Project Management Chapter 2
Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
2
Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
What is a Project? Project An interrelated set of activities with a definite starting and ending point, which results in a unique outcome for a specific allocation of resources. Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
3
What is Project Management?
A systemized, phased approach to defining, organizing, planning, monitoring, and controlling projects. Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
4
Defining and Organizing Projects
Defining the Scope and Objectives Selecting the Project Manager and Team Recognizing Organizational Structure Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
5
Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
Planning Projects Defining the Work Breakdown Structure Diagramming the network Developing the schedule Analyzing cost-time trade-offs Assessing risks Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
6
Work Breakdown Structure
A statement of all the work that has to be completed. Activity The smallest unit of work effort consuming both time and resources that can be planned and controlled. Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
7
Work Breakdown Structure
Relocation of St. John’s Hospital Level 0 Organizing and Site Preparation Physical Facilities and Infrastructure Level 1 Select administration staff Site selection and survey Select medical equipment Prepare final construction plans Bring utilities to site Interview applicants for nursing and support staff Purchase and deliver equipment Construct hospital Develop information system Install medical equipment Train nurses and support staff Level 2 02 -07 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall.
8
Diagramming the Network
Program Evaluation and Review Technique (PERT) Critical Path Method (CPM) Activity-on-Node approach Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
9
Establishing Precedence Relationships
Determining the sequence for undertaking activities. Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
10
Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
Example 2.1 Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 11
11
Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
Example 2.1 A — B — C A D B E B F A G C H D I A J E,G,H K F,I,J Immediate Predecessor I K Start A F C Finish G B J D H E Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 12
12
Immediate Predecessor(s)
Application 2.1 The following information is known about a project Activity Activity Time (days) Immediate Predecessor(s) A 7 — B 2 C 4 D B, C E F 3 G 5 Draw the network diagram for this project Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
13
Immediate Predecessor(s)
Application 2.1 Activity Activity Time (days) Immediate Predecessor(s) A 7 — B 2 C 4 D B, C E F 3 G 5 B 2 F 3 D 4 Finish Start A 7 E 4 C 4 G 5 Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
14
Developing the Schedule
Path The sequence of activities between a project’s start and finish. Critical Path – The sequence of activities between a start and finish that takes the longest time to complete. Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
15
Developing the Schedule
Earliest start time (ES) - the latest earliest finish time of any immediately preceding activities Earliest finish time (EF) - the earliest start time plus its estimated duration EF = ES + t Latest finish time (LF) – the earliest of the latest start times of any of the immediately following activities. Latest start time (LS) - the latest finish time minus its estimated duration LS = LF – t Activity Slack - the maximum length of time an activity can be delayed without delaying the entire project LF-EF or LS-ES Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
16
Developing the Schedule
Latest finish time Latest start time Activity Duration Earliest start time Earliest finish time 2 12 14 A Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
17
Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
Example 2.2 Paths are the sequence of activities between a project’s start and finish. Finish Start A B C D E F G H I J K Path Time (wks) A-I-K 33 A-F-K 28 A-C-G-J-K 67 B-D-H-J-K 69 B-E-J-K 43 Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall 24
18
Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
Example 2.2 K 6 C 10 G 35 J 4 H 40 B 9 D E 24 I 15 Finish Start A 12 F 12 Earliest finish time Earliest start time Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
19
Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
Example 2.2 K 6 C 10 G 35 J 4 H 40 B 9 D E 24 I 15 Finish Start A 12 F The Critical Path takes 69 weeks Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
20
Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
Latest finish time Example 2.2 K 6 C 10 G 35 J 4 H 40 B 9 D E 24 I 15 Finish Start A 12 F Latest start time Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
21
Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
Example 2.2 S = 36 K 6 C 10 G 35 J 4 H 40 B 9 D E 24 I 15 Finish Start A 12 F S = 0 S = 2 S = 41 S = 2 S = 2 S = 0 S = 0 S = 0 S = 0 S = 26 Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
22
Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
Developing a Schedule Gantt chart Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
23
Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
Application 2.2 Calculate the four times for each activity in order to determine the critical path and project duration for the diagram in Application Problem 1. Activity Duration Earliest Start (ES) Latest Start (LS) Earliest Finish (EF) Latest Finish (LF) Slack (LS-ES) On the Critical Path? A 7 0-0=0 Yes B 2 C 4 D E F 3 G 5 The critical path is A–C–D–E–G with a project duration of 24 days. Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
24
Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
Application 2.2 Calculate the four times for each activity in order to determine the critical path and project duration. Activity Duration Earliest Start (ES) Latest Start (LS) Earliest Finish (EF) Latest Finish (LF) Slack (LS-ES) On the Critical Path? A 7 0-0=0 Yes B 2 C 4 D E F 3 G 5 7 9 11 9-7=2 No 7 11 7-7=0 Yes 11 15 11-11=0 Yes 15 19 15-15=0 Yes 19 21 22 24 21-19=2 No 19 24 19-19=0 Yes Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
25
Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
Application 2.2 The critical path is A–C–D–E–G with a project duration of 24 days. Start Finish A 7 B 2 C 4 D E F 3 G 5 Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
26
Analyzing Cost-Time Trade-Offs
Project Crashing Shortening (or expediting) some activities within a project to reduce overall project completion time. Project Costs Direct Costs Indirect Costs Penalty Costs Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
27
Analyzing Cost-Time Trade-Offs
Project Costs Normal time (NT) is the time necessary to complete an activity under normal conditions. Normal cost (NC) is the activity cost associated with the normal time. Crash time (CT) is the shortest possible time to complete an activity. Crash cost (CC) is the activity cost associated with the crash time. Cost to crash per period = CC – NC NT – CT Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
28
Cost-Time Relationships
Linear cost assumption 8000 — 7000 — 6000 — 5000 — 4000 — 3000 — 0 — Direct cost (dollars) | | | | | | Time (weeks) Crash cost (CC) Normal cost (NC) (Crash time) (Normal time) Estimated costs for a 2-week reduction, from 10 weeks to 8 weeks 5200 Figure 2.6 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall.
29
Analyzing Cost-Time Trade-Offs
Determining the Minimum Cost Schedule: Determine the project’s critical path(s). Find the activity or activities on the critical path(s) with the lowest cost of crashing per week. Reduce the time for this activity until… It cannot be further reduced or Until another path becomes critical, or The increase in direct costs exceeds the savings that result from shortening the project (which lowers indirect costs). 4. Repeat this procedure until the increase in direct costs is larger than the savings generated by shortening the project. Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
30
DIRECT COST AND TIME DATA FOR THE ST. JOHN’S HOSPITAL PROJECT
Example 2.3 DIRECT COST AND TIME DATA FOR THE ST. JOHN’S HOSPITAL PROJECT Activity Normal Time (NT) (weeks) Normal Cost (NC)($) Crash Time (CT)(weeks) Crash Cost (CC)($) Maximum Time Reduction (week) Cost of Crashing per Week ($) A 12 $12,000 11 $13,000 1 1,000 B 9 50,000 7 64,000 2 7,000 C 10 4,000 5 600 D 16,000 8 20,000 2,000 E 24 120,000 14 200,000 8,000 F 10,000 6 4 1,500 G 35 500,000 25 530,000 3,000 H 40 1,200,000 1,260,000 12,000 I 15 40,000 52,500 2,500 J 13,000 3 K 30,000 34,000 Totals $1,992,000 $2,209,500 Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
31
Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
Example 2.3 Determine the minimum-cost schedule for the St. John’s Hospital project. Project completion time =69 weeks. Project cost = $2,624,000 Direct = $1,992,000 Indirect = 69($8,000) = $552,000 Penalty = (69 – 65)($20,000) = $80,000 A–I–K 33 weeks A–F–K 28 weeks A–C–G–J–K 67 weeks B–D–H–J–K 69 weeks B–E–J–K 43 weeks Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
32
Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
Example 2.3 STAGE 1 Step 1. The critical path is B–D–H–J–K. Step 2. The cheapest activity to crash per week is J at $1,000, which is much less than the savings in indirect and penalty costs of $28,000 per week. Step 3. Crash activity J by its limit of three weeks because the critical path remains unchanged. The new expected path times are A–C–G–J–K: 64 weeks B–D–H–J–K: 66 weeks The net savings are 3($28,000) – 3($1,000) = $81,000. The total project costs are now $2,624,000 - $81,000 = $2,543,000. Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
33
Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
