Presentation is loading. Please wait.

Presentation is loading. Please wait.

October 8, 2008 Spokane, WA Doug Walters, P.E. King County DOT

Similar presentations


Presentation on theme: "October 8, 2008 Spokane, WA Doug Walters, P.E. King County DOT"— Presentation transcript:

1 October 8, 2008 Spokane, WA Doug Walters, P.E. King County DOT
Sunday Creek Bridge Replacement Utilizing Geosynthetic Reinforced Soil (GRS) Abutments October 8, 2008 Spokane, WA Doug Walters, P.E. King County DOT

2 Project Location

3 Existing Log Stringer Bridge

4 Bridge Deck

5 Typical Bridge Traffic Prior to Load Restrictions

6 Deficiencies Structural Environmental
Timber cribbing abutments & log stringers damaged Minor scour 1997- Placed temporary shoring load limit of 3 tons Environmental Cited by the WA Department of Fish and Wildlife Temporary shoring within stream channel

7 West abutment temporary shoring
I-Beam on Ecology Blocks

8 East Abutment Temporary Shoring
Shoring Support

9 Typical rot on log stringers

10 Superstructure: Prefabricated Steel Truss

11 Superstructure Selection
Hydraulic Opening Above 100 year flood elevation Changing road grade additional environmental permitting Narrow Haul Road

12 Superstructure: Prefabricated Steel Truss
3ft clear space 12

13 Foundation Considerations
Borings Alternating layers of medium dense alluvial gravel, sand, and silt Abutment Foundation Shallow foundation Base of foundation below stream’s thalwag elevation Sheet Pile Cutoff Walls Allow dry construction Provide additional scour protection

14 GRS Abutment Selection
Constructability Avoid long concrete haul Not weather dependent Reduced time of construction Cost Savings Materials General labor Standard equipment Environmental No concrete placement

15 GRS Abutment Design Outline
King County preliminary GRS abutment NCHRP Report 556 “Design and construction of GRS abutments” Mike Adams (FHWA) reviewed & refined design Provided GRS design detail with layout continue to provide evaluation, design, and construction support

16 BRIDGE LAYOUT 22 ft 104 ft PLAN 14 ft 25 ft

17 GRS ABUTMENT DETAIL FINISHED GRADE LINE

18 CMU Block Schedule 36 ft 23 ft 5 ft 9 ft 11 ft 11 ft

19 Tasks to be completed Finalize Design Bid January 2009
Construction June 2009

20 THANK YOU! Question?


Download ppt "October 8, 2008 Spokane, WA Doug Walters, P.E. King County DOT"

Similar presentations


Ads by Google