INSTALLATION OF UNDERGROUND WIRING SYSTEM IN A NEW DEVELOPING TOWN! Project Name !
3
Project Members
4
To perk up the customary of living Corporate Agenda
5
To cope with the problems that occur due to the typical electricity transmission lines Maximum Possibility of cable impairments Irregular supply of electricity Maximum Possibility of injuries Background
6
Project will be benefited to : Mitigate damages to power lines structure and system Restore power quickly People are much secured. To elude transport difficulties in town Project Reimbursement
7
Install best underground wiring system to provide 24/7 electricity supply Provide safe and secured environment to people To make the town adductive Project Objectives
8
Electric Cables Digging Sand Concrete Cover Acquiring Labor Technical Staff Project will Comprise
9
Bad weather may cause problems Some resistance of sand during digging Constraints
10
Project wont be interrupted by telecom, gas and sewerage pipes Electricity supply wont be interrupted by other sources Smooth supply of electricity to consumers Key Assumptions
11
The project manager Finance manager Civil contractor HR manager Project Team Work
12
Project Manager Finance Manager Marketing Manager HRM Manager Civil Manager Asst. Manager Asst. Manager Asst. Manager Supervisor AccountantAdvisorAdministratorForeman CashierPromoterClerkLabor Activities
13
A. Selection of Material B. Selection of digging Channels C. Tender Floating D. Tender Accepting E. Procurement F. Digging G. Sand laying H. Cable Line I. Putting Concrete cover J. Check Post Selection K. Digging for check post L. Tiles laying Activities
14
ActivityPredecessor Time(Days) A ---3 B A5 C B4 D C 4 E D2 F D7 G F,E3 H G5 I H4 J H2 K J5 L K,I6
15
E=2 Dummy Activity A=3 B=5 C=4D=4 G=3 H=5 I=4 L=6 F=7 J=2 K=5 123457891112 10 6 Network Diagram
16
Contains only one critical path A-B-C-D-F-G-H-J-K-L = 44 days Dates to remember : Starting : Ist Feb,2008 Ending : 22nd march,2008 Time Duration : 44 days(Excluding 7 holidays) Critical Path
17
Material Procurement : Rs 20,000 Marketing Cost : 5,000 Training Cost : 4,000 Contractor Payment : 15,000 Transportation Cost : 3,000 Labor Cost : 20,000 Other Cost : 10,000 Total Cost : 77,000 Budget
18
? Any Query