CBM Building and Infrastructure
Wolfgang Niebur, GSI CBM Collaboration Meeting, Overview of new (since 2008) old status (before 2007) beamfocus costs
2
Cave+Supply building before 2007 – View in beam direction
access shaft 6 × 6 m access opening 10 × 10 m
3
Cave before 2007 – Top view, surface level
Annex building access shaft 6 X 6 m access opening 10 ×10 m
4
Cave 2008 – Top view, surface level
Annex building access opening 6 ×10 m Roof, compacted earth
5
Cave 2008 – Top view into cave
access opening 6 X 10 m Single wall
6
Cave before 2007 – Top view into cave
access shaft 6 ×6 m Double wall Sandwich filling
7
Cave 2008 – Side view Compacted earth access opening 6 X 10 m
Annex building Compacted earth Shielded area
8
Fair Baseline Technical Report 2006 (FBTR) Version 2
Costs Fair Baseline Technical Report 2006 (FBTR) Version 2 Building Cost FBTR 2006 is Million Euro Cave 11,80 M€ Annex building 0,98 M€ The building cost in our Draft version as of now around 10.5 Million Euro The cost optimizations are the following: 1) The cave floor is in one level 2) The sandwich walling is obsolete 3) 1 slab/floor opening for the crane instead of 2. 4) The new opening dimension is 6m x 10 m.
9
Thank you for your attention.
10
Cave before 2007 – Side view Roof, compacted earth
breakthrough 10 X 10 m
11
X X X X X - + - + + - Beamfocus CBM - Hades CBM-Magnet Cave wall
+ X - Hades-Target CBM-Magnet Cave wall Hades-Magnet Hades-Target CBM-Target - 4000 X X Beam + 6800 - 4700 12000 + 4700 - 4700 Hades-beamtime: beam pipe d 100 X 9400 + X - Hades-Target + + 1600 CBM-beamtime: beam pipe d 100 X 1600 X - Hades-Target W. Niebur