Example 2.3 Finish K 6 I 15 F 10 C D H 40 J 1 A 12 B 9 Start G 35 E 24 STAGE 1 Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
34
A–C–G–J–K: 64 weeks and B–D–H–J–K: 64 weeks
Example 2.3 STAGE 2 Step 1. The critical path is still B–D–H–J–K. Step 2. The cheapest activity to crash per week is now D at $2,000. Step 3. Crash D by two weeks. The first week of reduction in activity D saves $28,000 because it eliminates a week of penalty costs, as well as indirect costs. Crashing D by a second week saves only $8,000 in indirect costs because, after week 65, no more penalty costs are incurred. Updated path times are A–C–G–J–K: 64 weeks and B–D–H–J–K: 64 weeks The net savings are $28,000 + $8,000 – 2($2,000) = $32,000. Total project costs are now $2,543,000 – $32,000 = $2,511,000. Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
35
Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
Example 2.3 Finish K 6 I 15 F 10 C D 8 H 40 J 1 A 12 B 9 Start G 35 E 24 STAGE 2 Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
36
Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
Example 2.3 STAGE 3 Step 1. The critical paths are B–D–H–J–K and A-C-G-J-K Step 2. Activities eligible to be crashed: (A, B); (A, H); (C, B); (C, H); (G, B); (G, H)— or to crash Activity K We consider only those alternatives for which the costs of crashing are less than the potential savings of $8,000 per week. We choose activity K to crash 1 week at $4,000 per week. Step 3. Updated path times are: A–C–G–J–K: 63 weeks and B–D–H–J–K: 63 weeks Net savings are $8,000 - $4,000 = $4,000. Total project costs are $2,511,000 – $4,000 = $2,507,000. Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
37
Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
Example 2.3 Finish K 5 I 15 F 10 C D 8 H 40 J 1 A 12 B 9 Start G 35 E 24 STAGE 3 Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
38
A–C–G–J–K: 61 weeks and B–D–H–J–K: 61 weeks
Example 2.3 STAGE 4 Step 1. The critical paths are still B–D–H–J–K and A–C–G–J–K. Step 2. Activities eligible to be crashed: $7,600 per week. Step 3. Crash activities B and C by two weeks. Updated path times are A–C–G–J–K: 61 weeks and B–D–H–J–K: 61 weeks The net savings are 2($8,000) – 2($7,600) = $800. Total project costs are now $2,507,000 – $800 = $2,506,200. Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
39
Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
Example 2.3 Finish K 5 I 15 F 10 C 8 D H 40 J 1 A 12 B 7 Start G 35 E 24 STAGE 4 Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
40
Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
Example 2.3 Stage Crash Activity Time Reduction (weeks) Resulting Critical Path(s) Project Duration (weeks) Project Direct Costs, Last Trial ($000) Crash Cost Added ($000) Total Indirect Costs ($000) Total Penalty Costs ($000) Total Project Costs ($000) — B-D-H-J-K 69 1,992.0 552.0 80.0 2,624.0 1 J 3 66 3.0 528.0 20.0 2,543.0 2 D A-C-G-J-K 64 1,995.0 4.0 512.0 0.0 2,511.0 K 63 1,999.0 504.0 2,507.0 4 B, C 61 2,003.0 15.2 488.0 2,506.2 Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
41
Project Activity and Cost Data
Application 2.3 Indirect project costs = $250 per day Penalty cost = $100 per day past day 14. Project Activity and Cost Data Activity Normal Time (days) Normal Cost ($) Crash Time (days) Crash Cost ($) Immediate Predecessor(s) A 5 1,000 4 1,200 — B 800 3 2,000 C 2 600 1 900 A, B D 1,500 E C, D F 1,300 1,400 G H 500 Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
42
Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
Application 2.3 Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
43
Project Activity and Cost Data Maximum Crash Time (days)
Application 2.3 Project Activity and Cost Data Activity Crash Cost/Day Maximum Crash Time (days) A 200 1 B 600 2 C 300 D 500 E 150 F 100 G H Normal Total Costs = Total Indirect Costs = Penalty Cost = Total Project Costs = $7,500 $250 per day 21 days = $5,250 $100 per day 7 days = $700 $13,450 Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
44
Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
Application 2.3 Step 1: The critical path is , and the project duration is B–D–E–G–H 21 days. Step 2: Activity E on the critical path has the lowest cost of crashing ($150 per day). Note that activity G cannot be crashed. Step 3: Reduce the time (crashing 2 days will reduce the project duration to 19 days) and re-calculate costs: Normal Costs Last Trial = Crash Cost Added = Total Indirect Costs = Penalty Cost = Total Project Cost = $7,500 $150 2 days = $300 $250 per day 19 days = $4,750 $100 per day 5 days = $500 $13,050 Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
45
Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
