Brownfields in UK and Czech Republic An Engineer’s Experience Presentation for COBRAMAN Training Programme 5 th Training, 21 st – 22 nd September 2010 Dr. Martin Duris
2
Introduction PBA – Engineering Consultancy 500 staff in total 400 staff in UK, 100 overseas Prague Office since 1999 Brownfields Regeneration and Land Development are the main business areas HQ located in Reading, former industrial centre in SE England
3
Reading History – industrial city: brewing, biscuits (Huntley and Palmers), bulbs, bricks Dull, undesirable place to live in or visit
4
Reading Regeneration over the past 20 years has changed Reading out of recognition Production changed to high tech IT companies (Microsoft, Oracle) with offices in the centre, leading to pedestrianisation Huntley & Palmers demolished, just one building left
5
Reading City centre regeneration included construction of a major shopping centre – The Oracle
6
Reading New business was also attracted with extensive regeneration of edge of town sites: - Thames Valley Park, former coal- fired power station -Green Park, former landfill & other low grade land -Madejski Stadium, former landfill, now home to a Premierships team
7
Reading
9
Reading is now one of the top SE destinations for retail (The Oracle Centre) The Reading area is one of the best performing regions in the country It has become a desirable destination
10
Prague & Czech Republic Has not benefitted from the post-WWII growth as UK Many old factories, dilapidated industrial estates Poor maintenance, poor quality of construction, heavy pollution Sometimes arrogant decision-making by the ruling party left big scars Proper regeneration activities started only 10 to 15 years ago Issues identical to UK, but delayed, some issues more prominent, lack of public funds
11
Prague Zizkov Cargo Station redevelopment Former cargo station, full of old tracks, buildings and contamination Massive size – 55 ha Two private developers – Discovery and Sekyra Group Discovery – northern part, 30 ha, 1 st phase 6 ha Future uses – residential, office, retail (300m x 120m), hotel Project value CZK 6 billion
12
Zizkov Cargo Station
15
Prague Laser Centre Dolni Brezany ELI – Extreme Light Infrastructure (laser) Former wood processing plant Site 8 ha, buildings 35,000 m2 EU-funded, supported by Ministry of Education & Institute of Physics of the Czech Academy of Sciences Four buildings: laser hall, labs, offices, lecture halls, library, gallery Project value CZK 1 billion
16
ELI Laser Centre
18
Engineer’s role Developments can be Engineer - led Green Park – PBA were approached by the landowner 25 years ago for advice on how to develop the land Opportunities identified, PBA approached Prudential as a potential investor Green Park has become one of Pru’s flagship projects Same story with Thames Valley Park PBA still look to introduce potential investors to land that needs another use (quarries, landfill sites, etc)
19
Brownfield vs. Greenfield Often high clean-up costs, public funding often necessary (gas works, heavy metal manufacturing particularly onerous) Service diversions and tight access frequent issues Advantages in town centre – connectivity to public transport and well served by the utilities Greater attention now given to retain & restore industrial buildings – more sustainable, retains character of the site Greater emphasis placed on retaining or establishing communities through mixed use developments, even business parks Some recent redevelopments were too sweeping, removed character & critically damaged or destroyed communities
20
Image & Wealth Regeneration stimulates growth, but: Needs to be supported by local availability of skills Businesses need to be willing to relocate and/or expand (attractive image) New communities must be created Mix of old character and new imaginative landscaping Public money needed for clean-up
21
Image Change