Allison 2001 Charles Chambers Information Technology 2001 Tropical Storm Allison Recovery
2
Allison 2001 Time Line Saturday –flooding begins (1 A.M.) – IT team on campus –Additional IT staff arrive – pumping and power are critical –Institutional priorities are focused – Non-IT Sunday –Pumping of network node facilities begin –Power restored to UHS data center –Internet connection reestablished –713-743-1000 call center established –Systems and servers returned to service Sa 9 th Su 10 th M 11 th T 12th W 13th Th 14th F 15th Sa 16th Su 17th M 18th T 19th W 20th Th 21st F 22n d
3
Allison 2001 Time Line Monday, June 11th –WAN services restored except UHV –IP telephones activated in critical areas –Relocated some servers to Data Center Tuesday, June 12 th –Internet connectivity unstable due to ISP –Servers in Data Center grow by 20 –UHV network connection restored –Desktop assessment team inventories campus –Network teams inspect buildings for damage Sa 9 th Su 10 th M 11 th T 12th W 13th Th 14th F 15th Sa 16th Su 17th M 18th T 19th W 20th Th 21st F 22n d
4
Allison 2001 Time Line Wednesday, June 13 th –UH-CVN services restored, classes held. –Payroll processed –50% of phone system returned to service Thursday, June 14 th –Data backbone restored –Data connectivity to opened buildings –Order Equipment for Storm Solutions for Hofheinz Pavillion Sa 9 th Su 10 th M 11 th T 12th W 13th Th 14th F 15th Sa 16th Su 17th M 18th T 19th W 20th Th 21st F 22n d
5
Allison 2001 Time Line Friday, June 15 th –Majority of phone system restored Saturday, June 16 th –Equipment for Hofheinz Pavillion arrives, installed Sa 9 th Su 10 th M 11 th T 12th W 13th Th 14th F 15th Sa 16th Su 17th M 18th T 19th W 20th Th 21st F 22n d
6
Allison 2001 Time Line Sunday, June 17 th –Hofheinz Pavillion available 270 IP telephones 314 data ports IT support booth created Monday, June 18 th –University Re-Opens –First occupants moves into Hofheinz Pavillion Sa 9 th Su 10 th M 11 th T 12th W 13th Th 14th F 15th Sa 16th Su 17th M 18th T 19th W 20th Th 21st F 22n d
7
Allison 2001 Time Line Tuesday –Voice Mail system restored –Touch Tone Registration restored –Remainder of phone system restored Wednesday –Majority of SWB trunking problems corrected Sa 9 th Su 10 th M 11 th T 12th W 13th Th 14th F 15th Sa 16th Su 17th M 18th T 19th W 20th Th 21st F 22n d
8
Allison 2001 Time Line Thursday Friday –Reconfiguration of Hofheinz Pavillion network Sa 9 th Su 10 th M 11 th T 12th W 13th Th 14th F 15th Sa 16th Su 17th M 18th T 19th W 20th Th 21st F 22n d
9
Allison 2001 Technology Priorities Phone System Internet Connectivity Inter-campus Network Campus Data Network Interactive Video Network Data Center Operation Infrastructure
10
Allison 2001 Technology Priorities E-mail Web Site WebCT IVR for Registration/Records Payroll Financial Application Services
11
Allison 2001 Technology Priorities Inventory Repair Replacement Computers Data restores Desktop Computers
12
Allison 2001 Technology Priorities Used basketball pavilion Boxes became offices Basketball floor –became labs and cubicles Temporary Space - Holfheinz
13
Allison 2001 Holfheinz Pavillion 27 boxes Cisco IP telephony – 270 phones Switched data network –270 ports in offices –144 ports on basketball court –Over 100,000 feet of copper and fiber IT support booth –Voice and data network support –Desktop computer support From Basketball to Academics
14
Allison 2001 Recovery Resources Over xxx person hours (UH Staff) Loss and Business Resumption –Costs estimated in millions Over 250 IT related staff involved
15
Allison 2001 Lessons Learned Move IT facilities above ground Move generators above ground Flood doors on underground entrances Established plans helped... –The right people at the right places, making the right decisions was the key. Mobilize support efforts early –Food –Sleeping Quarters
16
Allison 2001 Heroic Efforts Pumps/Pumping Saving the Animals Getting Primary DID in service Internet Connectivity Holfheinz Pavillion
17
Allison 2001 How the Speedy Recovery Temporary fixes Great minds and enormous goals Dedicated staff Very long hours Multiple plans Quick vendor response Elimination of bureaucracy Communication of status and goals Central coordination point
18
Allison 2001 Starting Recovery Pumping and Power Starting pumping PGH on Saturday Moved pumps to animal lab (SR2) Sunday power restored to Computing Center Internet Connection –Reconfigured to computing center –Web and e-mail up first
19
Allison 2001 Recovery Partners Herculean efforts by all! –Pumping water –Removing damaged equipment –Designing and installing new systems –Power restoration UH Support –College volunteers –Facilities Vendor response was great! –Staff on site (over 100) –Rapid deployment of equipment
20
Allison 2001 Initial Impact Primary Technology Areas Affected –UHS Data Center –Network Node in PGH –Network Node in UCU –Headend Facility in Moody
21
Allison 2001 UHS Data Center Lost power No flooding or other damage
22
Allison 2001 Network Node (PGH) Services lost –Voice, data, video for UH –Internet and interactive video for all UHS Damage –Water 18 inches above raised floor –Power systems total loss
23
Allison 2001 Network Node (PGH) Telephone and Voice Mail Systems
24
Allison 2001 Network Node (UCU) Services lost –Voice network for 1/3 of campus –Trunk lines from SWB –High capacity circuits from SWB Damage –Telephone Switch corroded –Wire center destroyed 3600 stations
25
Allison 2001 Network Node (UCU) Telephone system
26
Allison 2001 Network Node (UCU) SWB Interface
27
Allison 2001 Network Node (UCU) Wire Center Frame
28
Allison 2001 Headend Facility (Moody) Services Lost –CATV Network
29
Allison 2001 Hofheinz Pavillion Home of “Phi Slamma Jama”
30
Allison 2001 Hofheinz Pavillion Wiring was pretty open…
31
Allison 2001 An wide shot view of the inner-city of Houston, Texas
32
Allison 2001 Flood waters invade the City with no Mercy
33
Allison 2001 Freeway Entrance ramp into downtown from the North
34
Allison 2001 Freeway Exit ramp
35
Allison 2001 A view of Allen-Parkway
36
Allison 2001 Raging waters in the Tunnel System Downtown
37
Allison 2001 Another view of the Tunnel System Downtown
38
Allison 2001 And...Another view of the Tunnel System Downtown
39
Allison 2001 Canoeing down HWY 59 near the Compaq Center
40
Allison 2001 A view of 1 of 3 of the Suspension Bridges that crosses over HWY 59 near the Compaq Center
41
Allison 2001 A view of the Houston’s Channel 11 - KHOU - Television Studio
42
Allison 2001 A view of Interstate Highway I-10
43
Allison 2001 Jet Sking in the flood waters on Interstate Highway I-10
44
Allison 2001 A view of a 3-way Intersection located at Allen Parkway and Sanford Street
45
Allison 2001 Here’s Who did it! CTS “Crew” at Storm Allison Luncheon