Cohesion Fund Monitoring Committee CR 1164/94 ISPA Measure 2001 BG 16 P PE 004 FGD Plants at Units 5&6 of TPP Maritsa East 2
2
Works Contract Commencement Date:14 th January 2009 Completion Date:01 st September 2011 Physical Execution:100 % Financial Execution:57 % Protokol 15 signed:30 August 2012 Contract terminated by the Employer: 14 December 2012 Cohesion Fund Monitoring Committee CR 1164/94
3
FGDP at Units 5&6 of TPP ME2 Construction Works Section 1 (Unit 6) Gas Ducts Cohesion Fund Monitoring Committee CR 1164/94 Section 1 (Unit 6) Gas Duct Connection to ID Fan
4
FGDP at Units 5&6 of TPP ME2 Construction Works Section 1 (Unit 6) Oil Station Room Section 1 (Unit 6) MCC Room Cohesion Fund Monitoring Committee CR 1164/94
5
FGDP at Units 5&6 of TPP ME2 Construction Works Section 2 (Unit 5) Erection of ID Fan Cohesion Fund Monitoring Committee CR 1164/94 Section 2 (Unit 5) Gas Duct Connection to Existing Part
6
FGDP at Units 5&6 of TPP ME2 Construction Works Section 2 (Unit 5) Oil Station with Sealing Air Fan Cohesion Fund Monitoring Committee CR 1164/94 Section 2 (Unit 5) Gas Duct Connection to Existing Electro-filters
7
FGDP at Units 5&6 of TPP ME2 Construction Works Section 2 (Unit 5) Gas Duct Connection to Electro-filters Cohesion Fund Monitoring Committee CR 1164/94 Section 2 (Unit 5) Gas Duct Out of ID Fan
8
FGDP at Units 5&6 of TPP ME2 Construction Works Section 3 – Limestone Slurry Preparation Building – Reinforcement Works 9 th Cohesion Fund Monitoring Committee CR 1164/94
9
FGDP at Units 5&6 of TPP ME2 Construction Works Section 3 – Wet Stack Support Structure Stepping on the Absorber Section 3 – Absorber Inside Cohesion Fund Monitoring Committee CR 1164/94 Section 3 – Wet Stack Support Structure
10
FGDP at Units 5&6 of TPP ME2 Construction Works Section 3 – Steel Support Structure for Pump Station 2 Section 3 – Slab at level 14.34 m, Pump Station 2 Cohesion Fund Monitoring Committee CR 1164/94
11
FGDP at Units 5&6 of TPP ME2 Construction Works Section 3 – Reinforcement Works for Pump Station 2 – slab at level 18.84 m Section 3 – Pump Station 2 and Absorber Cohesion Fund Monitoring Committee CR 1164/94
12
FGDP at Units 5&6 of TPP ME2 Construction Works Section 3 – Foundation for Limestone Slurry Preparation Building Cohesion Fund Monitoring Committee CR 1164/94 Section 3 – Erection of Gas Duct Connection to Absorber Inlet Nozzle
13
FGDP at Units 5&6 of TPP ME2 Deliveries Elements for Wet Stack Support Structure GRP Elements for Wet Stack Cohesion Fund Monitoring Committee CR 1164/94 GRP Pipes for Limestone Slurry Recirculation Transformer T 35
14
FGDP at Units 5&6 of TPP ME2 Signboards Cohesion Fund Monitoring Committee CR 1164/94
15
Supervision Contract Commencement Date:18 th Sept. 2006 Completion Date:18 th July 2014 Physical Execution:90 % Financial Execution:83 % Cohesion Fund Monitoring Committee CR 1164/94
16
Compliance with Article 8 of the Financing Memorandum Art. 8.4 (a) Whereas the requirement of Art. 8.4 (a) is not a condition related to payment, formal confirmation of EC for its fulfillment is not expected. Art. 8.5 (a) Monitoring programme has been prepared as part of the Basic Design and will be further elaborated with the Detailed Design for Section 3 of the facility. Art. 8.5 (b) Measures for ensuring air quality are being taken. All other conditions under Article 8 of the FM are considered fulfilled, except for the unavailability of EBRD financing. Cohesion Fund Monitoring Committee CR 1164/94