Application 2.3 Step 4: Repeat until direct costs greater than savings (step 2) Activity H on the critical path has the next lowest cost of crashing ($200 per day). (step 3) Reduce the time (crashing 2 days will reduce the project duration to 17 days) and re-calculate costs: Costs Last Trial = Crash Cost Added = Total Indirect Costs = Penalty Cost = Total Project Cost = $7,500 + $300 (the added crash costs) = $7,800 $200 2 days = $400 $250 per day 17 days = $4,250 $100 per day 3 days = $300 $12,750 Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
46
Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
Application 2.3 (step 4) Repeat (step 2) Activity D on the critical path has the next lowest crashing cost ($500 per day). (step 3) Reduce the time (crashing 1 day will reduce the project duration to 16 days) and re-calculate costs: Costs Last Trial = Crash Cost Added = Total Indirect Costs = Penalty Cost = Total Project Cost = $7,800 + $400 (the added crash costs) = $8,200 $500 1 day = $500 $250 per day 16 days = $4,000 $100 per day 2 days = $200 $12,900 which is greater than the last trial. Hence we stop the crashing process. Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
47
Resulting Critical Paths Project Duration (days)
Application 2.3 The recommended completion date is day 17. Trial Crash Activity Resulting Critical Paths Reduction (days) Project Duration (days) Costs Last Trial Crash Cost Added Total Indirect Costs Total Penalty Costs Total Project Costs — B-D-E-G-H 21 $7,500 $5,250 $700 $13,450 1 E 2 19 $300 $4,750 $500 $13,050 H 17 $7,800 $400 $4,250 $12,750 Further reductions will cost more than the savings in indirect costs and penalties. The critical path is B – D – E – G – H and the duration is 17 days. Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
48
Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
Assessing Risks Risk-management Plans Strategic Fit Service/Product Attributes Project Team Capability Operations Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
49
Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
Assessing Risks Statistical Analysis Optimistic time (a) Most likely time (m) Pessimistic time (b) Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
50
Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
Statistical Analysis a m b Mean Time Beta distribution a m b Mean Time 3σ Area under curve between a and b is 99.74% Normal distribution Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
51
Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
Statistical Analysis The mean of the beta distribution can be estimated by te = a + 4m + b 6 The variance of the beta distribution for each activity is σ2 = b – a 6 2 Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
52
a = 7 weeks, m = 8 weeks, and b = 15 weeks
Example 2.4 Suppose that the project team has arrived at the following time estimates for activity B (site selection and survey) of the St. John’s Hospital project: a = 7 weeks, m = 8 weeks, and b = 15 weeks a. Calculate the expected time and variance for activity B. b. Calculate the expected time and variance for the other activities in the project. Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
53
Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
Example 2.4 a. The expected time for activity B is te = = = 9 weeks 7 + 4(8) + 15 6 54 The variance for activity B is σ2 = = = 1.78 15 – 7 6 2 8 Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
54
Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
Example 2.4 The following table shows the expected activity times and variances for this project. Time Estimates (week) Activity Statistics Activity Optimistic (a) Most Likely (m) Pessimistic (b) Expected Time (te) Variance (σ2) A 11 12 13 0.11 B 7 8 15 9 1.78 C 5 10 2.78 D 16 E 14 25 30 24 7.11 F 6 18 4.00 G 36 41 35 H 40 45 I 28 9.00 J 1 2 4 5.44 K Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
55
Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
Application 2.4 The director of continuing education at Bluebird University just approved the planning for a sales training seminar. Her administrative assistant identified the various activities that must be done and their relationships to each other: Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
56
Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
Application 2.4 The Network Diagram is: A D G J B E I Finish Start C F H Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
57
Immediate Predecessor(s)
Application 2.4 For the Bluebird University sales training seminar activities, calculate the means and variances for each activity. Activity Immediate Predecessor(s) Optimistic (a) Most Likely (m) Pessimistic (b) Expected Time (t) Variance (σ) A — 5 7 8 B 6 12 C 3 4 D 11 17 25 E 10 F C, E G 9 H I G, H J Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
58
Immediate Predecessor(s)
Application 2.4 For the Bluebird University sales training seminar activities, calculate the means and variances for each activity. Activity Immediate Predecessor(s) Optimistic (a) Most Likely (m) Pessimistic (b) Expected Time (t) Variance (σ) A — 5 7 8 B 6 12 C 3 4 D 11 17 25 E 10 F C, E G 9 H I G, H J 6.83 0.25 8.33 1.00 4.00 0.11 17.33 5.44 10.00 0.44 7.50 0.69 7.00 11.50 2.25 0.00 Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
