Download presentation
Presentation is loading. Please wait.
Published byEustacia Stafford Modified over 9 years ago
1
2005 Pinnacle West Capital Corporation Special Open Meeting of the Arizona Corporation Commission 2005 Summer Assessment March 18, 2005 Arizona Public Service Company Steve Wheeler – Executive Vice President Jan H. Bennett – Vice President, Customer Service Cary B. Deise – Director, Transmission Operations and Planning March 18, 2005 Arizona Public Service Company Steve Wheeler – Executive Vice President Jan H. Bennett – Vice President, Customer Service Cary B. Deise – Director, Transmission Operations and Planning
2
2 Overview Westwing Update Load/Resources Adequacy Transmission Adequacy Planned Maintenance Activities Contingency Planning Coordination/Training Future Plans Conclusions Westwing Update Load/Resources Adequacy Transmission Adequacy Planned Maintenance Activities Contingency Planning Coordination/Training Future Plans Conclusions
3
3 Westwing Update Jan Bennett Westwing Update Jan Bennett
4
4 Original Schedule n One transformer scheduled to arrive each week starting March 30th n T-1 bank scheduled to be back in service before summer peak n Replacement of BPA unit scheduled to follow T-1 installation n Replacement of spare to follow BPA replacement n One transformer scheduled to arrive each week starting March 30th n T-1 bank scheduled to be back in service before summer peak n Replacement of BPA unit scheduled to follow T-1 installation n Replacement of spare to follow BPA replacement
5
5 Issue Identified n The schedule has been revised First two of seven transformers did not pass initial testing Corrections required before units could be shipped Manufacturer was on schedule prior to the initial test results Continuing to work with manufacturer on revised schedule n The schedule has been revised First two of seven transformers did not pass initial testing Corrections required before units could be shipped Manufacturer was on schedule prior to the initial test results Continuing to work with manufacturer on revised schedule
6
6 Revised Schedule n Mid-JuneBPA replacement unit commissioned n Mid-JulyThe T-1 Bank commissioned n By year-endThe original two transformers in the T-4 Bank and the spare unit will be in service - Removed units will become spares - Sale pending on BPA unit n Mid-JuneBPA replacement unit commissioned n Mid-JulyThe T-1 Bank commissioned n By year-endThe original two transformers in the T-4 Bank and the spare unit will be in service - Removed units will become spares - Sale pending on BPA unit
7
7 The Issue n Gassing occurred during testing that indicates a hot spot Results are similar for both units Unit One has been un-tanked All connections inspected All internal components inspected Tanks shunts removed Problem has been identified and corrections are being made to all units n Consultation with Jim Templeton on test procedures and corrective action n Gassing occurred during testing that indicates a hot spot Results are similar for both units Unit One has been un-tanked All connections inspected All internal components inspected Tanks shunts removed Problem has been identified and corrections are being made to all units n Consultation with Jim Templeton on test procedures and corrective action
8
8 The Issue
9
9 Actions Taken n APS and SRP sent technical teams to Canada to work with ABB n Notified all owners n Consulted with independent experts on the issue n Made ABB aware of the critical need for this equipment n APS and SRP sent technical teams to Canada to work with ABB n Notified all owners n Consulted with independent experts on the issue n Made ABB aware of the critical need for this equipment
10
10 Next Steps n Corrections will be made first to units one and five Unit one has been un-tanked Unit five is yet to be tanked Allows for quickest delivery of one unit to replace BPA unit n Corrections will be made first to units one and five Unit one has been un-tanked Unit five is yet to be tanked Allows for quickest delivery of one unit to replace BPA unit
11
11 Summary n With the replacement of the BPA transformer we will have adequate capacity to meet our load under expected conditions Full capacity and redundancy will be restored with the installation of the new T-1 bank n The problem has been identified and corrections are being made n We do not anticipate any voluntary or involuntary curtailment of customer load this summer n ABB is working diligently to remedy the problem n With the replacement of the BPA transformer we will have adequate capacity to meet our load under expected conditions Full capacity and redundancy will be restored with the installation of the new T-1 bank n The problem has been identified and corrections are being made n We do not anticipate any voluntary or involuntary curtailment of customer load this summer n ABB is working diligently to remedy the problem
12
12 Summer Preparedness Cary Deise Summer Preparedness Cary Deise
13
13 312 MW 2-Xfmr Banks 1-BPA Xfmr Reconfigured 11,172 MW 2005 1,240 MW 3-Xfmr Banks 12,100 MW 2005 530 MW 2-Xfmr Banks 1-New Xfmr Normal 11,390 MW 2005 2-Xfmr Banks 1-BPA Xfmr Reconfigured 10,800 MW 2004 10,003 MW 2004 Valley Peak Load Valley Maximum Load Serving Capability 10,860 MW Forecast 2005 Valley Peak Westwing Update 6,000 7,000 8,000 9,000 10,000 11,000 12,000 MW
14
14 APS Peak Load Forecast 6954 MW 2005 Forecast 6402 MW 2004 Actual Loads/Resources Adequacy 8.6% Phoenix is the second fastest-growing metropolitan area in U.S. Adding 160 APS customers every day
15
