1
Certificate IV in Project Management Week 3 – Scope Management Course Number Qualification Code BSB41507
2
In Class Example Throughout the semester we will work on an example Project together: We have recently started a boutique travel agency and we need to put together a new type of small group trip overseas. It will be a small guided group, with 1 guide and no more than 12 participants. No children as allowed. The expected duration is 3 weeks. The idea is to make it a premium experience with no expense spared. Options being considered are - Skiing in USA, Gourmet tour of Southern France, Wine and food experience in New Zealand including a flight around Mount Cook We need to produce a holiday package including a decision on which holiday to go with, then contracts with suppliers, marketing and an estimate of the profit per trip. Adapated from PMBOK 4th Edition
3
Definition of Project Scope
What is project scope? Why is it important? Adapated from PMBOK 4th Edition
4
Definition of Project Scope
Project Scope is – the work that must be performed to deliver a product, service or result as per the specifications or requirements concerned with what is included in the project and what is excluded from the project determined at a high level during the project initiation phase and expanded in the planning phase generally determined by the Project Sponsor, expanded by the Project Manager and then reconfirmed with the Project Sponsor defined by the boundaries or range for the project including constraints, assumptions and dependencies related to the objectives, outcomes, requirements Adapated from PMBOK 4th Edition
5
Importance of Project Scope
Why is it important? Gives the Project Manager concrete goals Ensures the objectives of the Project Sponsor are met Provides the basis for expectation management, monitoring and reporting Determines the baseline against which project success can be measured
6
What is a Project Sponsor?
The Project Sponsor is critical during the development of project scope and has a key role to play during project execution. They are the person for whom the project is being undertaken and they will directly benefit from the deliverables and outcomes of the project. The Project Manager needs to ensure that the Project Sponsor has approved the Project Scope so that there are no misunderstandings about the breadth and outcomes of the project. The Project Sponsor is often a senior manager, customer or external client.
7
Characteristics of Project Scope
Poor control over project scope is one of the common reasons for project failure Projects that never seem to finish are normally suffering from a failure to control scope Project scope is defined at a high level during the early stages of the project and then progressively refined Assumptions often required High level becoming detailed Measures project success Refined during the project Constraints will be applied Changes need to be monitored
8
Project Scope Interrelationships
Scope is related to Project Time, Project Cost and project Quality Sometimes referred to as the ‘triple constraint’ Scope expansion and contraction has flow on impacts to Time, Cost and Quality Trade offs between all four relationships are possible Cost Scope Time Quality
9
Project Scope Interrelationships
Increased Cost Scope Increases when Time Fixed leads to and/or Additional Resources If the project scope is increased when the project timeframe must remain fixed then normally the overall cost will need to increase as more resources are added in order to complete the additional work
10
Project Scope Interrelationships
Extra Time Scope Increases when Cost Fixed leads to and/or Reduced Quality If the project scope is increased and the project cost must remain fixed then normally the overall timeframe will need to be extended to allow extra time for the additional work to be undertaken (this assumes that there is no cost involved in extending the resources for a longer period). It may also be possible to compromise on quality in order to speed up execution so that no additional time is required, thereby reducing pressure on the budget.
11
Project Scope Interrelationships
Reduced Time Scope Decreases lead to and/or Reduced Cost When scope is decreased then it may be possible to reduce both the project cost and timeframe. Scope reduction is a common reaction to overall budget cuts within an organisation.
12
Project Scope Processes - Part 1
PMBOK Project Scope Management Processes - 5.1 Collect Requirements 5.2 Define Scope 5.3 Create Work Breakdown Structure 5.4 Verify Scope 5.5 Control Scope Related processes from Project Integration Management – 4.1 Develop Project Charter 4.2 Develop Project Management Plan 4.5 Perform Integrated Change Control PMBOK 4th Edition
13
4.1 Develop Project Charter
The process of developing a document that formally defines and authorises a project by documenting the initial requirements that will satisfy the needs of the Project Sponsor and stakeholder The high level Project Scope is formulated during this process The Project Charter establishes a partnership between the Project Sponsor or client and the Project Manager Occurs during the Initiation Phase Initiation Planning Execution Close Monitor Control Adapted from PMBOK 4th Edition
14
4.1 Develop Project Charter
Inputs into the Project Charter - Business need or rationale Product and project description Strategic Plan Business Case Regulations and standards Contractual requirements Methodologies, policies and procedures Adapted from PMBOK 4th Edition
15
4.1 Develop Project Charter
Common contents of a Project Charter – Project purpose or justification Project objectives – should be measurable Project description High level requirements High level risks or overall risk analysis Preferred timeframe Estimated high level budget High level project structure – Project Sponsor, Project Manager Authorisation or Governance processes PMBOK 4th Edition
16
Types of Project Charters
You may know a Project Charter by a different name as they can vary depending on your industry or the particular methodology being applied Some common names for Project Charters include – Project Brief Concept Paper High Level Plan Statement of Work Sample Project Charter templates are available to download from the links as you enter the Learning Programme for the Course Site – check which bit!!!
17
Project Objectives It is critical that the project objectives and success criteria and measurable, otherwise progress and success are difficult to achieve The recommended method is SMART Make sure all your objectives are – S pecific M easurable A chievable R ealistic, and T ime Bound An example?
