Presentation is loading. Please wait.

Presentation is loading. Please wait.

TVA Sequoyah and Watts Bar Nuclear Plants

Similar presentations


Presentation on theme: "TVA Sequoyah and Watts Bar Nuclear Plants"— Presentation transcript:

1 TVA Sequoyah and Watts Bar Nuclear Plants
Feedwater Control System Upgrades – Lessons Learned Scott Gladney Digital Upgrade Program Manager 1/23/13

2 Key Project Goals Replace obsolete Foxboro H-Line components
Continued K1 Relay issues Limited Replacement Controllers/Modules Reduce single point vulnerabilities (~40/unit) Multiple unit trips due to K1/Local Remote select switch issues Original design relied on single power feeds for critical components Ease Operator Burden Improve automatic control capability at low power Automate feedwater valve transfer (SQN) Auto Balance feedpumps during second pump start Reduce operator actions during instrument malfunctions

3 Project History - Sequoyah
Project to replace NSSS and BOP controls is started 2002 – Original project cancelled due to engineering budget and schedule issues Fall 2007 – Feedwater Controls portion of the Project is restarted 09/08 – Unit 1 Factory Acceptance Test 11/08 - Unit 1 Installation delayed from R16 to R17 due to Procedures 02/09 – Unit 2 Factory Acceptance Test 11/09 - U2R16 - Unit 2 Feedwater Controls Installation 11/10 – U1R17 - Unit 1 Feedwater Controls Installation

4 Project History – Watts Bar
Fall 2007 – Feedwater Controls and Boric Acid Blend Controls Replacement Project is started in conjunction with Sequoyah 07/09 – Unit 1 Project Cancelled 03/10 – U1R10, original scheduled installation 10/10 – Unit 1 Project resurrected, up-scoped due to WBN2 01/12 – All DCS but FW removed from U1R11 Outage 04/12 – Unit 1 Factory Acceptance Test 11/12 – U1R11 - Unit 1 Feedwater Controls Installation 04/14 – U1R12 - Scheduled remainder of DCS install (Major BOP/NSSS Control)

5 System Enhancements Replaced selector switch driven Feed/Steam Flow channel selection with software average and failure detection Removed ~40 single point failure vulnerabilities per unit such as hand stations, power supplies, inputs, etc. All new system power comes from diverse sources Redundant output cards used for critical control functions Channel segregation used to protect inputs on hardware failure Automated operator critical functions such as valve transfer (Sequoyah) and placing second main feed pump in service Enabled full automatic control from startup to full power (2% to 100% power at Sequoyah).

6 System Acceptance Testing
Factory Acceptance Testing Medium Fidelity Simulated Model Failure Mode Testing Network Broadcast Storm Power failure (including transmitter input and power supply) Component Failures Parameter updates (block reset) EMI/RFI Testing Performed in-house at a TVA lab Used to validate results from Foxboro and 3rd parties No changes required due to this testing Development system Used for Engineering Code testing Used for OPS procedure development Used for Maintenance procedure development Software Review Complete review of software settings Function testing to ensure analyzed timing still valid

7 Simulator Testing Additional Validation Testing performed on simulator
Used to validate system response Controller tuning developed separately based on existing analog tuning settings and empirical models Used to test failure modes and system response Eagle Rack Failure/Lockup Transmitter/Instrument Failures Loss of Power Supply(s) Design Enhancement due to lessons learned Previously unknown plant design issue on loss of Vital Instrument Power Board locking a turbine runback in

8 Implementation Issues
Simulator U2 installed first, U1 referenced simulator Malfunctions had to be recreated, new ones developed Training Generic training vs. specific training Generic Training for everyone vs. Maintenance Experts Procedures FW Controls affected hundreds of procedures across Maintenance, Engineering and Operations Understaffing of procedure writers delayed implementation one cycle at Sequoyah Significant changes to Operations Abnormal Operating procedures and General Operating Procedures Materials Large modification with lots of parts suppliers, track to ensure all parts are ordered and on-site Bench calibrate items like transmitters, valve positioners, etc before the outage Quantity of piece parts required due to retrofitting in old cabinets

9 Implementation Issues (cont.)
Challenges Remaining rack analog hardware in-service during rack modifications Re-use of existing racks at Sequoyah Extensive Control Board Modifications Poorly documented or labeled internal cabinet wiring in original plant cabinets

10 System Testing Outage Testing Startup Testing
Loop tests integrated with normal outage activities Hardware calibration verification done pre-installation Testing performed parallel to installation Startup Testing Intentional Process upsets to validate tuning Main Feed Pump Output Step Change Feedwater Flow Step Change Steam Generator Level Setpoint Step Change Monitoring of normal startup transients

11 Post Implementation Issues
All Problems are because of the DCS The new controls will be initially blamed for plant problems till proven otherwise Different characteristic response isn’t necessarily bad New or enhanced monitoring capability Legacy issues will come to the surface as “new” problems Valve Setup Measurement problems Feedpump/Heater oscillations Establish Performance Requirements beforehand Specific Issues Sequoyah Unit 2 Thermal Power Oscillation Initially blamed on DFW modification Sequoyah Unit 1 Reactor Trip Missed PMT of Steam Dump Controller (relocated old analog controller) Watts Bar Unit 1 Down Power I/P transducer issues on Main Feedwater Reg Valves

12 Lessons Learned Dedicated Team Simulator testing invaluable
A dedicated team for the project needs to be selected early and turnover kept as low as possible throughout the project Includes Maintenance, Ops, Engineering, and Training. Simulator testing invaluable Great for proof of concept, training, experimental tuning, etc Do NOT tune the plant system to the simulator and expect it to be perfect Utilize new racks if possible Create a highly integrated schedule (Mods, Maintenance, Testing, Ops) Material Verification Place hands on parts well prior to outage Establish holding area for project parts

13 Future Plans Complete moving the NSSS/BOP Critical Control Functions into DCS Pressurizer Pressure and Level CVCS Volume Control Boric Acid Blending Steam Dumps and Atmospheric Reliefs Automatic Rod Control module Upgrade Main Feed Pump turbine controls Main Feed Reg Valve positioner upgrade

14 Any Questions?


Download ppt "TVA Sequoyah and Watts Bar Nuclear Plants"

Similar presentations


Ads by Google