Detailed Program March 2011 to September 2011 goal – allow the winery to be self-sustainable in water & energy
3
Best Value Competition June 2011 to January 2012 Advertisement & Prequalification 17 Teams submit Prequalification Packets, June 2011 Prequalification consists of required elements (pass/fail) and scoring (48 points possible) based on experience of team and individuals 5 Teams interviewed, August 2011 Design Build Competition 3 Teams selected to prepare designs and bid price Two one-on-one sessions with each team, Nov & Dec 2011 Bids Received Bid date, January 2012 Detailed evaluation with points awarded Best value price determined
4
Project Award March 2012
9
Passive Design clerestory windows and shading devices
12
Optimize Design reduce loads insulate well daylight reduce infiltration address thermal breaks passive cooling
13
WALL Exterior Wall 4 inch insulated wall panel over Snap-R 1 inch EPS spacer over 10 inch girt (11in batt insulation) = R-55.7
14
ROOF Roof 6 inch insulated roof panel over 12 inch metal girt with batt insulation = R-70
15
specified double wall insulated dampers on all envelope penetrations provided thermal and load bearing insulation pads at structural steel connections Thermal Bridging
17
Challenges: maintain building interior temperature between 50 and 80 degrees F WITHOUT the use of any active mechanical systems net zero site energy Software Selection: IES vs Epro Thermal / Energy Modeling
18
Where to Look? Net Zero Energy Building Tip: Understand building physics Infiltration Opaque Envelope Windows
19
Infiltration construct an airtight building followed ASTM E1827-11 single point method for air tightness looking for rate less than 0.1 cfm/sf door blower test, identify leaks with smoke guns actual leakage 0.08 cfm/sf
20
once load reduced, use night flush through one fan with thermal storage in internal concrete walls and slab Net Zero Energy Building Tip: Understand micro climate Mechanical Solution
21
Temperature Results
23
Energy Results
24
If 6 months results are extrapolated to one year, Total Building Energy consumption = 3,588 kWh That is 1.44 kBtu/sq.ft-year Modeled was 1.66kBtu/sq.ft-year Energy Results Net Zero Energy Building Tip: Model accurately