Meeting Agenda 11-05-13 (1)Overview ( 概观 ) (2)Ongoing interview and Data Collection (SEAS) ( 进行 的访谈和数据收集 ) (3)Input sheet update and NN training(GT) (

Similar presentations


Presentation on theme: "Meeting Agenda 11-05-13 (1)Overview ( 概观 ) (2)Ongoing interview and Data Collection (SEAS) ( 进行 的访谈和数据收集 ) (3)Input sheet update and NN training(GT) ("— Presentation transcript:

1 Meeting Agenda 11-05-13 (1)Overview ( 概观 ) (2)Ongoing interview and Data Collection (SEAS) ( 进行 的访谈和数据收集 ) (3)Input sheet update and NN training(GT) ( 输入更新 ) (4)Ongoing tasks ( 进行中任务 ) (5)Approaching Dates ( 日期 ) (6)Timeline ( 时间安排 )

2 (1) Overview ( 概观 ) Previous Week and Current Week: –NN training with simulated data and KPI provided by SEAS. (GT) ( 用仿真的数据以及 SEAS 提出的输出指标來使用人工神经 ) –Input sheet update. ( 更新输入 ) Next Week: –Continue NN training using more mathematical models ( 使用更多 的数学模式来训练神经网络 ) –Verification of NN ( 验证人工神经 )

3 (2) Ongoing Interview and Data Collection SEAS will lead the discussion. – Any updates to be reported. – New update on KPI

4 (3) NN training NN will be trained by creating data and the KPI’s provided by SEAS will be used as the output value. ( 用仿真的数据以及 SEAS 提出的 输出指标來训练人工神经 ) – Check for compatibility (Completed) ( 检查兼容性 ) – Simulate data (Completed) ( 模拟数据 ) – Use a mathematical model (polynomial, exponential etc) to generate output (In progress) ( 使用的数学模型 ( 多项式,指数等 ) ,以生成输 出 ) – Train the NN using the simulated data and outputs generated by the mathematical model (In progress) ( 用模拟数据以及数学模型模拟输 出来训练人工神经 ) – Generate new input and outputs using the mathematical model (In progress) ( 采用数学模型, 生成新的输入和输出 ) – Validate the NN using the new inputs and outputs (In progress) ( 使用 新的输入和输出验证人工神经 )

5 (4) Ongoing Tasks NN simulation data generation and simulation. GT ( 人工神經仿真数据生成和 仿真 ) Input excel update. GT and SEAS ( 输入 Excel 更新 ) Historic data collection and scheduler interviews. SEAS ( 历史数据收集和采访 )

6 (5) Approaching Dates Interview and historic production data: SEAS (tentative) SEAS visit to GT (Confirmation between 11/5- 11/7).

7 As of 11-05-2013 Tasks Month AugustSeptemberOctoberNovemberDecember CompletedWork Plan CompletedIntelligent Matrix CompletedLiterature Survey OngoingInterview and Data Collection Completed Selection of ILE modeling methods and case study CompletedPredictive Modeling Module DelayedSEAS visit CompletedPrognotic Module CompletedModification of ILE for case study In progressModification of ILE for SEAS test bed GT visit Improving ILE


Download ppt "Meeting Agenda 11-05-13 (1)Overview ( 概观 ) (2)Ongoing interview and Data Collection (SEAS) ( 进行 的访谈和数据收集 ) (3)Input sheet update and NN training(GT) ("