘𝑖𝑗,𝑡 ≤ 𝑃 𝑘 𝑚𝑎𝑥 , ∀𝑡, 𝑘∈ Ω Ψ −𝑅 𝑔 ≤ 𝑃 𝑔,𝑡 𝐺 − 𝑃 𝑔, 𝑡−1 𝐺 ≤ 𝑅 𝑔 , ∀𝑡, 𝑔∈Γ Generation be in between capacity limits Max. Power flow limits are enforced The change in generation should be applicable.
34
Maintenance Scheduling Constraints
Definition of maintenance start variable Definition of approval status & Limitation on partial maintenance (optional) Limit on maintenance duration Complete maintenance in planning horizon
35
Unit Commitment Constraints
𝑠 𝑔,𝑡 − ℎ 𝑔,𝑡 = 𝑢 𝑔,𝑡 − 𝑢 𝑔, 𝑡−1 , ∀𝑡, 𝑔∈Γ 𝜏=𝑡− 𝑝 𝑔 +1 𝑇 𝑠 𝑔,𝜏 ≤ 𝑢 𝑔,𝑡 , ∀𝑡, 𝑔∈Γ 𝜏=𝑡− 𝑤 𝑔 +1 𝑇 ℎ 𝑔,𝜏 ≤1− 𝑢 𝑔,𝑡 , ∀𝑡, 𝑔∈Γ Definition of unit commitment variables Limit on minimum up-time Limit on minimum down-time
36
Numerical Example Modified 30-bus system
IEEE Reliability Test Case Data Low power transfer between Areas 13 MW Hourly Peak Data is from IEEE Reliability Test Case - A summer weekday
37
Requested Maintenance Starting Period
Outage Requests Line ID From Bus To Bus 15 4 12 10 7 6 18 8 9 38 28 3 31 24 25 Business-as-Usual Model Transmission Owner submit TIME Line ID Requested Maintenance Starting Period 15 Hour 8 7 Hour 6 18 Hour 12 9 Hour 15 38 Hour 20 31 Hour 9
38
Total Operating Cost ($) Total Operating Cost ($)
Results The Optimal Solution The SMaRTS Model Business-as-Usual Model Total Operating Cost ($) Approved Line ID(s) 53,051.83 --- 1 52,807.70 7 2 52,725.15 7, 18 3 52,722.56 7, 18, 9 4 52,722.47 7, 18, 9, 31 5 52,723.99 7, 18, 9, 31, 38 6 52,841.17 All Total Operating Cost ($) Approved Line ID(s) 53,051.83 ---- 1 53,054.75 38 2 53,062.72 38, 9 3 53,094.97 38, 9, 7 4 53,204.15 38, 9, 7, 18 5 54,264.13 38, 9, 7, 18, 31 6 55,030.72 All
39
Total Operating Cost ($) Total Operating Cost ($)
Decision Support BUSINESS-AS-USUAL MODEL Total Operating Cost ($) Approved Line ID(s) 53,051.83 ---- 1 53,054.75 38 2 53,062.72 38, 9 3 53,094.97 38, 9, 7 4 53,204.15 38, 9, 7, 18 5 54,264.13 38, 9, 7, 18, 31 6 55,030.72 All SMaRTS THE SMaRTS MODEL Total Operating Cost ($) Approved Line ID(s) 53,051.83 --- 1 52,807.70 7 2 52,725.15 7, 18 3 52,722.56 7, 18, 9 4 52,722.47 7, 18, 9, 31 5 52,723.99 7, 18, 9, 31, 38 6 52,841.17 All
40
The SMaRTS Model with N-1 Reliability
University at Buffalo, SUNY Department of Electrical Engineering
41
N-1 Reliability Criterion
3 2 G D Loss of Transmission Lines Loss of Generators B C 1 3 2 G D A C 1 3 2 G D A B 1 3 2 G D A B C 1 3 2 G D A B C 1 3 2 G D Status of Transmission Line at time t Status of Transmission Line at contingency c
42
Proposed N-1 Reliability The 3rd index
C 1 3 2 G D Time t & Contingency c zk, t, c : status of Line k Pkij, t, c : power flow on Line k Pg, t, c : power generation at Gen g Contingency Elements Status of Transmission Lines Time
43
Discarding 3rd index by Physical Property
1 3 2 G D Time t & Contingency c zk, t, c : status of Line k Pkij, t, c : power flow on Line k Pg, t, c : power generation at Gen g Loss of Transmission Lines B C 1 3 2 G D A C 1 3 2 G D zk, t, A = zk, t, 0 ,∀k – A zk, t, A = zk, t, 0 , k = A Pkij, t, A ≠ Pkij, t, 0 ,∀k Pg, t, A ≠ Pg, t, 0 ,∀k zk, t, B = zk, t, 0 ,∀k – B zk, t, B = zk, t, 0 , k = B Pkij, t, B ≠ Pkij, t, 0 ,∀k Pg, t, B ≠ Pg, t, 0 ,∀k
44
Utilizing Physical Meaning
Discard 3rd index & a variable Transmission Line Contingency Enforce the flow to be ZERO Generation Contingency Enforce the generation to be ZERO
45
Numerical Example Modified 30-bus system
IEEE Reliability Test Case Data Low power transfer between Areas Hourly Peak Data is from IEEE Reliability Test Case - A summer weekday Tie lines Radial Lines
46
Requested Maintenance Starting Period
Outage Requests Line ID From Bus To Bus 15 4 12 10 7 6 18 8 9 38 28 3 31 24 25 Business-as-Usual Model Transmission Owner submit TIME Line ID Requested Maintenance Starting Period 15 Hour 8 7 Hour 6 18 Hour 12 9 Hour 15 38 Hour 20 31 Hour 9
47
Results Business-as-Usual Model The SMaRTS Model
Total Operating Cost ($) Approved Line ID(s) 53,781.71 --- 1 53,756.47 7 2 53,753.67 7, 18 3 53,736.75 7, 18, 31 4 7, 18, 31, 38 5 Infeasible - 6 infeasible Total Operating Cost ($) Approved Line ID(s) 53,781.71 ---- 1 53,783.72 38 2 53,795.89 38, 7 3 53,842.87 38, 7, 18 4 54,211.41 38, 7, 18, 31 5 Infeasible - 6 The SMaRTS Model w/ no Partial Maintenance Total Operating Cost ($) Approved Line ID(s) 53,781.71 --- 1 53,772.01 7 2 53,773.44 7, 38 3 53,790.29 7, 18, 38 4 53,833.21 7, 18, 31, 38 5 Infeasible - 6 infeasible
48
Results
49
Impact of N-1 Reliability
50
PART I - SDP Based Transmission Topology Control
Conclusion PART I - SDP Based Transmission Topology Control AC Model with physical flow limits Up to 9% cost reduction Guaranteed to find a better topology PART II - The SMaRTS Model A new method to utilize Transmission Switching in Outage Coordination Method to discard additional variable for N-1 Up to 4% daily cost reduction NYISO - daily operating cost is $15 Million.
51
Gokturk Poyrazoglu gokturkp@buffalo.edu
Thank you. Gokturk Poyrazoglu University at Buffalo, SUNY Department of Electrical Engineering
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.