18
Project Charter There are templates of Project Charters on the Scope Site. We will look at the Project Charter Basic template for our project.
19
4.2 Develop Project Management Plan
This is the process of defining and documenting the actions necessary to prepare and integrate all subsidiary plans for each of the 8 key knowledge areas of project management. Good practice dictates that the Project Management Plan is baselined at the end of the Planning Phase, particularly in the areas of scope, cost and time It is progressively updated during project execution via the Perform Integrated Change Control process (PMBOK 4.5) Initiation Planning Execution Close Monitor Control Adapted from PMBOK 4th Edition
20
4.2 Develop Project Management Plan
The planning processes for all project management key knowledge areas are normally performed at the same time this process, or expanded upon shortly afterwards The relationship to Scope, Time and Cost is slightly different to the other areas of Communication, Risk, Human Resources, Quality and Procurement There are no stand alone Scope, Time or Cost Planning processes, they contained within the Develop Project Management Plan process The other key knowledge areas have discrete processes for planning that are defined in their process groups Adapted from PMBOK 4th Edition
21
4.2 Develop Project Management Plan
The Project Management Plan – can be composed of subsidiary plans for each of the 8 key knowledge areas or these planning elements can be included into one integrated end product can be either high level or detailed depending on the characteristics of the project and the project management methodology that is being applied Can only be changed via a Change Request once it has been baselined defines how all aspects of the project are to be undertaken through the Execution Phase establishes the mechanisms and processes to Monitor and Control the project defines how the project is to be Closed Initiation Planning Execution Close Monitor Control Adapted from PMBOK 4th Edition
22
4.2 Develop Project Management Plan
Inputs into the Project Management Plan – Project Charter Subsidiary plans developed in other planning processes Industry standards and regulations Organisational policies and procedures Project management methodology Project management tools Planning templates Knowledge from past projects Expert judgement and advice Initiation Planning Execution Close Monitor Control Adapted from PMBOK 4th Edition
23
4.2 Develop Project Management Plan
Common inclusions in the Project Management Plan – Project lifecycle and project management processes Selected tools and techniques Project objectives and how these will be achieved Change Management Plan Baselines for Scope, Time and Cost Performance measurement and status reporting processes Governance structure Team structure Subsidiary plans if required Initiation Planning Execution Close Monitor Control Adapted from PMBOK 4th Edition
24
Scope Management Plan The Scope Management Plan is a critical output of this process and is critically connected to the process to Define Scope (5.2) Good practice is to assemble the different scope definition and planning outputs into one integrated document Common inclusions in the Scope Management Plan – Project scope statement Scope baseline Processes to Monitor and Control scope Configuration management (advanced concept, often applied to Information Technology projects) Change Control process Assumptions, dependencies and constraints Initiation Planning Execution Close Monitor Control Adapted from PMBOK 4th Edition
25
How do we know what to put into a Project Management Plan?
5.1 Collect Requirements How do we know what to put into a Project Management Plan? The process of defining and documenting the needs of stakeholders Encompasses the requirements related to the specific characteristics of any end products being delivered by the project Large projects will often define the requirements at a high level during this process and then allow for a more detailed requirements definition process at the beginning of project execution Relates to project success measures Occurs during Planning Initiation Planning Execution Close Monitor Control Adapted from PMBOK 4th Edition
26
5.1 Collect Requirements Inputs to Collect Requirements
Project Charter Stakeholder needs and expectations Rough specifications Tools and techniques to Collect Requirements Ranking Questionaries Brainstorming Focus groups Interviews Surveys Observation Mind Mapping Prototype Workshops Research Adapted from PMBOK 4th Edition
27
5.1 Collect Requirements Common requirements documentation includes –
Objectives and success measures Functional requirements – how an end product must perform Non functional requirements – not related to product performance, could include optional characteristics, cosmetic details and other organisational requirements Quality requirements Acceptance criteria Support and training requirements Assumptions and constraints Initiation Planning Execution Close Monitor Control Adapted from PMBOK 4th Edition
28
5.1 Collect Requirements Outputs of this process include –
Requirements documentation as per previous slide Requirements Management Plan (advanced concept, often applied to large Information Technology, Defence and Engineering projects) Detailed plan of how the requirements will be planned, tracked and reported Especially important where the project is large enough to have a Requirements Workstream or Sub-Project Requirements Traceability Matrix (advanced concept, often applied to large Information Technology, Defence and Engineering projects) Links requirements to their origin in order to trace them through the project lifecycle Can be linked to objectives, high level requirements, testing Adapted from PMBOK 4th Edition
29
5.2 Define Scope The process of developing a detailed description of the project and end products A detailed scope statement is critical to project success Refines high level deliverables and dependencies Clarifies and resolves assumptions and constraints documented during the Initiation phase Good practice dictates that the detailed scope must be signed off by the Project Sponsor and key stakeholders Undertaken during Planning Initiation Planning Execution Close Monitor Control Adapted from PMBOK 4th Edition
30
5.2 Define Scope The inputs into Define Scope are –
Project Charter Requirements Documentation The outputs from Define Scope are – Project Scope Statement Product scope description Product acceptance criteria Project deliverables and exclusions Project assumptions and constraints Project dependencies Initiation Planning Execution Close Monitor Control Adapted from PMBOK 4th Edition