System Events
3
3 March 24, 2012 @ 15:37 – Alberta Separation March 30, 2012 @ 10:20 – 1,600 MW generation loss in WAPA CM, including both Laramie River units March 30, 2012 @ 16:05 – 952 MW generation loss at Grand Coulee April 6, 2012 @ 9:38 – AC RAS event, drop about 1,400 MW of generation April 20, 2012 @ 15:37 – AC RAS event, drop 1,643 MW of generation Summary of WECC Events
4
Alberta Separation
8
Frequency Response Summary Dot size is proportional to size of generation drop Blue = nadir, Red = settle