LNG in North America Tommy Stone – Vice President, Operations & Engineering Trunkline LNG Company, LLC – Lake Charles, LA Tommy Stone – Vice President, Operations & Engineering Trunkline LNG Company, LLC – Lake Charles, LA
2
2 0105-005 LNG Properties – A Means of Transportation Liquefied Natural Gas (LNG) Temperature –Minus 260 degrees Fahrenheit Volume reduction of 620 to 1 620 Ships of Gas = 1 Ship of LNG Composition –Methane (85 – 98%) –Ethane (2 – 12%) –Propane (0 – 4%) –Butane (0 – 1%) –Others (0 – 1%) LNG is nontoxic Odorless, colorless Vapor is natural gas – lighter than air as it warms Stored near atmospheric pressure (± 2 psig)
3
3 0105-005 Government and Academics Agree, LNG is the Solution FERC changes U.S. policy towards LNG terminals “The public interest is served through encouraging gas-on-gas competition by introducing new imported supplies of natural gas which will be accessible to all willing purchasers,” - FERC Order 12-18-02 “in a short time the commission had made changes to federal policies dealing with LNG licensing and seen a response from businesses interested in investing in terminals, which will contribute to alleviation of shortages of natural gas in the U.S.,” - Pat Wood III, FERC Chairman 09-10-03 Energy Market Research LNG…will set the price of gas in North America for the foreseeable future… - Michael Economides, University of Houston
4
4 0105-005 Rockies Deep Gulf $3.60 - $5.85 Arctic Gas Supply tightening –Demand growth –Traditional basins in decline New supply must come from new areas –But will only come at a price that supports development LNG has the opportunity to gain market share LNG Nation Needs New Sources of Supply
5
5 0105-005 LNG Value Chain, Exploration & Production $0.6 B$2.0 B $1.5 B 1 Bcf/d Scenario $6.1 B $.50 –.75$.60 – 1.60$1.25 – 1.50$1.25 – 2.00 Per Unit $/Mcf $3.60 – 5.85 Regasification Shipping* Liquefaction Exploration & Production TOTAL Reserves9 Tcf Scope$0.05B Initial drilling $0.05B Develop- ment $1.4B Trains required 2 Cost per train $1.0B Distance12,000 nm Rd. Trip Time 30 days Ships Required 12 Cost per ship $0.17B Port $0.14B Storage $0.16B Vaporization.20B Engineering & Other.10B *Shipping: West Africa to U.S. Gulf Coast. % of Total 9%33% 25%100%
6
6 0105-005 Proven World Natural Gas Reserves Source:BP Statistical Review of World Energy, 2006 \\ ~ 4.1% of World Reserves
7
7 0105-005 LNG Value Chain, Liquefaction $0.6 B$2.0 B $1.5 B 1 Bcf/d Scenario $6.1 B $.50 –.75$.60 – 1.60$1.25 – 1.50$1.25 – 2.00 Per Unit $/Mcf $3.60 – 5.85 Regasification Shipping* Liquefaction Exploration & Production TOTAL Reserves9 Tcf Scope$0.05B Initial drilling $0.05B Develop- ment $1.4B Trains required 2 Cost per train $1.0B Distance12,000 nm Rd. Trip Time 30 days Ships Required 12 Cost per ship $0.17B Port $0.14B Storage $0.16B Vaporization.20B Engineering & Other.10B *Shipping: West Africa to U.S. Gulf Coast. % of Total 9%33% 25%100%
8
