Massachusetts Avenue Roadway Improvements Board of Selectmen’s Meeting July 13, 2015 TOWN OF LEXINGTON
2
Project Goals Improve Safety & Mobility Improve Bicycle, Pedestrian and Transit Accommodations and Accessibility Improve the existing infrastructure TOWN OF LEXINGTON
3
Project History & Public Outreach November 2012 – Public Workshop/Meeting Fall/Winter 2012 – Discussions with Town Boards and Committees February 2013 – Third Public Meeting March 2015 – Historic Districts Commission May 2015 – MassDOT Design Public Hearing July 2015 – Board of Selectmen’s Meeting TOWN OF LEXINGTON
4
Pleasant Street – Existing Conditions Project in General TOWN OF LEXINGTON
5
Pleasant Street – 1 st Roundabout Concept Project in General TOWN OF LEXINGTON
6
Pleasant Street – 2 nd Roundabout Concept Project in General TOWN OF LEXINGTON
7
Pleasant Street – Roundabout ROW Impacts Project in General TOWN OF LEXINGTON
8
Pleasant Street Signal Concept Project in General TOWN OF LEXINGTON
9
Marrett Road – Existing Conditions Project in General TOWN OF LEXINGTON
10
Marrett Road Signal Concept Project in General TOWN OF LEXINGTON
11
Marrett Road without Signal Concept
12
Questions TOWN OF LEXINGTON