59
Analyzing Probabilities
Because the central limit theorem can be applied, the mean of the distribution is the earliest expected finish time for the project TE = = Expected activity times on the critical path Mean of normal distribution Because the activity times are independent σp2 = (Variances of activities on the critical path) Using the z-transformation where T = due date for the project z = T – TE σp Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
60
Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
Example 2.5 Calculate the probability that St. John’s Hospital will become operational in 72 weeks, using (a) the critical path and (b) path A–C–G–J–K. a. The critical path B–D–H–J–K has a length of 69 weeks. From the table in Example 2.4, we obtain the variance of path B–D–H–J–K: σ2 = = Next, we calculate the z-value: Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
61
Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
Example 2.5 Using the Normal Distribution appendix, we find a value of Thus the probability is about 0.81 the length of path B–D–H–J–K will be no greater than 72 weeks. Length of critical path Probability of meeting the schedule is Normal distribution: Mean = 69 weeks; σ = 3.45 weeks Probability of exceeding 72 weeks is Project duration (weeks) Because this is the critical path, there is a 19 percent probability that the project will take longer than 72 weeks. Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
62
Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
Example 2.5 b. The sum of the expected activity times on path A–C–G–J–K is 67 weeks and that σ2 = = The z-value is The probability is about 0.90 that the length of path A–C–G–J–K will be no greater than 72 weeks. Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
63
Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
Application 2.5 The director of the continuing education at Bluebird University wants to conduct the seminar in 47 working days from now. Using the activity data from Application 2.4, what is the probability that everything will be ready in time? T = TE is: 47 days 43.16 days And the sum of the variances for the critical activities is: ( ) = 8.63 The critical path is and the expected completion time is A–D–G–I, 43.16 days. Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
64
Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
Application 2.5 The Network Diagram is: A D G J B E I Finish Start C F H The critical path is A-D-G-I Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
65
Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
Application 2.5 T = 47 days TE = days And the sum of the variances for the critical activities is: 8.63 z = T – TE σ2 = = = 1.31 3.84 2.94 47 – 43.16 8.63 Assuming the normal distribution applies, we use the table for the normal probability distribution. Given z = 1.30, the probability that activities A–D–G–I can be completed in 47 days or less is Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
66
Monitoring and Controlling Projects
Monitoring Project Status Open Issues and Risks Schedule Status Monitoring Project Resources Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
67
Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
Solved Problem 2.1 Your company has just received an order from a good customer for a specially designed electric motor. The contract states that, starting on the thirteenth day from now, your firm will experience a penalty of $100 per day until the job is completed. Indirect project costs amount to $200 per day. The data on direct costs and activity precedent relationships are given in Table 2.2. a. Draw the project network diagram. b. What completion date would you recommend? Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
68
ELECTRIC MOTOR PROJECT DATA
Solved Problem 2.1 ELECTRIC MOTOR PROJECT DATA Activity Normal Time (days) Normal Cost ($) Crash Time (days) Crash Cost ($) Immediate Predecessor(s) A 4 1,000 3 1,300 None B 7 1,400 2,000 C 5 2,700 D 6 1,200 E 900 2 1,100 F 11 2,500 3,750 G 800 1,450 D, E H 300 1 500 F, G Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
69
Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
Solved Problem 2.1 The network diagram is shown in Figure Keep the following points in mind while constructing a network diagram. Start Finish A 4 B 7 C 5 D 6 E 3 F 11 G H Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
70
Maximum crash time = Normal time – Crash time =
Solved Problem 2.1 With these activity times, the project will be completed in 19 days and incur a $700 penalty. Using the data in Table 2.2, you can determine the maximum crash-time reduction and crash cost per day for each activity. For activity A Maximum crash time = Normal time – Crash time = 4 days – 3 days = 1 day Crash cost per day = = Crash cost – Normal cost Normal time – Crash time CC – NC NT – CT = = $300 $1,300 – $1,000 4 days – 3 days Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
