LISD Board of Trustees Construction Committee Meeting Tuesday, December 11, 2001
2
Farias Elementary School Construction Committee Meeting Tuesday, December 11, 2001
3
THIS VIEW IS LOOKING NORTH WEST AT THE BUILDING PAD. PAD IS WET DUE TO RECENT RAINS.
4
THIS VIEW IS LOOKING NORTHEAST AT THE BUILDING PAD. SURVEYORS ARE SETTING THE CORNER PINS FOR THE BUILDING.
5
Santa Maria Elementary School Construction Committee Meeting Tuesday, December 11, 2001
6
PLUMBING SUBCONTRACTOR TRENCHING FOR THE INSTALLATION OF PLUMBING LINES.
7
THE PLUMBING LINES PREFABRICATED ON SITE FOR INSTALLATION IN THE PLUMBING TRENCH.
8
PREPARATION OF THE BUILDING PAD AT THE BUILDING.
9
Dovalina Elementary School Construction Committee Meeting Tuesday, December 11, 2001
10
VIEW LOOKING NORTH WEST AT THE CONCRETE FOUNDATION. MASONRY BLOCK WALLS BEING CONSTRUCTED.
12
SOUTHEAST VIEW OF THE COMPLETED FOUNDATION SYSTEM.
14
Project:Christen Middle School Architect: Sepulveda Associates Architects, Inc. Status: Design Development Budget: $7,193,380. Timeline: Start of Final Design Phase: Jan 2002 Present Final Contract Dwgs: Mar 2002 Completion of Construction: Dec 2003
15
Project: Martin High School Architect: Sepulveda Associates Architects, Inc. Status: Design Development Budget: $7,823,946. Timeline: Start of Final Design Phase: Dec 2001 Present Final Contract Dwgs: Feb 2002 Completion of Construction: May 2003
16
Ochoa/T. Sanchez Elementary School Construction Committee Meeting Tuesday, December 11, 2001
17
THIS VIEW IS LOOKING SOUTH EAST AT THE BUILDING PAD.
20
EXISTING CITY SEWER LINE BEING REROUTED. NEW SEWER LINE BEING INSTALLED.
21
Project: K.Tarver Elementary School Architect: Cavazos & Associates Architects Status: Design Development Budget: $ 4,606,191.00 Dlls. Timeline: Start of Final Design Phase: Feb 2002 Present Final Contract Dwgs: April 2002 Completion of Construction: June 2003
22
C.L. Milton Elementary School Construction Committee Meeting Tuesday, December 11, 2001
23
THIS VIEW IS OF THE PAD PREPARATION FOR THE NEW PORTABLE CLASSROOMS. THIS IS A SOUTH EAST VIEW. THIS VIEW IS OF THE PAD PREPARATION FOR THE NEW PORTABLE CLASSROOMS. THIS IS A SOUTH EAST VIEW.
24
NORTH EAST VIEW OF THE PAD PREPARATION FOR THE PORTABLE BUILDINGS.
25
Project: J.C. Martin Elementary School Architect: Ashley Humphries & Sanchez Architects Status: Preliminary Design Budget: $1,997,044. Timeline: Start Design Development : Feb 2002 Start of Final Design Phase: April 2002 Present Final Contract Dwgs: June 2002 Completion of Construction: Aug 2003
26
Project: Lamar Middle School Architect: Cavazos & Associates Architects Status: Final Design Phase Budget: $ 7,358,620. Timeline: Start of Final Design Phase: Aug 2001 Present Final Contract Dwgs: Feb 2002 Completion of Construction: June 2003
27
J.W. NIXON HIGH SCHOOL Construction Committee Meeting Tuesday, December 11, 2001
28
THIS IS A VIEW LOOKING WEST AT THE CANOPY ON THE SOUTH END OF THE PORTABLE BUILDING.
29
THIS VIEW IS LOOKING NORTH ALONG THE NEW SIDE WALK FOR THE STUDENTS.
30
THIS VIEW SHOWS THE FENCING ON TOP OF THE EXISTING BLOCK WALL.
31
MAIN PATIO DECK. MAIN ENTRANCE TO BUILDINGS.
32
Project: Daiches Elementary School Architect: Turner Hickey & Associates, Inc. Status: Design Development Budget: $5,191,225. Timeline: Start of Final Design Phase: Dec 2001 Present Final Contract Dwgs: March 2002 Completion of Construction: April 2003
33
Project: Heights Elementary School Architect: Pending Status: Pending Budget: Pending Timeline: Pending
34
Project: Santo Nino Elementary School Architect: Frank Architects Inc. Status: Final Design Phase Budget: $5,191,225. Timeline: Start of Final Design Phase: Sept. 2001 Present Final Contract Dwgs: Jan 2002 Completion of Construction: March 03
35
Project: Kawas Elementary School Architect: Ashley Humphries & Sanchez Architects Status: Construction Documents Phase Budget: $4,211,386. Timeline: Start of Final Design Phase: July 2001 Present Final Contract Dwgs: Oct 2001 Completion of Construction: Dec 2002
36
Project: H.B. Zachry Elementary School Architect: Design Group International, Inc. Status: Construction Documents Phase Budget: $1,456,725. Timeline: Start of Final Design Phase: Oct 2001 Present Final Contract Dwgs: Dec 2001 Completion of Construction: Dec 2002
37
Project: H. Ligarde Elementary School Architect: Ashley Humphries & Sanchez Architects Status: Construction Documents Phase Budget: $3,388,153. Timeline: Start of Final Design Phase: Oct 2001 Present Final Contract Dwgs: Dec 2001 Completion of Construction: Dec 2002
38
Project: Cigarroa Middle School Architect: Ashley Humphries & Sanchez Architects Status: Construction Documents Phase Budget: $3,314,867. Timeline: Start of Final Design Phase: July 2001 Present Final Contract Dwgs: Dec 2001 Completion of Construction: June 2003
39
Project: Cigarroa High School Architect: Ashley Humphries & Sanchez Architects Status: Construction Documents Phase Budget: $8,168,516. Timeline: Start of Final Design Phase: July 2001 Present Final Contract Dwgs: Dec 2001 Completion of Construction: June 2003