2 Core Financial information Year-end 2012
Total Assets $45B Gross Revenues $19.6b Gross Profit $5.8b EBITDA $6.76b Capex $5.57b Large reserve base & major production potential Source: KMG Bond Prospectus 2013

3 Kazakhstan: Strengthening Positions on the Global Energy Market
21.4 36 mn tons 2012 2025 Oil production by KazMunayGas 0.5 Total recoverable oil reserves bn tons of oil 11 7.2 production (mn tons) 2012 2025 44 oil and gas fields 65% of oil transportation 100% gas transportation Karachaganak 1.3 Total recoverable oil reserves bn tons of oil 24.2 37 production (mn tons) 2012 2025 Tengiz Kashagan start 36.7 production (mn tons) 2012 2025 79.2 108 mn tons 2012 2025 Oil Production in Kazakhstan 2 Total recoverable oil reserves bn tons of oil

4 Intensification of Exploration Efforts
797 bn KZT Financing of Exploration Efforts in the KazMunayGas group 823 1,414 mn tons 2012 2022 Dynamics of oil and condensate reserves of the KazMunayGas group By 2022 increase in the RESERVES of the KazMunayGas group to 1.4 bn tons is expected From 2017, the reserves growth is planned using geologic exploration works with application of leading-edge TECHNOLOGY 738 Prospecting and exploratory drilling costs bn KZT 50 3D seismic prospecting costs 9 2D seismic prospecting costs Leading-edge technology in exploration works: airborne magnetic surveying reservoir simulation basin simulation multifocusing Dynamics of KMG's oil and condensate reserves, mn tons: 2011 2012 (fact) 2012* (forecast) 2013* 2014* 2015* 2016* 2017* 2018* 2019* 2020* 2021* 2022*

5 Diversification and capacity expansion of export routes
Kazakhstan-China oil pipeline: EXPANSION of the oil pipeline on the Atyrau - Kenkiyak - Kumkol - Karakoin - Atasu - Alashankou sections (implementation: ) Kazakhstan-China gas pipeline: construction of the THIRD LINE (line С) (launch in 2016) Atyrau Kenkiyak Kumkol Atasu Alashankou Shymkent Taraz Khorgos Almaty TURKMENISTAN - UZBEKISTAN Beineu Bozoi Kyzylorda Line C Gas pipeline Kazakhstan-China Oil Pipeline Beineu-Bozoi-Shymkent Beineu-Bozoi-Shymkent gas pipeline: phased commissioning, incl. Section BEINEU – BOZOI (implementation: 2011 – 2015)

6 MAJOR MANUFACTURING PROGRAMME UNDERWAY /PLANNED
Atyrau refinery ( underway) Aromatics Production complex $1.098m Road Bitumen production $290m Deeper oil conversion complex $1.680m Shymkent Refinery reconstruction project Pavlodar Refinery upgrading project Petromedia Refinery upgrade ( completed) ADDING VALUE TO KAZAKHSTAN PRODUCTION & RAISING KAZAKH CONTENT