LIFE-Nature-2005 Restoration of the Wetlands of Zahorie Lowland prepared by: Jaromír ŠÍBL – project manager
2
Beneficiary and partners State Nature Conservancy of SR Slovak Water Management Enterprise BROZ
3
Duration + budget start: February 2005 end: December 2008 total budget: 624,000 EURO EC contribution: 50%
5
Objectives General: development of NATURA 2000 network Specific: improve habitat conditions of wetlands degraded by drainage reach / maintain favourable conservation status of species and habitats targeted public awareness on wetlands conservation / restoration
6
NATURA 2000 - 8 proposed Sites of Community Importance Habitats: semi-natural pine, oak, birch and alder forests pine monucultures inland sand dunes dry grasslands and heaths wetlands meadows running waters
7
Species (all species recorded): higher plants - more than 500 fish - 30 amphibians - 13 reptiles - 6 birds - 48 mammals - 24 Species of Community interest (Annex II of Habitats Directive) higher plants - 1 beetles - 6 butterflies - 3 dragonflies - 4 cyclostomes and fish - 7 amphibians - 1 mammals - 7 birds (Annex I of Birds Directive) - 48
55
Threats drainage of wetlands, regulations of watercourses unsustainable forest management (clearcuts, pine monocultures) fish migration obstacled by weir at Rudava River lack of management of meadows lack of awareness
60
Problems - Consequences Lack of scientific information on MTA´s biodiversity (inventories) Unsustainable forest management (in terms of biodiversity) - large scale clear-cuts - planting pine monocultures - increased danger of forest fires – loss of biodiversity Deterioration of water regime - drainage of wetlands, stream regulations - interruption of fish migration routes (barriers) - loss of biodiversity - loss of retention capacity of the landscape – increased danger of climatic extremes (drought, floods)
61
Actions A.1. Management Plans for 8 project sites elaborated deadline: 31/12/2007 status: on-going outputs: -botanical and zoological inventories carried - GIS database developed -draft Management plans elaborated for 4 project sites
62
A.2. Education and training of project personnel deadline: 31/07/2007 status: on-going outputs: - study visit to Czech repulic (2 persons) acomplished - study visit to Poland (11 persons) acomplished
66
A.3. Amendments to forest management plans for 7 project sites deadline: 31/12/2006 status: on-going outputs: -proposals elaborated for 3 project sites, -draft proposals elaborated for 4 project sites
68
C.1. Implementation of specific restoration and management measures deadline: 31/03/2008 status: on-going outputs: -Bahno - dead trees removed from 2,8 ha (100%) -Vanišovec - 140 m of drainage canals filled (100%) -Zelienka - 90 m of drainage canals filled (60%) -Jasenácke - 20 m of drainage canals filled (50%) -Kotlina - restoration works start in September 2006
76
C.2. Construction of the fish by-pass at Rudava River deadline: 30/11/2007 status: on-going outputs: -the technical documentation for the construction project revised, construction budget updated
78
C.3. Restoration of lowland hay meadows along Rudava River deadline: 30/09/2008 status: on-going outputs: - base line survey carried on the butterfly species targeted - restoration works started at the area of 12 ha
83
E.1. Produce educational materials on the project for general public and for media deadline: 31/10/2008 status: on-going outputs: - 5 articles published, 1 press release, 3 TV and 1 radio broadcasts released -interim project website established, new website under preparation -film/video/DVD producer selected
87
E.2. Workshops and public meetings deadline: 31/10/2008 status: on-going outputs: - 1 public meeting prepared
88
F.1. Project management + monitoring status: on-going F.2. Bookkeeping status: on-going F.3 Auditing status: pending F.4 After LIFE - Conservation Plan status: pending
89
Project focus in 2006 Management Plans + Restoration Projects Forest management plans wetland restoration - filling the drainage ditches and canals) at 4 project sites documentation for construction permit of fish by-pass at Rudava River restoration of degraded meadows at pSCI Rudava
90
Thank you for your attention !