8 0105-005 Indonesia Algeria Malaysia Qatar Trinidad Nigeria Australia Oman Brunei Abu Dhabi USA Libya Egypt Iran Bolivia Yemen Russia Venezuela Angola Norway Peru Eq. Guinea Brazil Source:G.I.I.G.N.L, Liquefaction Capacity is Large and Will Continue to Grow
9
9 0105-005 Res./Liq. (yrs) Growth Potential in Atlantic Basin Supply 500 1000 1500 2000 2500 Atlantic BasinMiddle EastPacific Basin Tcf Reserves 0 2 4 6 8 10 Bcf/d Liquefaction Tcf Reserves Liquefaction 1015 9.6 2,546 5.6 527 11.5 Atlantic Basin 2901,246126 Source:BP Statistical Review, 2006 & G.I.I.G.N.L. 3000 12
10
10 0105-005 Abundant LNG Supply Nigeria Angola Venezuela Trinidad Algeria Libya Norway Middle East Egypt Equatorial Guinea Middle East
11
11 0105-005 LNG Value Chain, Shipping $0.6 B$2.0 B $1.5 B 1 Bcf/d Scenario $6.1 B $.50 –.75$.60 – 1.60$1.25 – 1.50$1.25 – 2.00 Per Unit $/Mcf $3.60 – 5.85 Regasification Shipping* Liquefaction Exploration & Production TOTAL Reserves9 Tcf Scope$0.05B Initial drilling $0.05B Develop- ment $1.4B Trains required 2 Cost per train $1.0B Distance12,000 nm Rd. Trip Time 30 days Ships Required 12 Cost per ship $0.20B Port $0.14B Storage $0.16B Vaporization.20B Engineering & Other.10B *Shipping: West Africa to U.S. Gulf Coast. % of Total 9%33% 25%100%
12
12 0105-005 LNG FLEET HISTORY CAPACITY
13
13 0105-005 LNG VESSEL COST
14
14 0105-005 LNG Vessel Fleet 228 Vessels - World Fleet 136 Vessels On Book (New Builds) –Deliveries Through 2010 85% Membrane Containment 15% Moss (Spherical) –Avg. 10/12 New Orders Each Year
15
15 0105-005 LNG SHIP TYPES Membrane Tank Design MossMoss
16
16 0105-005 LNG/C – Physical Size Length: 950 feet (3 football fields) Width: 150’ Draft: 37’ (Underwater) –2615 m 2 (28,000 sq/ft.) Air Draft: 195’ (Above Water) –6,600 m 2 (71,000 sq/ft) Displacement: 110,000 Metric Tons Two Tractor Tugs Required for Berthing
17
17 0105-005 VESSEL TRANSIT TO TLNG 6-8 Hour Transit – Approx. 52 Miles One Way Traffic for Deep Draft Vessels 24 Hour Transits Lake Charles Pilots Corp of Engineers Project Project Depth = 40 feet Outer Bar = 800 ft. Width Inner bar = 400 ft. Width
18
18 0105-005 LNG Value Chain, Regasification $0.6 B$2.0 B $1.5 B 1 Bcf/d Scenario $6.1 B $.50 –.75$.60 – 1.60$1.25 – 1.50$1.25 – 2.00 Per Unit $/Mcf $3.60 – 5.85 Regasification Shipping* Liquefaction Exploration & Production TOTAL Reserves9 Tcf Scope$0.05B Initial drilling $0.05B Develop- ment $1.4B Trains required 2 Cost per train $1.0B Distance12,000 nm Rd. Trip Time 30 days Ships Required 12 Cost per ship $0.17B Port $0.14B Storage $0.16B Vaporization.20B Engineering & Other.10B *Shipping: West Africa to U.S. Gulf Coast. % of Total 9%33% 25%100%
19
19 0105-005 North America France Spain North America France Spain Italy North America becomes much more significant in the global LNG community Atlantic Basin Regasification Capacity Growing
20
20 0105-005 LNG Imports Relative to U.S. Demand Quotes from EIA Energy Outlook 2006 “Imports are expected to play an important role in U.S. natural gas markets, accounting for 21 percent of total U.S. natural gas consumption in 2030” “LNG imports are projected to grow from 650 billion cubic feet in 2004 to 4.4 trillion cubic feet in 2030, with net LNG imports rising from 17 percent of net imports in 2004 to 78 percent in 2030” “The most rapid growth in LNG import capacity will occur over the next decade, with peak annual capacity increasing from 1.4 trillion cubic feet in 2004 to 4.9 trillion cubic feet in 2015” Source: EIA
21
21 0105-005 Distrigas, Tractebel Everett, MA CurrentExpanded Sendout: (MMcf/d) 715n/a Storage: (Bcf) 3.4n/a Cove Point LNG, Dominion Cove Point, MD CurrentExpanded Sendout: (MMcf/d) 1,0001,800 Storage: (Bcf) 7.814.5 Elba Island, El Paso Savanna, GA CurrentExpanded Sendout: (MMcf/d) 8231,800 Storage: (Bcf) 7.4515.85 Trunkline LNG, Panhandle Energy Lake Charles, LA Sustained Peak Sendout: (MMcf/d) 1,8002,100 Storage: (Bcf) 9.09.0 Summary Total Existing U.S. Regasification CurrentExpanded Sendout: (MMcf/d) 4,3886,115 Storage: (Bcf) 27.6542.75 TLNG Currently Offers Greatest Flexibility of All Domestic Terminals
22
22 0105-005 22 0105-005
23
23 0105-005 LNG in U.S. Gulf Coast Region U.S. Gulf region 45-55% of U.S. supply Sufficient pipeline infrastructure Blending and processing allow a broader range of gas quality Low cost storage Deepwater ports Supportive state & local govt’s Reduced NIMBY issues *Source: US Department of Energy 0105-005
24
24 0105-005 Texas/Louisiana LNG Projects Approved by FERC or MARAD/USCG Proposed to FERC Approved by FERC or MARAD/USCG Proposed to FERC Sabine Pass LNG In-service date: 2008-9 Sendout: 2.6 – 4.0 Bcf/d Developer: Cheniere Capacity Holder: Total & ChevronTexaco Sabine Pass LNG In-service date: 2008-9 Sendout: 2.6 – 4.0 Bcf/d Developer: Cheniere Capacity Holder: Total & ChevronTexaco *Freeport LNG Development is composed of a General Partnership which has management control, but zero economic interest (Michael Smith 50% and ConocoPhillips 50%) and Limited Partners which have zero management interest, but have economic interest (Michael Smith 60%, Cheniere 30% and Contango 10%). Creole Trail In-service date: 2011 Sendout: 3.0 Bcf/d Developer: Cheniere Capacity Holder: TBD Creole Trail In-service date: 2011 Sendout: 3.0 Bcf/d Developer: Cheniere Capacity Holder: TBD Energy Bridge In-service date: 3/2005 Sendout: 0.5 Bcf/d Developer: Excelerate Energy Energy Bridge In-service date: 3/2005 Sendout: 0.5 Bcf/d Developer: Excelerate Energy Freeport LNG In-service date: 2008 Sendout:1.5 Bcf/d (expand to 3.0 Bcf/d) Developer: Freeport LNG Dev.* Capacity Holder: Dow & ConocoPhillips & Mitsubishi Freeport LNG In-service date: 2008 Sendout:1.5 Bcf/d (expand to 3.0 Bcf/d) Developer: Freeport LNG Dev.