Building for Learning Project Photo Progress Report 3 October 2009 – November 2009 Project commencement 21 st September 2009
2
Internal Demolition Begins 6 th Oct 2009
3
Classrooms 6-9 Demolition continues Oct 2009 Rooms emptied, carpets, ceilings, all electrics wiring removed ready for 1 st storey construction and concrete slab floor
4
Racking construction for refurbishment storage 14 th Oct 2009
5
Demolition continues Oct 2009
6
Corporate Services area refurbishment 19 th Oct 2009 Windows removed Ceiling Fans replaced
7
Floor demolition 19 th Oct 2009
8
Graeme Connelly supervising wall demolition 21 st Oct 2009
9
Internal framing and windows being cut in 27 th Oct 2009
10
Framing and floors added 28 th Oct 2009 Staff inspections of works
11
Outside area demolition ready for major works to begin 29 th Oct 2009
12
1 st Storey works commences November 09
13
Scaffolding up early November
14
Room demolition – mid November
15
Some of the removed materials 24 th November
16
Roof on – Roof Off (29 th November 2009) Over a period of about 2 weeks the roof and all timber roof trusses, wiring, air-conditioners, chimneys and a satellite dish were removed and prepared for a new 1 st storey floor slab to be created. This change meant that the possums who had taken residence in the ceiling over the last 100+ years have now moved on!!!