71
Maximum Time Reduction (days)
Solved Problem 2.1 Activity Crash Cost per Day ($) Maximum Time Reduction (days) A 300 1 B 200 3 C 700 D E F 250 5 G 650 H 100 2 Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
72
Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
Solved Problem 2.1 PROJECT COST ANALYSIS Stage Crash Activity Time Reduction (days) Resulting Critical Path(s) Project Duration (days) Project Direct Costs, Last Trial ($) Crash Cost Added ($) Total Indirect Costs ($) Total Penalty Costs ($) Total Project Costs ($) — C-F-H 19 10,100 3,800 700 14,600 1 H 2 17 200 3,400 500 14,200 F A-D-G-H 15 10,300 3,000 300 14,100 B-E-G-H Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
73
A–D–G–H: 15 days, B–E–G–H: 15 days, and C–F–H: 17 days
Solved Problem 2.1 The critical path is C–F–H at 19 days, which is the longest path in the network. The cheapest activity to crash is H which, when combined with reduced penalty costs, saves $300 per day. Crashing this activity for two days gives A–D–G–H: 15 days, B–E–G–H: 15 days, and C–F–H: 17 days Crash activity F next. This makes all activities critical and no more crashing should be done as the cost of crashing exceeds the savings. Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
74
Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
Solved Problem 2.2 An advertising project manager developed the network diagram in Figure 2.11 for a new advertising campaign. In addition, the manager gathered the time information for each activity, as shown in the accompanying table. Calculate the expected time and variance for each activity. Calculate the activity slacks and determine the critical path, using the expected activity times. What is the probability of completing the project within 23 weeks? Start Finish A B C D E F G Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
75
Immediate Predecessor(s)
Solved Problem 2.2 Time Estimate (weeks) Activity Optimistic Most Likely Pessimistic Immediate Predecessor(s) A 1 4 7 — B 2 6 C 3 D 13 14 E 12 A, C F 8 16 G 5 E, F Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
76
Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
Solved Problem 2.2 The expected time and variance for each activity are calculated as follows te = a + 4m + b 6 Activity Expected Time (weeks) Variance A 4.0 1.00 B 5.5 0.69 C 3.5 0.25 D 12.0 1.78 E 6.5 2.25 F 9.0 2.78 G 4.5 Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
77
Earliest Start (weeks) Earliest Finish (weeks)
Solved Problem 2.2 We need to calculate the earliest start, latest start, earliest finish, and latest finish times for each activity. Starting with activities A and B, we proceed from the beginning of the network and move to the end, calculating the earliest start and finish times. Activity Earliest Start (weeks) Earliest Finish (weeks) A = 4.0 B = 5.5 C 5.5 = 9.0 D 4.0 = 16.0 E 9.0 = 15.5 F = 14.5 G 15.5 = 20.0 Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
78
Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
Solved Problem 2.2 Based on expected times, the earliest finish date for the project is week 20, when activity G has been completed. Using that as a target date, we can work backward through the network, calculating the latest start and finish times Activity Latest Start (weeks) Latest Finish (weeks) G 15.5 20.0 F 6.5 E 9.0 D 8.0 C 5.5 B 0.0 A 4.0 Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
79
Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
Solved Problem 2.2 A 4.0 0.0 8.0 D 12.0 16.0 20.0 E 6.5 9.0 15.5 G 4.5 C 3.5 5.5 F 14.5 B Finish Start Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
80
Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
Solved Problem 2.2 Start (weeks) Finish (weeks) Activity Earliest Latest Slack Critical Path A 4.0 8.0 No B 0.0 5.5 Yes C 9.0 D 16.0 20.0 E 15.5 F 6.5 14.5 1.0 G Path Total Expected Time (weeks) Total Variance A–D = 16 = 2.78 A–E–G = 15 = 3.94 B–C–E–G = 20 = 3.88 B–F–G = 19 = 4.16 Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
81
Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
Solved Problem 2.2 The critical path is B–C–E–G with a total expected time of 20 weeks. However, path B–F–G is 19 weeks and has a large variance. We first calculate the z-value: z = = = 1.52 T – TE σ2 23 – 20 3.88 Using the Normal Distribution Appendix, we find the probability of completing the project in 23 weeks or less is Because the length of path B–F–G is close to that of the critical path and has a large variance, it might well become the critical path during the project Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall
82
Printed in the United States of America.
All rights reserved. No part of this publication may be reproduced, stored in a retrieval system, or transmitted, in any form or by any means, electronic, mechanical, photocopying, recording, or otherwise, without the prior written permission of the publisher. Printed in the United States of America. Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall