Detector Cooling Project Thermosiphon Project Status Report
Michele Battistin EN/CV/Detector Cooling 14/12/2011 M. Battistin
2
Agenda Basic schematics Review process Integration Main Components
Risk Analysis Project Management Cost tracking Planning Resources 14/12/2011 M. Battistin
3
Basics schematics R23 C3F8 H2O Real P&I EDMS 1101188 R404a 14/12/2011
C6F14 brine circuit Normal operation -65°C to -70°C Warm operation -15°C to -20°C liquid tank Water condenser Normal operation evap. Cascade condenser R404a R23 Surface USA15 cavern C3F8 H2O Warm operation evap. Air condenser UX15 cavern Real P&I EDMS ATLAS ID Detector 14/12/2011 M. Battistin
4
Reviews process 14/12/2011 M. Battistin
1st Thermosiphon review: 6th July 2009 Pre-design and general lines of the project. Indico agenda and documents here. 2nd Thermosiphon review: 1st October 2009 Detailed design for the 2 kW Thermosiphon, mini-thermosiphon and blends. Indico agenda and documents here. 3rd Thermosiphon review: 28th May 2010 Advancement status of Thermosiphon project, oil free centrifugal compressors and sonar sensor. 4th Thermosiphon review: 19th of November 2010 Project Readiness Review. 5th Thermosiphon review: 20th of October 2011 Project advancement. 14/12/2011 M. Battistin
5
Integration: Point 1 overview
Condenser Location Chiller and Brine Station Location SX1 SDX1 SH1 SUX1 PX15 USA15 14/12/2011 M. Battistin
6
Thermosyphon Piping and By-pass components
SDX1 Piping connection to condenser SDX1 PX15 Pipe route to PX15 pit 72m vertical pipe line Thermosyphon by-pass By-pass integration on platform USA15 Components location 14/12/2011 M. Battistin
7
Water and Brine Circuits
14/12/2011 M. Battistin
8
Integration documentation status
Approval Status Condenser integration EDMS v1 Under Approval C3F8 pipe integration EDMS v1 Approved Chiller & Brine Pumps Integration EDMS v1 Electrical Requirements EDMS v1 Electrical Cabinet Integration EDMS v1 USA15 Integration EDMS v1 Water Circuit Integration EDMS v1 Brine Piping Integration EDMS v1 Brine piping calculation specifications EDMS v1 14/12/2011 M. Battistin
9
Chiller Construction Schedule
Chiller: -70°C Chiller Construction Schedule Technical Specifications (Done) Market Survey (Done) Invitation to Tender (Done) Purchase Order (Done) Chiller Construction (On going) Contract started: 10% Completed (September 2011) Design phase completed 20% Completed (October 2011) Construction of the Chiller 30% On going (December 2011) Delivery and Installation at CERN 30% Planned to January 2012 Commissioning at CERN 10% Planned to June 2012 14/12/2011 M. Battistin
10
Thermosyphon Condenser
Condenser Construction Schedule Technical Specifications (Done) Request for Quotation (Done) Purchase Order (Done) Condenser Construction (On going) Contract start: October 2011 Detailed design: November 2011 Purchasing of material: January 2012 Condenser construction: March 2012 Final pressure tests: May 2012 Insulation of the condenser: May 2012 Delivery at CERN: June 2012 14/12/2011 M. Battistin
11
Hydraulic Components Selection
All project working documents on SharePoint Part list (reference #, order status, cost, specs, etc) Components Selection Criteria Fluids: Fluorocarbons C2F6, C3F8, C6F14 Pressure: PN16, PN40, DESP 97/23EC approval Temperature: 20°C to -70°C. Cryo extension Material: Stainless steel, flat metallic gasket, no fluorinated plastic Leak tightness: General 10-7 mbar.l/s Cleaning: every part degreased, driers, 1µm filter Safety: Twin relief valves with 3 ways valve, Deported sensors, Double switches on valves EDMS 14/12/2011 M. Battistin
12
Electrical Installed Power
Surface – SX1 Underground – USA15 14/12/2011 M. Battistin
13
Risk Analysis 1. Usage limits
Operating phases and procedures (2kW Thermosiphon) Control system (overall architecture) System users (accesses control) 2. Time limits (continues operation) 3. Space limits (Point 1, USA15, B3184 roof) 4. Other limits (properties of cooling fluids) Determination of the system limits Hazard identification – identifying the hazards and environmental aspects occurring in normal and exceptional conditions Risk estimation Risk evaluation 14/12/2011 M. Battistin
14
(New version with updated P&ID in work)
Risk Analyses Considered: 240 hazards 202 hazardous events 76 individual components in 7 groups 98 risk reduction proposals mechanical, electrical and control failures included EDMS document under approval EDMS (New version with updated P&ID in work) Medium [A3, A4, B2, B3, C1, C2, D1] Unacceptable risk: actions are necessary to reduce the risk. 14/12/2011 M. Battistin
15
Cost and Planning – Earned Value Management
Responsibility and Resources Matrix Project Breakdown Structure Conceptual design report Definition Project breakdown structure Equipment coding convention PBS Work breakdown structure List of working units WBS & WU’s Resource responsibility matrix RRM Work units dictionary WU Planning Project coordination schedule 14/12/2011 M. Battistin
16
Cost Tracking Cost rise from 2010.
Last budget presented to ATLAS management on 08/2011. Chiller N2 is not accounted. Cost are constantly tracked on EVM. The project has negative cost variance The project has negative schedule variance 14/12/2011 M. Battistin
17
Planning Extended Technical Stop interference 14/12/2011 M. Battistin
Time Autumn 2011 Winter 2011/2012 Spring 2012 Summer 2012 Autumn 2012 Winter 2012/2013 Design and integration Complete detailed design and integration Chiller system Manufacture Supply and installation Brine circuit Integration Tendering Installation connection Tank/condenser Contract signature C3F8 piping Design and Supports installation Installation of the pipes By-pass Detailed design Purchase of material Construction USA15 installation Instrumentation and control Functional analysis Purchase of hardware Programming Program tuning Electricity and Pneumatic installations Study the requirements Cupboards construction and installation Commissioning Tests with by-pass Tests with detector Extended Technical Stop interference 14/12/2011 M. Battistin
18
Conclusions The TS detailed design is well advanced
The equipment integration is still an important open issue. We shall start and operate the 2 kW to obtain insight for the functional analysis. Chiller construction is under-control. Condenser order has been sent. Support Piping installation is going to start In general the project is late and needs extra-resources to get the target date (Dec 2012): one Catia draftsman for 2 week to finalize 3D integration. one member of ATLAS ID collaboration will be welcome to join the team. a polish technician team for the assembly of the hydraulic part. resource to develop the PVSS/UNICOS control system shall be guaranteed. A workshop shall still be identified to give space and tools or the assembly! 14/12/2011 M. Battistin