15 Fuel n Nuclear Full requirements under contract. n Coal Cholla Current inventory and contract commitments provide adequate coal for the projected 2005 burn. 43 days of inventory on the ground. n Nuclear Full requirements under contract. n Coal Cholla Current inventory and contract commitments provide adequate coal for the projected 2005 burn. 43 days of inventory on the ground. Loads/Resources Adequacy
16
16 n Coal (cont.) Four Corners Mine mouth plant with full supply contract in effect. 30 days of inventory on the ground by May. n Gas 85% of supply is under contract Firm transportation contracts with EPNG in effect. Fuel oil back-up at the Yucca, West Phoenix and Saguaro Plants. n Coal (cont.) Four Corners Mine mouth plant with full supply contract in effect. 30 days of inventory on the ground by May. n Gas 85% of supply is under contract Firm transportation contracts with EPNG in effect. Fuel oil back-up at the Yucca, West Phoenix and Saguaro Plants. Fuel, continued Loads/Resources Adequacy
17
17 APS Resources – Existing Generation Fuel TypeCapacity - MW Nuclear1107 Coal1725 Gas1054 Oil 70 Other 5 Total3961 Loads/Resources Adequacy
18
18 Resources – Existing PWEC/Other APS Committed Capacity – MW Redhawk1020 Saguaro 76 West Phoenix 640 Sundance 325 Total2061 Plant Loads/Resources Adequacy
19
19 Resources Generation 2005 (MW) Existing Generation 3961 PWEC/Other2061 Subtotal6022 Long-term Contracts Pacificorp Exchange 480 SRP 364 Subtotal 844 Market Contracts 900 Total Resources 7766 Generation 2005 (MW) Existing Generation 3961 PWEC/Other2061 Subtotal6022 Long-term Contracts Pacificorp Exchange 480 SRP 364 Subtotal 844 Market Contracts 900 Total Resources 7766 Loads/Resources Adequacy
20
20 APS System Load and Resources 812 MW Loads/Resources Adequacy
21
21 Substation Transformers NEWXfmr Banks n 69/12kV15 n 115/69kV 1 n 230/69kV 1 n 500/69kV 1 UPGRADED n 69/12kV 8 n 230/69kV 5 n 345/230kV 1 Total32 NEWXfmr Banks n 69/12kV15 n 115/69kV 1 n 230/69kV 1 n 500/69kV 1 UPGRADED n 69/12kV 8 n 230/69kV 5 n 345/230kV 1 Total32 Transmission Adequacy
22
22 Transmission Lines Line Sections New n 69kV4 Upgraded n 69kV9 Line Sections New n 69kV4 Upgraded n 69kV9 Transmission Adequacy
23
23 APS EHV System Transmission Capacity less wheeling obligations 500kV 345kV N.Gila Kyrene Four Corners Palo Verde Westwing Yavapai Pinnacle Peak Cholla Saguaro Moenkopi Navajo Mead 236 MW 559 MW 315 MW 782 MW 1175 MW 615 MW 1683 MW 2380 MW 1107 MW 140 MW 310 MW Rudd Jojoba Gila River Generation Capacity Transmission Capacity Transmission Adequacy
24
24 APS EHV System 5248 MW 4969 MW Tx to Load = 4998 MW Purch Tx = 250 MW 279 MW Transmission Adequacy
25
25 Yuma Maximum Load Serving Capability 375 MW Forecasted Peak 60 MW 2004 Peak 347 MW Transmission Adequacy 435 MW 375 MW 100 150 200 250 300 350 400 450 20042005 MW Generation & Transmission
26
26 n APS Planned Maintenance Scheduled to be completed by May 31: Palo Verde 2 & 3 Cholla 2 Navajo 1 Four Corners 1 and 5 W. Phoenix Combined Cycle 1 – 3 and CT 1 & 2 Saguaro Steam 1 & 2 and CT 1 & 2 Yucca CT 1-4 Ocotillo Steam 1 & 2 and CT 1 & 2 Douglas CT Generation Planned Maintenance
27
27 Transmission n Key lines/substations on schedule n Special emphasis on critical transformers n Tree trimming in northern area due to damage from snow storms n Key lines/substations on schedule n Special emphasis on critical transformers n Tree trimming in northern area due to damage from snow storms Planned Maintenance
28
28 Contingency Planning Jan Bennett Contingency Planning Jan Bennett
29
29 Contingency Planning n Updated Load Curtailment Plans will be filed with ACC by June 1, 2005 Essential Critical Major-use customers/other with notice Other n EMS Load Shedding program annual update by May 16, 2005 n Coordination with emergency organizations Contingency Planning
30
30 Emergency Equipment n Mobile 69/12kV Transformers n Emergency Towers Two Lindsey towers LocationXfmrs Phoenix4 Flagstaff2 Yuma1 Total7 Contingency Planning
31
31 Training & Drills Cary Deise Training & Drills Cary Deise
32
32 Training & Drills n Regional Black Start DrillMarch n Usage of Load Curtailment toolsApril n Summer StudiesMay n Transmission Path OperationsMay n Emergency OperationsMarch-June Power Simulator n NERC policies addressingMarch-June emergency operations n DOE simulator trainingMarch-Oct. n Regional Black Start DrillMarch n Usage of Load Curtailment toolsApril n Summer StudiesMay n Transmission Path OperationsMay n Emergency OperationsMarch-June Power Simulator n NERC policies addressingMarch-June emergency operations n DOE simulator trainingMarch-Oct. Coordination / Training
33
33 EHV Transmission Future Plans
34
34 West Valley 230kV Future Plans
35
35 East Valley 230kV 345KV 2 0 0 9 J/O (SRP) ( S R P ) TO RACEWAY NE3 2010 ( S R P ) T B D Substation locations and line routings depict an electrical connection only and donot reflect any assumed physical locations or routing. Future Plans
36
36 Conclusions Steve Wheeler Conclusions Steve Wheeler
37
37 Conclusions Adequate resources to meet load and reserve requirements Sufficient transmission to import remote generation and purchases Plans in-place to respond to extreme conditions Coordination/training has been established with various State and local agencies Anticipate meeting customers needs Adequate resources to meet load and reserve requirements Sufficient transmission to import remote generation and purchases Plans in-place to respond to extreme conditions Coordination/training has been established with various State and local agencies Anticipate meeting customers needs
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.