Presentation is loading. Please wait.

Presentation is loading. Please wait.

Copyright © 2009 PMI RiskSIGNovember 5-6, 2009 RiskSIG - Advancing the State of the Art A collaboration of the PMI, Rome Italy Chapter and the RiskSIG.

Similar presentations


Presentation on theme: "Copyright © 2009 PMI RiskSIGNovember 5-6, 2009 RiskSIG - Advancing the State of the Art A collaboration of the PMI, Rome Italy Chapter and the RiskSIG."— Presentation transcript:

1 Copyright © 2009 PMI RiskSIGNovember 5-6, 2009 RiskSIG - Advancing the State of the Art A collaboration of the PMI, Rome Italy Chapter and the RiskSIG “Project Risk Management – An International Perspective”

2 Slide 2November 5-6, 2009 Copyright © 2009 PMI RiskSIG Bayesian Networks: A Novel Approach For Modelling Uncertainty in Projects By: Vahid Khodakarami

3 Slide 3November 5-6, 2009 Copyright © 2009 PMI RiskSIG Outline: u What is missing in current PRM practice? u Bayesian Networks u Application of BNs in PRM u Models u Case study

4 Slide 4November 5-6, 2009 Copyright © 2009 PMI RiskSIG Conceptual steps in PRMP u Risk Identification âQualitative Analysis u Risk Analysis (Risk Measurement) âQuantitative Analysis u Risk Response (Mitigation)

5 Slide 5November 5-6, 2009 Copyright © 2009 PMI RiskSIG Project Scheduling Under uncertainty u (CPM) u PERT u Simulation u Critical chain

6 Slide 6November 5-6, 2009 Copyright © 2009 PMI RiskSIG What is missing? u Causality in project uncertainty u Estimation and Subjectivity u Unknown Risks (Common cause factors) u Trade-off between time, cost and performance u Dynamic Learning

7 Slide 7November 5-6, 2009 Copyright © 2009 PMI RiskSIG Bayesian Networks (BNs) u Graphical model âNodes (variables) âArcs (causality) u Probabilistic (Bayesian) inference

8 Slide 8November 5-6, 2009 Copyright © 2009 PMI RiskSIG Bayesian vs. Frequentist FrequentistBayesian VariablesRandomUncertain Probability Physical Property (Data) Degree of belief (Subjective) InferenceConfidence interval Bayes’ Theorem only feasible method for many practical problems

9 Slide 9November 5-6, 2009 Copyright © 2009 PMI RiskSIG Bayes’ Theorem u ‘A’ represents hypothesis and ‘B’ represents evidence. u P(A) is called ‘prior distribution’. u P(B/A) is called ’Likelihood function’. u P(A/B) is called ’Posterior distribution’.

10 Slide 10November 5-6, 2009 Copyright © 2009 PMI RiskSIG Constructing BN High 0.7 Low 0.3 On time 0.95 Late 0.05 Prior Probability Sub-contract On time Late Staff Experience High Low High Low No 0.99 0.8 0.7 0.02 Delay Yes 0.01 0.2 0.3 0.98 Conditional Probability

11 Slide 11November 5-6, 2009 Copyright © 2009 PMI RiskSIG Inference in BN (cause to effect) With no other information P(Delay)=0.14.4 Knowing the sub-contract is late P(Delay)=0.50.7

12 Slide 12November 5-6, 2009 Copyright © 2009 PMI RiskSIG Backward Propagation (effect to cause) Prior probability with no data (0.7,0.3) Posterior (learnt) probability (0.28,0.72)

13 Slide 13November 5-6, 2009 Copyright © 2009 PMI RiskSIG BNs Advantages u Rigorous method to make formal use of subjective data u Explicitly quantify uncertainty u Make predictions with incomplete data u Reason from effect to cause as well as from cause to effect u Update previous beliefs in the light of new data (learning) u Complex sensitivity analysis

14 Slide 14November 5-6, 2009 Copyright © 2009 PMI RiskSIG BNs Applications u Industrial âProcessor Fault Diagnosis - by Intel âAuxiliary Turbine Diagnosis - by GE âDiagnosis of space shuttle propulsion systems - by NASA/Rockwell âSituation assessment for nuclear power plant – NRC u Medical Diagnosis âInternal Medicine âPathology diagnosis - âBreast Cancer Manager u Commercial âSoftware troubleshooting and advice – MS-Office âFinancial Market Analysis âInformation Retrieval âSoftware Defect detection u Military âAutomatic Target Recognition – MITRE âAutonomous control of unmanned underwater vehicle - Lockheed Martin

15 Slide 15November 5-6, 2009 Copyright © 2009 PMI RiskSIG Bayesian CPM CPM Calculation

16 Slide 16November 5-6, 2009 Copyright © 2009 PMI RiskSIG BCPM Example

17 Slide 17November 5-6, 2009 Copyright © 2009 PMI RiskSIG Activity Duration

18 Slide 18November 5-6, 2009 Copyright © 2009 PMI RiskSIG Trade off

19 Slide 19November 5-6, 2009 Copyright © 2009 PMI RiskSIG Trade off (Prior vs. required resources )

20 Slide 20November 5-6, 2009 Copyright © 2009 PMI RiskSIG Known Risk

21 Slide 21November 5-6, 2009 Copyright © 2009 PMI RiskSIG Known Risk (Control)

22 Slide 22November 5-6, 2009 Copyright © 2009 PMI RiskSIG Known Risk (Impact)

23 Slide 23November 5-6, 2009 Copyright © 2009 PMI RiskSIG Known Risk (Response)

24 Slide 24November 5-6, 2009 Copyright © 2009 PMI RiskSIG Unknown Factors

25 Slide 25November 5-6, 2009 Copyright © 2009 PMI RiskSIG Unknown Factors (Learning)

26 Slide 26November 5-6, 2009 Copyright © 2009 PMI RiskSIG Learnt distribution

27 Slide 27November 5-6, 2009 Copyright © 2009 PMI RiskSIG Total Duration

28 Slide 28November 5-6, 2009 Copyright © 2009 PMI RiskSIG Case Study (construction Project)

29 Slide 29November 5-6, 2009 Copyright © 2009 PMI RiskSIG Case Study (Bayesian CPM)

30 Slide 30November 5-6, 2009 Copyright © 2009 PMI RiskSIG Case Study (predictive)

31 Slide 31November 5-6, 2009 Copyright © 2009 PMI RiskSIG Case Study (diagnostic)

32 Slide 32November 5-6, 2009 Copyright © 2009 PMI RiskSIG Case Study (learning)

33 Slide 33November 5-6, 2009 Copyright © 2009 PMI RiskSIG Summary u Current practice in modelling risk in project time management has serious limitations u BNs are particularly suitable for modelling uncertainty in project u The proposed models provide a new generation of project risk assessment tools that are better informed and hence, more valid

34 Slide 34November 5-6, 2009 Copyright © 2009 PMI RiskSIG Questions? Thank you for your attention


Download ppt "Copyright © 2009 PMI RiskSIGNovember 5-6, 2009 RiskSIG - Advancing the State of the Art A collaboration of the PMI, Rome Italy Chapter and the RiskSIG."

Similar presentations


Ads by Google