NANPA Oversight Working Group Status Report to the NANC April 17, 2001 Chair Pat Caldwell
2
April 17, 2001 NOWG Status Report to the NANC 2 Overview 2000 Performance Review Update NANPA Technical Requirements Update Future Meeting Schedule
3
April 17, 2001 NOWG Status Report to the NANC 3 2000 NANPA Performance Review 39 surveys have been submitted –16 States –16 Companies Conducted meeting is in Dallas March 26 - 30 to develop NANC report on NANPA performance results. –Documented this years operational review results. –Analyzing surveys. Next meeting is April 18 & 19 Expect results in May.
4
April 17, 2001 NOWG Status Report to the NANC 4 NANPA Technical Requirements Status Detailed Schedule 03-15-01Completed baseline 03-16-01Complete first draft 07-17-01Share 1st draft with Steering Group 07-27-01Final draft to Legal Working Group 08-03-01Review with Legal Working Group 08-27-01Submit to NANC 09-11-01NANC review, approval and forward to the FCC
5
April 17, 2001 NOWG Status Report to the NANC 5 NOWG Meeting Schedule April 18-19 USTA in DC April 30-May 4 Verizon in New York May 23-25 BellSouth in DC June 20-22 USTA in DC July 24-27TBD August 3Conference Call August 14-15Tentative TBD Sep 12 - 13AT&T in DC Oct 17 - 18USTA in DC Nov 28 - 29TBD in DC