Lafayette Parish School Board Board Workshop * October 14, 2010 REVISED for October 20, 2010 Board Meeting
2
AGENDA ITEM #1 REVIEW OF PROPOSED SITES FOR THIBODAUX CAREER & TECHNICAL HIGH SCHOOL - GUIDRY/LANDRY/LILLY/LEMOINE Information will be presented to the Board relating to the sites that will be proposed for Thibodaux Career & Technical High School. Lafayette Parish School System – Board Workshop – October 14, 2010
3
Proposed Location for Thibodaux Career & Technical High School Lafayette Parish Address: 3300 Ambassador Caffery Parkway (Former site of “Super Kmart”)
4
Note: Road frontages – based on dimensions used in appraisal report Schedule 1Proposed Site #1 3300 Ambassador Caffery Parkway
5
NOT a proposed site * Schedule 2 – * REVISED from 10/14 Workshop 1-a Tract 1: 5.92 acres on Ridge Road 1-b Tract 2: 11.39 acres on Ridge Road 1-c Tract 3: 19.00 acres on Ridge Road Proposed sites 1-a, 1-b and 1-c * Period of Offer Extended
6
Schedule 3 Proposed site 1-d Quint M Partnership 58.55 Acres on Ridge Road
7
AGENDA ITEM #2 REVIEW OF DUE DILIGENCE WORK FOR PROPOSED SITES FOR THIBODAUX CAREER & TECHNICAL HIGH SCHOOL – GUIDRY/LANDRY/LILLY/LEMOINE Information will be presented to the Board which will summarize the due diligence work that has been performed or is in the process of being completed. Lafayette Parish School System – Board Workshop – October 14, 2010
9
Schedule 4 Pg 1 of 3
10
Schedule 4 Pg 2 of 3
11
Schedule 4 Pg 3 of 3
12
Schedule 5 Pg 1 of 2
13
Schedule 5 Pg 2 of 2
14
Schedule 6 Pg 1 of 2
15
Schedule 6 Pg 2 of 2
16
Schedule 7 Pg 1 of 2
17
Schedule 7 Pg 2 of 2
18
Schedule 8 Pg 1 of 3
19
Schedule 8 Pg 2 of 3
20
Schedule 8 Pg 3 of 3
21
Schedule 9 Schedule 9 – REVISED from 10/14 Workshop
22
Schedule 10
23
AGENDA ITEM #3 REVIEW OF PROJECTED TIMELINE AND PROJECTED COSTS FOR PHASE-IN OF CONSTRUCTION FOR THIBODAUX CAREER & TECHNICAL HIGH SCHOOL- GUIDRY/LANDRY/LILLY/LEMOINE Information will be presented to the Board which will include a projected timeline for the phase-in of construction for Thibodaux Career & Technical High School. Projected costs for this project will also be presented. Lafayette Parish School System – Board Workshop – October 14, 2010
24
Projected timeline for the phase in of construction and projected costs will now be presented by:
25
Information will be presented to the Board which will include options for financing Thibodaux Career & Technical High School. Lafayette Parish School System – Board Workshop – October 14, 2010
26
Schedule 11 – REVISED from 10/14 Workshop
27
Financing Options will now be presented by our bond attorney: Mr. Jerry R. Osborne of Foley & Judell, L.L.P. Attorneys and Counsellors at Law One Canal Place, Suite 2600 365 Canal Street New Orleans, Louisiana 70130-1138
28
This concludes our presentation. Thank you for your interest in our school system.