Building for Learning Project Photo Progress Report 3 October 2009 – November 2009 Project commencement 21 st September 2009.

Similar presentations


Presentation on theme: "Building for Learning Project Photo Progress Report 3 October 2009 – November 2009 Project commencement 21 st September 2009."— Presentation transcript:

1 Building for Learning Project Photo Progress Report 3 October 2009 – November 2009 Project commencement 21 st September 2009

2 Internal Demolition Begins 6 th Oct 2009

3 Classrooms 6-9 Demolition continues Oct 2009 Rooms emptied, carpets, ceilings, all electrics wiring removed ready for 1 st storey construction and concrete slab floor

4 Racking construction for refurbishment storage 14 th Oct 2009

5 Demolition continues Oct 2009

6 Corporate Services area refurbishment 19 th Oct 2009 Windows removed Ceiling Fans replaced

7 Floor demolition 19 th Oct 2009

8 Graeme Connelly supervising wall demolition 21 st Oct 2009

9 Internal framing and windows being cut in 27 th Oct 2009

10 Framing and floors added 28 th Oct 2009 Staff inspections of works

11 Outside area demolition ready for major works to begin 29 th Oct 2009

12 1 st Storey works commences November 09

13 Scaffolding up early November

14 Room demolition – mid November

15 Some of the removed materials 24 th November

16 Roof on – Roof Off (29 th November 2009) Over a period of about 2 weeks the roof and all timber roof trusses, wiring, air-conditioners, chimneys and a satellite dish were removed and prepared for a new 1 st storey floor slab to be created. This change meant that the possums who had taken residence in the ceiling over the last 100+ years have now moved on!!!