1
Design Items and Tasks for pol. 3 He Remain design items: Support structure Main support Tube/oven (90% complete) Temp. support in the target lab Target ladder assembly holder for optics target Pick-up coil/mounts Access/safety Enclosure and viewing Optics lines (including EPR, spectra-analyzer) Reference cell support Compass mounts BB fringe field shielding/compensation
2
Tasks for pol. 3 He (I) Target lab: Finish spin-reversal test RF sweep water calibration EPR New oven (arrive next week) test Test new components Test new optics Test/characterize new cells
3
Other tasks/issues for pol. 3 He (II) Other tasks/issues: Compass Vertical coils Optical fibers Lasers Cells Budget Manpower Readiness review Milestones