p. 1Mario Deile – TOTEMino: Infrastructure Status and Schedule Mario Deile 29.08.2006 1.Zone 2.Gas system 3.Cabling 4.Cooling water 5.Counting-Room 6.Safety 7.Schedule
2
p. 2Mario Deile – Zone
3
p. 3Mario Deile – Zone
4
p. 4Mario Deile – Setup (Side View) Cables trays ready 1 ground line per tray (both connected to the 1 common ground of the area, no loops so far) power outlets on the 4 support pillars and on the fence
5
p. 5Mario Deile – Setup (Top View)
6
p. 6Mario Deile – Gas System Green: done by central supply group Blue: (to be) done by F. Hahn’s group Red: to be done by TOTEM T2 mixing + distribution rack ready; INOX pipes delivered to cleaning service; pipes to be installed in mid september. The TIS wants it.
7
p. 7Mario Deile – Cooling Water Problems: collection of parts is main difficulty; many components not available from store need someone with experience in water circuit design tried company, but unreliable
8
p. 8Mario Deile – Cables (GEMino)
9
p. 9Mario Deile – Cables (RPino)
10
p. 10Mario Deile – Cables (CSCino) Note for all systems: connectors still undefined / unknown to me.
11
p. 11Mario Deile – Trigger Scintillators Available: Genova stock at CERN: 10x10 cm 2 1x1 cm 2 ~ 1x6 cm 2 3x3 mm 2 CERN group: 5x5 cm 2 50x50 cm 2 (4 for T1; to be assembled) 2 support stands; HV and BNC cables: enough but old
12
p. 12Mario Deile – Counting-Room Network: Fast Ethernet functional Wireless network functional Room needs cleaning up (some ATLAS equipment and junk left; we are free to either keep it or throw it away).
13
p. 13Mario Deile – Safety ISIEC form submitted. Had first talk with Gunnar Lindell & Claude Detraz: - problem with some old BNC cables; - gas pipes need pressure test; - ground lines need better electrical connections to cable trays; - for working on high detectors, special platforms needed; - in the zone, passageways have to be > 0.9 m wide ( constraints for gas rack positions); - counting-room needs pharmacy box; - need “initial safety discussion” (11. – 14.09.); - then safety inspection after installations Everybody needs to have attended the safety course (levels 1 – 3) within the last 5 years.
14
p. 14Mario Deile – Schedule Main user time 31.08. – 03.09. to be given away (to 3D Si?) Crystal channel: no access! Hurts our installation activities. Have to use MD days.
15
p. 15Mario Deile – Schedule (RP)
16
p. 16Mario Deile – Schedule (T1)
17
p. 17Mario Deile – Long-Term Schedule Next year: Start of SPS physics in early May. End still unclear Start thinking about our plans!