EE/CS 480/481 19/17/2015 10:28:58 PM University of Portland School of Engineering Project Burnside Programmable Logic Solar Radiant Heating System Team Arturo Bimrose Troy Heynderickx Jon Sakkos Advisor Dr. Wayne Lu, Dr. Ken Lulay Industry Representative Mr. Jonathan Fant
2
EE/CS 480/481 2 University of Portland School of Engineering Overview Introduction Scorecard Additional Accomplishments Plans Issues/Concerns Conclusions 9/17/2015 10:28:58 PM
3
EE/CS 480/481 3 University of Portland School of Engineering Introduction 9/17/2015 10:28:58 PM Programmable Logic Solar Radiant Heating System
4
EE/CS 480/481 4 University of Portland School of Engineering Scorecard Previously: –Received LCD, controller, sensors –Got programmer –Got many misc. components Completed: –TOps finished “Your team has chosen a great project and you are doing a first-rate job with the design and engineering.” –LCD programming –Defined ME construction space Shortcomings: –No serial bus testing, no pump/valve routines tested. –No keypad, transformer, solid state relays/transistors and diodes (mosfet) –U of P did not provide us with facilities to construct mechanical portion 9/17/2015 10:28:58 PM
5
EE/CS 480/481 5 University of Portland School of Engineering Additional Accomplishments ME construction started Gathered important materials for ME construction Two possible pumps Resolved budget issues 9/17/2015 10:28:58 PM
6
EE/CS 480/481 6 University of Portland School of Engineering Plans Construct major mechanical components Construct microcontroller portion to work with keypad, LCD, and pumps Integration 9/17/2015 10:28:58 PM
7
EE/CS 480/481 7 University of Portland School of Engineering Milestones NumberDescriptionOriginal 09 Oct 08 Previous 28 Jan 09 Present 24 Feb 09 4Define Controller Routines17 Nov 0825 Nov 08 5Circuit Design17 Nov 08 6Theory of Operations Draft24 Nov 0825 Nov 08 7Order Electronics29 Nov 08 8ToOps version 1.0 30 Jan 09 7 Feb 09 9 Start Constructing Mechanical System 01 Feb 09 10Receive Electronics16 Feb 09 21 Feb 09 11Construct Controller23 Feb 09 12System Integration15 Mar 09 9/17/2015 10:28:58 PM
8
EE/CS 480/481 8 University of Portland School of Engineering Concerns/Issues “Tweakers” stealing copper from project Serial bus issues 9/17/2015 10:28:58 PM
9
EE/CS 480/481 9 University of Portland School of Engineering Conclusions Assured by industry representative Pump obscurity now clear Project completely compartmentalized –Everyone is getting components done 9/17/2015 10:28:58 PM