1 NORWEGIAN SOCIAL SCIENCE DATA SERVICES MADIERA Project Management

2 NORWEGIAN SOCIAL SCIENCE DATA SERVICES Overview Kick-Off Dec 2002 Dec 2003 Dec 2004 Dec 2005 Prototype Beta VersionVersion 1.0 WP1 Quality Assurance Plan WP2 User Analysis WP4 Metadata Geo-referencing WP5 Thesaurus WP6 Content for testing WP2 Usability WP4 Metadata Geo-referencing Comparative data WP5 Thesaurus WP6 Content for testing WP2 Usability WP4 Metadata Geo-referencing Comparative data Naming/Identification WP5 Thesaurus WP6 Content Guidelines Workshops Content WP7 Dissemination Version 1.1 Hyperlinked Information Space Version 1.0 Hyperlinked Information Space Version 2.0 WP2 Usability WP4 Metadata Guidelines Recommendations Geo-referencing Comparative data Naming/Identificat WP5 Thesaurus Guidelines Languages WP6 Content Guidelines Workshops Content WP7 Dissemination WP2 Usability WP4 Metadata Guidelines Recommendations Geo-referencing Comparative data Naming/Identificat WP5 Thesaurus Guidelines Languages WP6 Content Guidelines Workshops Content WP7 Dissemination WP8 Exploitation

3 NORWEGIAN SOCIAL SCIENCE DATA SERVICES Project Management Project Steering Committee (PSC) Project Co-ordinator(CO) Project Manager (PM) Project Co-ordination Committee (PCC) Co-ordination Team (CT) European Commission

4 NORWEGIAN SOCIAL SCIENCE DATA SERVICES Project Steering Committee (PSC) The PSC is the highest management board of the project. It will consist of one representative from each principal contractor. It will be chaired by the project co-ordinator. The PSC provides the overall policy, direction and management of the project. The PSC will be responsible for all formal decisions regarding project strategy and eventual amendments to the Project Work Description (Technical annex). It will approve project objectives and reports from the CT and the Coordinator. The PSC will be responsible for allocation of resources, decisions on intellectual property rights, and conflict resolution.

5 NORWEGIAN SOCIAL SCIENCE DATA SERVICES Co-ordinator / Project Manager be responsible for the coordination and the day-to-day running of the project be responsible for all communication with the European Commission report on project progress to the PSC inform partners about the decisions of PSC work in close collaboration with the CT maintain contacts with all partners ensure that each partner deliver their work in time provide administrative support to the partners in kind of transfer of funds and coordination of cost statement between the Commission and partners as well as help with organising workshops ensure that the timetable is maintained and all deliverables completed according to work-plan and project intentions. Ensure that financial contributions to partners are connected to in time delivery of contributions. Maintain the internal project website

6 NORWEGIAN SOCIAL SCIENCE DATA SERVICES Co-ordination Team (CT) Day to day management will be carried out by the three largest contractors: NSD, UKDA and Nesstar. Bjarne Øymyr, NSD Ken Miller, UKDA Jostein Ryssevik, Nesstar A small team is considered essential for easy communication and planning, but this team will be expanded as necessary and will liase with the principal contractors, who include all work package leaders, at very regular intervals, via fortnightly tele-conferences.

7 NORWEGIAN SOCIAL SCIENCE DATA SERVICES Project Co-ordination Committee (PCC) The broader management will be carried out by the Project Co-ordination Committee (PCC). This is composed of the work package leaders and this ensures that at least one member from each principal contractor is involved. The Co-ordinator will chair it and it will meet three times per year to review project progress and to ensure that the project meets all objectives, milestones and deliverables. Forthnightly tele-conferences Meeting notes, minutes and action plans, will be taken care of by the project administrator, to be appointed by NSD. At least twice during the project it will meet with all contractors, including the assistant contractors, to review project progress and address wider issues of project strategy, including dissemination and exploitation.

8 NORWEGIAN SOCIAL SCIENCE DATA SERVICES Work Packages Leaders WP1 Project Management (Bjarne Øymyr, NSD) WP2 User Analysis and Usability (Anne Sofie Fink, DDA) WP3 The Technical Platform (Jostein Ryssevik, Nesstar) WP4 Metadata Development (Atle Alvheim, NSD) WP5 Language (Ken Miller, UKDA) WP6 Content Provision (Ken Miller, UKDA) WP7 Dissemination (Sami Borg, FSD) WP8 Exploitation (Simon Musgrave, Nesstar)

9 NORWEGIAN SOCIAL SCIENCE DATA SERVICES Communication Internal Project Web Site –deliverables status –all documents (memos, reports) –links to demonstrators etc. –meeting minutes E-mail –mailing list Instant Messenger Teleconferences

10 NORWEGIAN SOCIAL SCIENCE DATA SERVICES MADIERA...has started! Summary and Action Points

11 NORWEGIAN SOCIAL SCIENCE DATA SERVICES Madiera has started

12 NORWEGIAN SOCIAL SCIENCE DATA SERVICES Getting Started...

13 NORWEGIAN SOCIAL SCIENCE DATA SERVICES Getting Started...

14 NORWEGIAN SOCIAL SCIENCE DATA SERVICES Another View of Dependencies

15 NORWEGIAN SOCIAL SCIENCE DATA SERVICES Progress Plan Dec 2002 Dec 2003 Dec 2004 Dec 2005 Start-up 1.1 Project Initiation Doc 3.1 Functional Spec/Design 5.1 Thesaurus Guidelines 1.2 Quality Assurance Plan 2.1 User Analysis Report 3.2 MADIERA Prototype 7.1 Dissemination Plan 2.3 Usability test 3.3 Beta Version 4.1 Geo-ref Recomm. 6.1 Content - Guidelines 2.2 Usability test 4.2 Meth. Comparison 3.4 Madiera Ver 1.0 4.3 Name/Ident Rec. 5.2 Adm. framework Thesaurus 6.2 User Guides/Training Packs 6.3 Hyperlinked Info.space ver 1 6.4 Data Archive Workshop 6.5 Content Metadata Workshop 7.3 User Guides /Training packs 8.1 TIP (Tech implementation plan) 8.2 Workshop – non-archive providers 5.3 Extended thesauri 6.6 Hyperlinked IS ver2 2.4 Usability test 4.4 Revised Rec. 5.4 Evaluation Workshops 1.3 Final Report 2.5 Usability report 3.5 Version 1.1 5.5 Thesaurus hierarchies 8.3 Final TIP

16 NORWEGIAN SOCIAL SCIENCE DATA SERVICES Action Each contractor E-mail info about staff Instant messenger Tips about links etc. to the internal website

17 NORWEGIAN SOCIAL SCIENCE DATA SERVICES Action Workpackage Leaders Dec 6 th –slides – presentations in this meeting –links to relevant resources (ELSST, papers) Dec 13 th –overview - tasks that have to start now –presentations from this meeting for the website Dec 31 st –split the workpackage into subtasks –deadlines and responsibilities Continuously –Provide links to relevant material

18 NORWEGIAN SOCIAL SCIENCE DATA SERVICES Action Co-ordination Dec 13 th –presentations from this meeting for the website –meeting minutes Dec 31 st –templates for timesheets Jan 10 th –full project plan (input from wpl) where tasks are split into sub-tasks with deadlines and responsibilities –revised meeting plan –system for monitoring resources Continuously –update the websites –arrange teleconferences as needed

19 NORWEGIAN SOCIAL SCIENCE DATA SERVICES The Result