1
Site Report Poroton Home to Building shell – in record time
2
In record time to the complete building shell Location: Trier Outside wall: ThermoPlan T10 Inside wall: Planziegel Hlz Incl. special bricks Team: 3 workers (1 master craftsman, 2 assistant ) Constr. period: 5 days for the complete building shell.
3
The bottom slab is casted
4
The first delivery
5
Professional discharging
7
The second delivery... Everything has to be at it‘s place.
8
The first layer
9
After 4 hours, the first layer is ready
10
Now, the plan-bricks have to be worked up
11
Brick after brick
12
Some hours later-The building is growing fast
14
The result of one day
15
The next day - The inside walls
16
Nearly ready
17
After 30 hours with 3 workers
19
During the time lag of ceiling delivering – the garage was built
20
Bricks for the top floor
21
Again – the first layer is ready
22
Exact plans allowed the preparation of the bricks for the pitch
23
Usage of U-Blocks for the ring armature
24
The ring armature encloses the masonry
25
Some details
26
Working with concrete is finished
27
Inside walls in top floor
28
Now, the truss can be constructed
29
Craftsmanship – just great
30
Insulation at the ring armature....
31
Finished
32
The result of 120 hours work
33
Finally The complete building shell was finished after 5 days. -With 1 craftsman and 2 helpers -Top quality, 100% brick A brickhouse makes you happy