* Capacity Holder: Dow & ConocoPhillips & Mitsubishi Golden Pass In-service date: 2009 Sendout: 2 Bcf/d Developer: ExxonMobil Golden Pass In-service date: 2009 Sendout: 2 Bcf/d Developer: ExxonMobil Cameron LNG In-service date: 2008 Sendout: 1.5 – 2.65 Bcf/d Developer: Sempra Capacity Holder: ENI & Merrill Lynch Cameron LNG In-service date: 2008 Sendout: 1.5 – 2.65 Bcf/d Developer: Sempra Capacity Holder: ENI & Merrill Lynch Trunkline LNG In-service date: 2006 (expansions) Sendout: 1.8 Bcf/d Developer: Southern Union Capacity Holder: BG LNG Trunkline LNG In-service date: 2006 (expansions) Sendout: 1.8 Bcf/d Developer: Southern Union Capacity Holder: BG LNG Corpus Christi Projects (3) In-service dates: 2009-10 Sendout: 4.7 Bcf/d (total) Developers: 4Gas, Occidental Corpus Christi Projects (3) In-service dates: 2009-10 Sendout: 4.7 Bcf/d (total) Developers: 4Gas, Occidental 24 0105-005
25
25 0105-005 Trunkline LNG Activity (2Q 2007) Everett 21% Lake Charles 40% Lake Charles 40% Elba Island 19% Elba Island 19% Cove Point 19% Cove Point 19% LNG Imports by Terminal Jan – June 2007 Total = 464.0 Bcf *Source: US Department of Energy Shell 5% BG LNG 59% BG LNG 59% LNG Imports by Company Jan – June 2007 3.9% of U.S. Gas Demand (2 Qtr) Suez LNG 21% Statoil 6% BP 7% Excelerate 2% Excelerate 1%
26
26 0105-005 Trunkline LNG Expansion Facilities Phase I –Construction Completed April 2006 –Double sendout capacity to 1.2 Bcf/d Peaking of 1.3 Bcf/d –Increase storage capacity to 9.0 Bcf Phase II –Construction Complete July 2006 –Increase sendout capacity to 1.8 Bcf/d Peaking of 2.1 Bcf/d Trunkline Gas Company Loop –Construction Complete –22 miles (new construction) of 36” pipeline loop –Several (6+) new or expanded delivery points
27
27 0105-005 Beeville Edna Cypress Kountze Longville Centerville Patterson Terrebonne Lake Charles LNG 2006MMcf/d TGC Receipts:2,494 TGC Mainline Capacity:1,500 Field Zone Supply Overage:994 2006MMcf/d TGC Receipts:2,494 TGC Mainline Capacity:1,500 Field Zone Supply Overage:994 1,500MMcf/d Mainline Capacity TLNG & TGC Field Zone Supply with LNG Expansions Sea Robin Trunkline LNG Supply 2003 - 2006 (avg):525 MMcf/d 2007+ (est):1,500 +MMcf/d Trunkline LNG Supply 2003 - 2006 (avg):525 MMcf/d 2007+ (est):1,500 +MMcf/d
28
28 0105-005 LNG Value Chain – Total Project $0.6 B$2.0 B $1.5 B 1 Bcf/d Scenario $6.1 B $.50 –.75$.60 – 1.60$1.25 – 1.50$1.25 – 2.00 Per Unit $/Mcf $3.60 – 5.85 Regasification Shipping* Liquefaction Exploration & Production TOTAL Reserves9 Tcf Scope$0.05B Initial drilling $0.05B Develop- ment $1.4B Trains required 2 Cost per train $1.0B Distance12,000 nm Rd. Trip Time 30 days Ships Required 12 Cost per ship $0.17B Port $0.14B Storage $0.16B Vaporization.20B Engineering & Other.10B *Shipping: West Africa to U.S. Gulf Coast. % of Total 9%33% 25%100%
29
29 0105-005 TRUNKLINE LNG – LAKE CHARLES, LOUISIANA
30
30 0105-005 REGASIFICATION PROCESS GAS LIQUID LNGSTORAGETANKS PIPELINECOMPRESSOR VAPORIZERS DESUPERHEATER BOIL-OFFCOMPRESSOR PIPELINE RECONDENSER
31
31 0105-005 Trunkline LNG - Infrastructure Enhancement Project (IEP)
32
32 0105-005 Conclusion “One of the benefits of LNG is that new supplies could enter the market within the next few years, well ahead of other opportunities, and begin to offer relief to American consumers.” - Center for LNG
33
Questions & Answers